The City Five Year CIP is prepared annually. This permits revisions to existing projects and submittal of new projects for consideration. The Finance Department usually begins the process in September and is concluded in March of the subsequent year. During this process there are public hearings by the Planning Commission, City Council Committees, and the City Council.
The City Five Year CIP is prepared annually. This permits revisions to existing projects and submittal of new projects for consideration. The Finance Department usually begins the process in September and is concluded in March of the subsequent year. During this process there are public hearings by the Planning Commission, City Council Committees, and the City Council.


Refer to KDOT's [https://www.ksdot.org/Assets/wwwksdotorg/bureaus/burTransPlan/pdf/SharingtheFuture.pdf '''"Guidelines for Public Involvement"'''] and [http://www.fhwa.dot.gov/hep/guidance/superseded/23cfr771.cfm Code of Federal Regulations '''23CFR771'''] regarding the public involvement process requirements for Federal funded projects.  
Refer to KDOT's [https://www.ksdot.org/Assets/wwwksdotorg/bureaus/burTransPlan/pdf/SharingtheFuture.pdf '''"Guidelines for Public Involvement"'''] and Code of Federal Regulations [http://www.fhwa.dot.gov/hep/guidance/superseded/23cfr771.cfm '''23CFR771'''] regarding the public involvement process requirements for Federal funded projects.  


{{Exhibit|I-5a.pdf|No. I-5a| is a sample transmittal letter to the City Staff and CIP calendar.}}
{{Exhibit|I-5a.pdf|No. I-5a| is a sample transmittal letter to the City Staff and CIP calendar.}}

Revision as of 06:19, 24 August 2018

Home I-Vision II-Preliminary Design III-Final Design IV-Pre-Construction V-Construction VI-Retrospect

Introduction

Phase I - Vision

Phase I is the beginning of a project. The principal document involved is the City's Five-Year Capital Improvements Program (Task 5). For extensive complex projects a preliminary plan/cost estimate should be prepared for establishing the scope and the project cost estimate.

Project funding is determined early in the planning/scheduling process. Funding sources will depend on project classification and qualifications. The proposed funding sources will have a significant role in determining the tasks that will be involved in this or subsequent phases of a project. For example, if Federal funding is involved, KDOT and MARC are major players in this and subsequent phases.

A very major objective of this manual is to receive permission from KDOT, subsequent to approval, for the City's Public Works staff to manage/administer Federal funded projects.

Phase I Checklist

Task 1 - Prepare Preliminary Plans/Cost Estimate

For major projects a preliminary plan and a cost estimate will be prepared. This report will be the basis of establishing the design parameters and preliminary project cost. For thoroughfare street projects, this report will also establish the cross section, right-of-way widths, median openings, intersection geometrics, future traffic signal locations, and vertical and horizontal alignments. The preliminary plan is a valuable tool to ensure subsequent development complies with the ultimate construction.

Exhibit No. I-1 is a sample report for 175th Street - Quivira Rd. to Antioch Rd. Preliminary Engineering Study.
Exhibit No. I-1a is a list of the City's Standard Bid Items.

Task 2 - Prepare Feasibility Report

Top

A feasibility report is required when an Improvement District is proposed as a method of financing all or part of a project. This feasibility report is required to have the following:

  • Project description,
  • A description of the proposed improvements and benefit points if applicable,
  • Estimate of probable cost and the potential funding sources available for the project (Improvement District, SMAC, and City funds) including the apportionment of the costs,
  • A legal description of the property to be included in the Improvement District,
  • Easement and property acquisitions,
  • Method of assessment,
  • Apportionment of cost and
  • A summary of the project and a staff recommendation.
Exhibit No. I-2a is a sample feasibility report for the TC-4C Storm Drainage project.
Exhibit No. I-2b is a sample feasibility report for Grandview, 135th Street to 137th Street.

Citizen petitions for requesting projects and/or services are an important method of determining interest. If IDs are the method for financing projects, a formal approved petition form must be obtained from the City along with any instructional information. Informal petitions are available for requesting streetlights, drainage and sidewalk projects.

Exhibit No. I-2c is a copy of Public Works Policy regarding stormwater improvement policies and procedures.
Exhibit No. I-2d is a copy of City Resolution 3655 establishing a policy of creating ID's for bank stabilization projects.
Exhibit No. I-2e is a copy of City Resolution 3900 establishing a policy of creating ID's for drainage projects.
Exhibit No. I-2f is a copy of the City’s petition form for IDs and informal petition forms for streetlights, drainage and sidewalks.

Task 3 - Prepare SMAC Project Addition Study (Form)

Top

If a proposed project was not identified by the County's Consulting Engineer, in the initial or subsequent study, a project addition request letter for a proposed project must first be submitted to the Stormwater Program Manager for approval prior to beginning the Preliminary Engineering Study. The project request letter shall include all the requirements documented in the Administrative Procedures. After the proposed project request is approved, an interlocal agreement is prepared and executed prior to beginning the Preliminary Engineering Study.

Exhibit No. I-3a is a copy of the Johnson County, Stormwater Management Program Policy.
Exhibit No. I-3b is a copy of the Johnson County, Stormwater Management Advisory Council, By Laws.
Exhibit No. I-3c is a copy of the Johnson County, Administrative Procedures for the Stormwater Management Program.
Exhibit No. I-3d is a sample project addition request letter to the Stormwater Program Manager.

Task 4 - Obtain City Council Approval-Preliminary Plans

Completed preliminary plans may need Public Works Committee review and recommendation to the City Council, especially if the proposed plan deviates from any City ordinance or policy. The Director of Public Works shall make this determination.

Task 5 - Obtain City Council Approval - CIP

Top

The City Five Year CIP is prepared annually. This permits revisions to existing projects and submittal of new projects for consideration. The Finance Department usually begins the process in September and is concluded in March of the subsequent year. During this process there are public hearings by the Planning Commission, City Council Committees, and the City Council.

Refer to KDOT's "Guidelines for Public Involvement" and Code of Federal Regulations 23CFR771 regarding the public involvement process requirements for Federal funded projects.

Exhibit No. I-5a is a sample transmittal letter to the City Staff and CIP calendar.
Exhibit No. I-5b is a 2013-2017 CIP project revision form.
Exhibit No. I-5c is a 2013-2017 CIP project addition form.

See CIP for current CIP.

Task 6 - Submit MARC Five Year Plan

Top

Subsequent to City approval of the CIP, the Mid-America Regional Council (MARC) will call for new projects along with updates to the current Transportation Improvement Program (TIP). MARC produces a new TIP every other year to outline federal transportation expenditures over the next five-year period. The call for new projects and updates occur in December with the submittals due to MARC by the first of February. MARC has automated this process as outlined on their website at http://www.marc.org/transportation/tip.htm.

Task 7 - Obtain MARC Approval

Proposed transportation projects will first be prioritized by the Kansas Highway Priority Committee consisting of City Staff members. This recommendation is forwarded to the MARC Total Transportation Policy Committee for recommendation to the MARC Board.

Task 8 - Submit Application to HUD

Top

Overland Park is a HUD Entitlement City and annually receives grant money for low and moderate income neighborhoods. A Citizens' Advisory Committee has been organized to monitor the implementation and progress of all CDBG activities.

Exhibit No. I-8 is the CDBG Citizens' Participation Plan.

Task 9 - Receive HUD Approval

Top

The City Manager receives the official grant approval from HUD and the PDS Staff notifies the city department responsible for project design/construction for capital projects.

Task 10 - Submit CARS Five Year Plan to County

Top

In January of each year Johnson County sends the City a packet containing forms and instructions to be used in submitting funding requests for the CARS Five-Year Program. Submittals must be completed by March 1st of each year. One form must be submitted for each project. A detailed description of the existing facility and a detailed description of the project must be provided as well as project cost information.

Exhibit No. I-10a is a copy of CARS Program Policies and Administrative Procedures and a copy of Resolution No. 019-01, which approved the Policies and Procedures.
Exhibit No. I-10b is a copy of Resolutions 44-90, 058-94 and 082-04 which define the Major Collectors eligible for County's participation through the CARS program.
Exhibit No. I-10c is a map of CARS eligible routes current as of Resolution 082-04.
Exhibit No. I-10d is an example of CARS packet with instructions for submitting CARS Five-Year program to the Board of County Commissioners. A new packet will be sent by CARS each January.
Exhibit No. I-10e is CARS Form A. (2017-2021)
Exhibit No. I-10f is CARS program summary sheet. (2017-2021) The summary sheet is no longer required by CARS but is still used and submitted by City staff in developing the CARS Five-Year program.

Task 11 - Execute Other Agency Agreements

Top

  • CARS:

This agreement between the City and County should be executed prior to beginning project construction. The agreement is generally furnished by the County.

Exhibit No. I-11a is an example of a previously executed CARS Agreement.
  • SMAC:

This agreement between the City and County should be executed prior to beginning project engineering. The agreement is generally furnished by the County.

Exhibit No. I-11b is an example of a previously executed SMAC Agreement for design.
Exhibit No. I-11c is an example of a previously executed SMAC Agreement for construction.
  • City:

The interlocal agreement between the cities shall be executed prior to beginning project engineering. If there is CARS, SMAC and/or KDOT funding the interlocal agreement between the cities shall be executed prior to execution of CARS, SMAC, and/or KDOT agreements.

Exhibit No. I-11d is an Interlocal Agreement template.

Submit staff billing reports to the Finance Department for projects which staff time is reimbursable according to executed Interlocal Agreements. This also includes Improvement Districts.

Exhibit No. V-16c is a sample of a Staff Billing Report to finance.

Task 12 - Obtain Priority Evaluation from KDOT

Top

KDOT participates in the MARC process. As the Federal-Aid projects identified in MARC's approved TIP is scheduled, and funding is available, the City is notified to begin project engineering. For more information see Chapter 2.0 Programming of KDOT's LPA Project Development Manual.

Task 13 - Submit KDOT Form 1302 for Project Request. Submit City's Request to Administer the Project

Top

Once approved in the TIP, the City shall submit a Request for Construction Project (KDOT form 1302) along with a copy of the approved TIP page showing the approved project, and a project schedule. With the transmittal of KDOT form 1302 the City shall also request to administer the Federally Funded project. Once this is received by the BLP, the project shall be programmed. After a two week review the BLP shall generate the 883 and create the City/State Agreement. Once the project receives the project number, the field check plans can be submitted. For more information see Chapter 2.0 Programming of KDOT's LPA Project Development Manual.

Exhibit No. I-13a is a Request for Construction Project (KDOT Form 1302)
Exhibit No. I-13b is RUPIS project schedule.
Exhibit No. I-13c is a sample transmittal letter for KDOT form 1302, TIP page, project schedule, and City's request to administer the federally funded project.

Task 14 - Receive Project Authorization from KDOT. Begin Environmental Process.

Top

No action is required by the City. This is handled by KDOT.

When the project is authorized and Form 883 is executed, the KDOT Bureau of Design, Environmental Services Section (ESS) will perform initial reviews and make initial contacts with environmental regulatory agencies to ascertain the potential for environmental impact.

For more information refer to Chapter 2.0 Programming and Chapter 4.0 Environmental of KDOT's LPA Project Development Manual.

Exhibit No. I-14 is a sample KDOT project authorization form with a typical project schedule.