- 09:01, 16 June 2023 diff hist +163 Phase V - Construction →Task No. 19 - Prepare Revisions/As-Built Plans current
- 08:57, 16 June 2023 diff hist +49 N File:V-19c Pavement Marking Project Data Sheet.docx Pavement Marking Project Data Sheet current
- 08:56, 16 June 2023 diff hist +71 Phase V - Construction →Task No. 19 - Prepare Revisions/As-Built Plans
- 14:59, 1 June 2023 diff hist 0 Approved Materials - Erosion and Sediment Control →Erosion Control Blanket & Turf Reinforcement Mat current
- 12:22, 1 June 2023 diff hist −62 Main Page →Special Pages current
- 12:19, 1 June 2023 diff hist +136 Main Page →Special Pages
- 08:43, 1 June 2023 diff hist +26 N File:159 Metcalf to Nall owners.xls mailing list current
- 10:22, 31 May 2023 diff hist +40 Phase IV - Pre-Construction →Task No. 1 - Complete Plans, Specifications and Estimate
- 10:21, 31 May 2023 diff hist −55 Phase III - Final Design →Task No. 3 - Complete Environmental Process
- 10:19, 31 May 2023 diff hist −58 Phase III - Final Design →Task No. 3 - Complete Environmental Process
- 10:07, 31 May 2023 diff hist −124 Phase II - Preliminary Design →Task No. 24 - Submit Required Permit Applications
- 09:55, 31 May 2023 diff hist +18 Phase III - Final Design →Task No. 3 - Complete Environmental Process
- 09:54, 31 May 2023 diff hist +135 Phase III - Final Design →Task No. 3 - Complete Environmental Process
- 10:20, 23 January 2023 diff hist −29 Streetlight Design Manual → Intersection Lighting for Continuously Lighted Streets:
- 09:48, 23 January 2023 diff hist −30 Streetlight Design Manual → Intersection Lighting for Continuously Lighted Streets:
- 09:39, 23 January 2023 diff hist +1 Streetlight Design Manual → Intersection Lighting for Continuously Lighted Streets:
- 17:22, 19 January 2023 diff hist −100 Phase II - Preliminary Design →Task No. 7 - Initiate Utility Coordination. Schedule Utility Meeting (optional)
- 10:26, 19 October 2022 diff hist +9 Phase IV - Pre-Construction →Task No. 2 - Selection of Material Testing Firm
- 10:25, 19 October 2022 diff hist +61 N File:IV-2a 10-19-22.docx Material Testing/Geotechnical Service Companies current
- 15:29, 13 October 2022 diff hist +9 Phase IV - Pre-Construction →Task No. 5 - Notice to Contractors/DBE Firms
- 15:28, 13 October 2022 diff hist +55 N File:IV-5i 10-13-22.docx List of Contractors for Building Projects current
- 15:26, 13 October 2022 diff hist +1 Phase IV - Pre-Construction →Task No. 5 - Notice to Contractors/DBE Firms
- 15:26, 13 October 2022 diff hist +61 N File:IV-5e 10-13-22.docx List of Contractors for Traffic Signal Projects current
- 15:14, 13 October 2022 diff hist +1 Phase II - Preliminary Design →Task No. 3 - Consultant Selection/Certification
- 15:13, 13 October 2022 diff hist +38 N File:II-3o 10-13-22.xlsx List of Consulting Firms current
- 10:31, 26 July 2022 diff hist −2,757 Contract Documents for CDBG Projects current
- 10:27, 26 July 2022 diff hist +462 Contract Documents for CDBG Projects
- 10:16, 26 July 2022 diff hist −2,378 Phase III - Final Design →Task No. 11 - Submit Contract Documents and Insurance
- 07:56, 26 July 2022 diff hist +4,867 N Contract Documents for CDBG Projects Created page with "'''City's Standard Contract Documents''' {{Exhibit|III-11a-1 Agreement.docx|No. III-11a-1|Agreement}} {{Exhibit|III-11a-2 Bid - use for hard copy bids.docx|No. III-11a-2|Bid (use for hard copy bids)}} {{Exhibit|III-11a-2a Bid items (eBid).xlsx|No. III-11a-2a|Bid (use for all ebid projects, including KDOT and CDBG)}} {{Exhibit|III-11a-2c eBid Certification Form KDOT.docx|No. III-11a-2c|eBid Certification Form for KDOT projects}} {{Exhibit|III-11a-3 General Conditions rev..."
- 07:45, 26 July 2022 diff hist 0 File:III-11a-10a Table of Contents KDOT Projects.docx Irina Idelson uploaded a new version of File:III-11a-10a Table of Contents KDOT Projects.docx
- 15:16, 22 July 2022 diff hist +8 Phase IV - Pre-Construction →Task No. 5 - Notice to Contractors/DBE Firms
- 15:15, 22 July 2022 diff hist +61 N File:IV-5e 7-21-22.docx List of Contractors for Traffic Signal Projects current
- 15:14, 22 July 2022 diff hist +8 Phase IV - Pre-Construction →Task No. 5 - Notice to Contractors/DBE Firms
- 15:13, 22 July 2022 diff hist +58 N File:IV-5d 7-21-22.docx List of Contractors for Streetlight Projects current
- 15:11, 22 July 2022 diff hist +1 Phase IV - Pre-Construction →Task No. 5 - Notice to Contractors/DBE Firms
- 15:05, 22 July 2022 diff hist +58 N File:IV-5b 7-21-22.docx List of Contractors for Storm Sewer Projects current
- 15:01, 22 July 2022 diff hist +1 Phase IV - Pre-Construction →Task No. 5 - Notice to Contractors/DBE Firms
- 15:00, 22 July 2022 diff hist +64 N File:IV-5a 7-21-22.docx List of Contractors for Street and Bridge Projects current
- 14:51, 22 July 2022 diff hist +8 Phase II - Preliminary Design →Task No. 3 - Consultant Selection/Certification
- 14:50, 22 July 2022 diff hist +38 N File:II-3o 7-21-22.xlsx List of Consulting Firms current
- 16:11, 11 July 2022 diff hist −1 Phase IV - Pre-Construction →Task No. 2 - Selection of Material Testing Firm
- 16:10, 11 July 2022 diff hist +40 N File:IV-2g Testing Services Agreement - rev 7-5-22.docx Testing Services Agreement current
- 16:09, 11 July 2022 diff hist +11 Phase III - Final Design →Task No. 11 - Submit Contract Documents and Insurance
- 16:08, 11 July 2022 diff hist +55 N File:III-11a-4C 2 eBid-Instructions to Bidders-Opt C rev 7-5-22.docx Instructions to Bidders (ebid) - Option C current
- 16:07, 11 July 2022 diff hist +11 Phase III - Final Design →Task No. 11 - Submit Contract Documents and Insurance
- 16:05, 11 July 2022 diff hist +55 N File:III-11a-4B 2 eBid-Instructions to Bidders-Opt B rev 7-5-22.docx Instructions to Bidders (ebid) - Option B current
- 16:04, 11 July 2022 diff hist +11 Phase III - Final Design →Task No. 11 - Submit Contract Documents and Insurance
- 16:02, 11 July 2022 diff hist +58 N File:III-11a-4A 2 eBid- Instructions to Bidders-Opt A rev 7-5-22.docx Instructions to Bidders - Electronic Bidding current
- 15:56, 11 July 2022 diff hist +11 Phase III - Final Design →Task No. 11 - Submit Contract Documents and Insurance
- 15:55, 11 July 2022 diff hist +40 N File:III-11a-3 General Conditions rev 7-5-22.docx Project General Conditions current
- 15:51, 11 July 2022 diff hist −2 Phase II - Preliminary Design →Task No. 34 - Hire Appraiser
- 15:50, 11 July 2022 diff hist +54 N File:II-34e Appraiser Agreement over 10K rev 7-5-22.docx Appraisal Agreement for Fee over $10,000 current
- 15:49, 11 July 2022 diff hist −1 Phase II - Preliminary Design →Task No. 34 - Hire Appraiser
- 15:48, 11 July 2022 diff hist +55 N File:II-34d Appraiser Agreement under 10K rev 7-5-22.docx Appraisal Agreement for fee under $10,000 current
- 15:46, 11 July 2022 diff hist −1 Phase II - Preliminary Design →Task No. 3 - Consultant Selection/Certification
- 15:45, 11 July 2022 diff hist +58 N File:II-3c Consultant Agreement-non design rev 7-5-22.docx Consultant Agreement for non-design projects current
- 15:43, 11 July 2022 diff hist −2 Phase II - Preliminary Design →Task No. 3 - Consultant Selection/Certification
- 15:42, 11 July 2022 diff hist +60 N File:II-3a Engineering Architectural Services Agreement rev 7-5-22.docx Engineering / Architectural Services Agreement current
- 16:00, 9 June 2022 diff hist +11 Phase II - Preliminary Design →Task No. 35 - Prepare R/W and Easement Documents
- 15:59, 9 June 2022 diff hist +32 N File:Temporary-construction-easement-city-grantee rev 6-9-22.docx TCE - City Grantee current
- 15:06, 6 June 2022 diff hist +7 Phase IV - Pre-Construction →Task No. 5 - Notice to Contractors/DBE Firms
- 15:02, 6 June 2022 diff hist +64 N File:IV-5c 6-6-22.docx List of Contractors for Sidewalk and Curb Projects current
- 15:01, 6 June 2022 diff hist +7 Phase IV - Pre-Construction →Task No. 5 - Notice to Contractors/DBE Firms
- 15:01, 6 June 2022 diff hist +58 N File:IV-5b 6-6-22.docx List of Contractors for Storm Sewer Projects current
- 15:00, 6 June 2022 diff hist +7 Phase IV - Pre-Construction →Task No. 5 - Notice to Contractors/DBE Firms
- 14:59, 6 June 2022 diff hist +64 N File:IV-5a 6-6-22.docx List of Contractors for Street and Bridge Projects current
- 15:54, 28 April 2022 diff hist −139 Phase V - Construction →Task No. 12 - On-Going Inspections Tag: Manual revert
- 10:21, 26 April 2022 diff hist +139 Phase V - Construction →Task No. 12 - On-Going Inspections Tag: Reverted
- 10:15, 26 April 2022 diff hist +47 N File:2020 KDOT BLP Bridge Inspection Manual.pdf KDOT BLP Bridge Inspection Manual current
- 13:07, 21 April 2022 diff hist +2 Phase II - Preliminary Design →Task No. 10 - Standard Details
- 13:07, 21 April 2022 diff hist +58 N File:Thoroughfare Ultimate 4- and 3-Lane Sections March-2022.pdf Thoroughfare Ultimate 4- and 3-lane Sections current
- 13:06, 21 April 2022 diff hist +2 Phase II - Preliminary Design →Task No. 10 - Standard Details
- 13:06, 21 April 2022 diff hist +51 N File:Thoroughfare Ultimate 2-Lane Sections March-2022.pdf Thoroughfare Ultimate 2-lane Sections current
- 13:05, 21 April 2022 diff hist +2 Phase II - Preliminary Design →Task No. 10 - Standard Details
- 13:04, 21 April 2022 diff hist +43 N File:Thoroughfare Interim Sections March-2022.pdf Thoroughfare Interim Sections current
- 16:35, 28 February 2022 diff hist 0 File:IV-5l Plan Rooms.docx Irina Idelson uploaded a new version of File:IV-5l Plan Rooms.docx current
- 16:26, 28 February 2022 diff hist 0 File:IV-5l.docx Irina Idelson uploaded a new version of File:IV-5l.docx current
- 14:03, 28 February 2022 diff hist 0 File:IV-5l.doc Irina Idelson uploaded a new version of File:IV-5l.doc current
- 14:01, 28 February 2022 diff hist 0 File:IV-5j.docx Irina Idelson uploaded a new version of File:IV-5j.docx current
- 14:00, 28 February 2022 diff hist 0 File:IV-5i.docx Irina Idelson uploaded a new version of File:IV-5i.docx current
- 13:59, 28 February 2022 diff hist 0 File:IV-5h.docx Irina Idelson uploaded a new version of File:IV-5h.docx current
- 13:58, 28 February 2022 diff hist 0 File:IV-5g.docx Irina Idelson uploaded a new version of File:IV-5g.docx current
- 13:57, 28 February 2022 diff hist 0 File:IV-5f.docx Irina Idelson uploaded a new version of File:IV-5f.docx current
- 13:55, 28 February 2022 diff hist 0 File:IV-5e.docx Irina Idelson uploaded a new version of File:IV-5e.docx current
- 13:54, 28 February 2022 diff hist 0 File:IV-5d.docx Irina Idelson uploaded a new version of File:IV-5d.docx current
- 13:53, 28 February 2022 diff hist 0 File:IV-5c.docx Irina Idelson uploaded a new version of File:IV-5c.docx current
- 13:51, 28 February 2022 diff hist 0 File:IV-5b.docx Irina Idelson uploaded a new version of File:IV-5b.docx current
- 13:47, 28 February 2022 diff hist 0 File:IV-5a.docx Irina Idelson uploaded a new version of File:IV-5a.docx current
- 13:43, 28 February 2022 diff hist 0 File:II-34a.docx Irina Idelson uploaded a new version of File:II-34a.docx current
- 13:37, 28 February 2022 diff hist +2 Phase II - Preliminary Design →Task No. 3 - Consultant Selection/Certification Tag: Visual edit
- 13:35, 28 February 2022 diff hist +60 N File:II-3a Engineering Architectural Services Agreement rev 10-15-21.docx Engineering / Architectural Services Agreement current
- 13:15, 28 February 2022 diff hist 0 File:II-3o.xlsx Irina Idelson uploaded a new version of File:II-3o.xlsx
- 15:05, 27 December 2021 diff hist +1 Phase I - Vision →Task 12 - Obtain Priority Evaluation from KDOT
- 12:27, 23 December 2021 diff hist −230 Phase I - Vision →Task 13 - Submit KDOT Form 1302 for Project Request. Submit City's Request to Administer the Project
- 12:07, 19 November 2021 diff hist 0 File:Phase IV Checklist.docx Irina Idelson uploaded a new version of File:Phase IV Checklist.docx current
- 12:05, 19 November 2021 diff hist 0 File:Phase VI Checklist.docx Irina Idelson uploaded a new version of File:Phase VI Checklist.docx current
- 11:58, 19 November 2021 diff hist 0 File:Phase VI Checklist.docx Irina Idelson uploaded a new version of File:Phase VI Checklist.docx
- 11:50, 19 November 2021 diff hist −95 Phase III - Final Design →Task No. 14 - Submit PS&E Package
- 11:48, 19 November 2021 diff hist 0 File:III-14 Request for Obligation.pdf Irina Idelson uploaded a new version of File:III-14 Request for Obligation.pdf current
- 11:19, 19 November 2021 diff hist +15 Phase IV - Pre-Construction →Task No. 8 - Determine Contractor Qualifications - KDOT Projects
- 09:55, 17 November 2021 diff hist +11 Phase IV - Pre-Construction →Task No. 8 - Determine Contractor Qualifications - KDOT Projects
- 09:04, 17 November 2021 diff hist +2 Phase III - Final Design →Task No. 14 - Submit PS&E Package
- 08:55, 17 November 2021 diff hist −3 Phase II - Preliminary Design →Task No. 31 - Complete Public Interest Finding
- 17:51, 16 November 2021 diff hist −13 Phase V - Construction →Task No. 14 - On-Going Contractor Payments
- 17:50, 16 November 2021 diff hist 0 Phase V - Construction →Task No. 4 - Distribute Executed Contract Documents
- 17:49, 16 November 2021 diff hist +4 Phase V - Construction →Task No. 4 - Distribute Executed Contract Documents
- 17:48, 16 November 2021 diff hist +58 Phase V - Construction →Task No. 4 - Distribute Executed Contract Documents
- 17:44, 16 November 2021 diff hist +58 Phase V - Construction →Task No. 4 - Distribute Executed Contract Documents
- 11:29, 16 November 2021 diff hist +3 Phase II - Preliminary Design →Task No. 31 - Complete Public Interest Finding
- 09:32, 10 November 2021 diff hist 0 File:V-12c Concrete Inspections Guidelines.xlsx Irina Idelson uploaded a new version of File:V-12c Concrete Inspections Guidelines.xlsx current
- 08:31, 10 November 2021 diff hist +33 Phase V - Construction →Task No. 12 - On-Going Inspections
- 08:30, 10 November 2021 diff hist +53 N File:V-12c Concrete Inspections Guidelines.xlsx City's Concrete Inspection Requirements
- 16:45, 1 November 2021 diff hist +47 Template:Green current
- 14:40, 1 November 2021 diff hist −688 Phase V - Construction →Task No. 15 - On-Going Change Orders
- 11:44, 1 November 2021 diff hist +4 Template:Green
- 11:44, 1 November 2021 diff hist +13 Template:Green
- 11:42, 1 November 2021 diff hist +46 Template:Green
- 11:29, 1 November 2021 diff hist +690 Template:Green
- 11:18, 1 November 2021 diff hist +151 Phase V - Construction →Task No. 15 - On-Going Change Orders
- 16:35, 19 October 2021 diff hist +106 Phase VI - Retrospect →Task No. 7 - Receive Project Audit by KDOT
- 16:28, 19 October 2021 diff hist −60 Phase V - Construction →Task No. 24 - Submit Material Certification to KDOT
- 16:25, 19 October 2021 diff hist +141 Phase V - Construction →Task No. 16 - On-Going Construction Administration
- 15:39, 19 October 2021 diff hist −93 Phase V - Construction →Task No. 14 - On-Going Contractor Payments
- 15:26, 19 October 2021 diff hist 0 Phase V - Construction →Task No. 10 - Issue Notice to Proceed
- 15:25, 19 October 2021 diff hist −51 Phase V - Construction →Task No. 10 - Issue Notice to Proceed
- 15:19, 19 October 2021 diff hist +37 Phase V - Construction →Task No. 21 - Receive Contractor Project Completion Certification
- 15:03, 19 October 2021 diff hist +38 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 14:58, 19 October 2021 diff hist +43 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 14:55, 19 October 2021 diff hist +48 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 14:51, 19 October 2021 diff hist +37 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 14:41, 19 October 2021 diff hist +158 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 14:12, 19 October 2021 diff hist +123 Phase II - Preliminary Design →Task No. 19 - Prepare Field Check Plans
- 14:12, 19 October 2021 diff hist −1 Phase II - Preliminary Design →Task No. 18 - Submit Request for Design Exception to KDOT
- 14:11, 19 October 2021 diff hist +100 Phase II - Preliminary Design →Task No. 19 - Prepare Field Check Plans
- 13:52, 19 October 2021 diff hist +64 Phase II - Preliminary Design →Task No. 18 - Submit Request for Design Exception to KDOT
- 13:36, 19 October 2021 diff hist −71 Phase II - Preliminary Design →Task No. 18 - Submit Request for Design Exception to KDOT
- 13:35, 19 October 2021 diff hist +71 Phase II - Preliminary Design →Task No. 18 - Submit Request for Design Exception to KDOT
- 16:47, 18 October 2021 diff hist −14 Phase IV - Pre-Construction →Task No. 16 - Request Bid Approval from KDOT
- 16:47, 18 October 2021 diff hist +46 N File:Checklist for Authority to Award.pdf Checklist for Authority to Award current
- 16:11, 18 October 2021 diff hist +211 Phase IV - Pre-Construction →Task No. 8 - Determine Contractor Qualifications - KDOT Projects
- 10:27, 6 October 2021 diff hist −80 Phase III - Final Design →Task No. 19 - Receive Obligation of Funds from KDOT
- 09:55, 6 October 2021 diff hist −823 Phase III - Final Design →Task No. 19 - Receive Obligation of Funds from KDOT
- 09:26, 6 October 2021 diff hist −129 Phase IV - Pre-Construction →Task No. 12 - Determine and Approve the Lowest and Best Qualified Contractor and Subcontractor Percent of Work
- 09:25, 6 October 2021 diff hist +1 Phase IV - Pre-Construction →Task No. 12 - Determine and Approve the Lowest and Best Qualified Contractor and Subcontractor Percent of Work
- 09:24, 6 October 2021 diff hist +129 Phase IV - Pre-Construction →Task No. 12 - Determine and Approve the Lowest and Best Qualified Contractor and Subcontractor Percent of Work
- 08:16, 6 October 2021 diff hist −9 Phase IV - Pre-Construction →Task No. 13 - Evaluate Possible Contractor Collusion
- 15:40, 30 September 2021 diff hist +125 Phase II - Preliminary Design →Task No. 24 - Submit Required Permit Applications
- 14:52, 30 September 2021 diff hist −16 Phase V - Construction →Task No. 8 - Complete Contractor Permits
- 14:49, 30 September 2021 diff hist −72 Phase V - Construction →Task No. 8 - Complete Contractor Permits
- 12:01, 30 September 2021 diff hist −260 Phase II - Preliminary Design →Task No. 15 - Schedule First Public Information Meeting
- 12:00, 30 September 2021 diff hist +57 Phase II - Preliminary Design →Task No. 15 - Schedule First Public Information Meeting
- 11:56, 30 September 2021 diff hist +173 Phase II - Preliminary Design →Task No. 15 - Schedule First Public Information Meeting
- 11:33, 30 September 2021 diff hist +6 Phase II - Preliminary Design →Task No. 4 - Submit Project Description to Law Department. Execute Ordinances-Resolution.
- 11:32, 30 September 2021 diff hist −1 Phase II - Preliminary Design →Task No. 4 - Submit Project Description to Law Department. Execute Ordinances-Resolution.
- 11:13, 30 September 2021 diff hist −384 Phase II - Preliminary Design →Task No. 8 - Pre-Design Meeting
- 11:12, 30 September 2021 diff hist −61 Phase II - Preliminary Design →Task No. 8 - Pre-Design Meeting
- 11:08, 30 September 2021 diff hist +293 Phase II - Preliminary Design →Task No. 8 - Pre-Design Meeting
- 10:54, 30 September 2021 diff hist +40 Phase II - Preliminary Design →Task No. 8 - Pre-Design Meeting
- 10:39, 30 September 2021 diff hist +35 Phase II - Preliminary Design →Task No. 8 - Pre-Design Meeting
- 10:35, 30 September 2021 diff hist −34 Phase II - Preliminary Design →Task No. 8 - Pre-Design Meeting
- 10:30, 30 September 2021 diff hist −1 Phase II - Preliminary Design →Task No. 8 - Pre-Design Meeting
- 10:30, 30 September 2021 diff hist −37 Phase II - Preliminary Design →Task No. 8 - Pre-Design Meeting
- 16:26, 29 September 2021 diff hist +1 Phase III - Final Design →Task No. 19 - Receive Obligation of Funds from KDOT
- 15:57, 29 September 2021 diff hist +194 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 15:12, 29 September 2021 diff hist −38 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 15:03, 29 September 2021 diff hist −2 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 15:02, 29 September 2021 diff hist −17 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 14:47, 29 September 2021 diff hist −102 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 14:45, 29 September 2021 diff hist +38 N File:Traffic-Control-Handbook-July-2016.pdf Traffic Control Handbook current
- 14:39, 29 September 2021 diff hist −76 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 14:33, 29 September 2021 diff hist −137 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 14:31, 29 September 2021 diff hist −137 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 14:29, 29 September 2021 diff hist −61 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 14:28, 29 September 2021 diff hist +64 N File:2021 Design Criteria Volume 2 - Specifications as posted to website 06.15.2021.pdf Design Criteria Volume 2 - Standard Specifications current
- 14:26, 29 September 2021 diff hist −76 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 14:23, 29 September 2021 diff hist +40 N File:2021 Design Criteria Volume 1 - as Posted to website 06.11.2021.pdf Design Criteria - Volume 1 current
- 13:46, 29 September 2021 diff hist +29 Phase III - Final Design →Task No. 14 - Submit PS&E Package
- 13:42, 29 September 2021 diff hist +177 Phase III - Final Design →Task No. 14 - Submit PS&E Package
- 13:59, 28 September 2021 diff hist −159 Phase VI - Retrospect →Task No. 6 - Complete Two-Year Inspection and Bond Release
- 13:59, 28 September 2021 diff hist +159 Phase VI - Retrospect →Task No. 6 - Complete Two-Year Inspection and Bond Release
- 13:20, 28 September 2021 diff hist +1 Phase III - Final Design →Task No. 14 - Submit PS&E Package
- 13:19, 28 September 2021 diff hist +54 Phase III - Final Design →Task No. 14 - Submit PS&E Package
- 12:00, 22 September 2021 diff hist +128 Phase I - Vision →Task 13 - Submit KDOT Form 1302 for Project Request. Submit City's Request to Administer the Project
- 11:55, 22 September 2021 diff hist +47 N File:1302 Form Transmittal email.pdf Project Programming Request email current
- 11:49, 22 September 2021 diff hist +11 Phase I - Vision →Task 13 - Submit KDOT Form 1302 for Project Request. Submit City's Request to Administer the Project
- 11:45, 22 September 2021 diff hist +80 Phase I - Vision →Task 13 - Submit KDOT Form 1302 for Project Request. Submit City's Request to Administer the Project
- 11:28, 22 September 2021 diff hist +80 Phase II - Preliminary Design →Task No. 32 - NHS Approval Procedure
- 11:23, 22 September 2021 diff hist 0 Phase II - Preliminary Design →Task No. 32 - NHS Approval Procedure
- 15:22, 21 September 2021 diff hist −17 Phase III - Final Design →For KDOT (Federally Funded) projects, the City’s Standard Contract Documents shall be supplemented with the following required contract provisions:
- 15:20, 21 September 2021 diff hist +94 Phase III - Final Design →For KDOT (Federally Funded) projects, the City’s Standard Contract Documents shall be supplemented with the following required contract provisions: