- 08:01, 16 June 2023 diff hist +163 Phase V - Construction →Task No. 19 - Prepare Revisions/As-Built Plans
- 07:57, 16 June 2023 diff hist +49 N File:V-19c Pavement Marking Project Data Sheet.docx Pavement Marking Project Data Sheet current
- 07:56, 16 June 2023 diff hist +71 Phase V - Construction →Task No. 19 - Prepare Revisions/As-Built Plans
- 13:59, 1 June 2023 diff hist 0 Approved Materials - Erosion and Sediment Control →Erosion Control Blanket & Turf Reinforcement Mat current
- 11:22, 1 June 2023 diff hist −62 Main Page →Special Pages current
- 11:19, 1 June 2023 diff hist +136 Main Page →Special Pages
- 07:43, 1 June 2023 diff hist +26 N File:159 Metcalf to Nall owners.xls mailing list current
- 09:22, 31 May 2023 diff hist +40 Phase IV - Pre-Construction →Task No. 1 - Complete Plans, Specifications and Estimate
- 09:21, 31 May 2023 diff hist −55 Phase III - Final Design →Task No. 3 - Complete Environmental Process
- 09:19, 31 May 2023 diff hist −58 Phase III - Final Design →Task No. 3 - Complete Environmental Process
- 09:07, 31 May 2023 diff hist −124 Phase II - Preliminary Design →Task No. 24 - Submit Required Permit Applications
- 08:55, 31 May 2023 diff hist +18 Phase III - Final Design →Task No. 3 - Complete Environmental Process
- 08:54, 31 May 2023 diff hist +135 Phase III - Final Design →Task No. 3 - Complete Environmental Process
- 09:20, 23 January 2023 diff hist −29 Streetlight Design Manual → Intersection Lighting for Continuously Lighted Streets:
- 08:48, 23 January 2023 diff hist −30 Streetlight Design Manual → Intersection Lighting for Continuously Lighted Streets:
- 08:39, 23 January 2023 diff hist +1 Streetlight Design Manual → Intersection Lighting for Continuously Lighted Streets:
- 16:22, 19 January 2023 diff hist −100 Phase II - Preliminary Design →Task No. 7 - Initiate Utility Coordination. Schedule Utility Meeting (optional)
- 09:26, 19 October 2022 diff hist +9 Phase IV - Pre-Construction →Task No. 2 - Selection of Material Testing Firm
- 09:25, 19 October 2022 diff hist +61 N File:IV-2a 10-19-22.docx Material Testing/Geotechnical Service Companies current
- 14:29, 13 October 2022 diff hist +9 Phase IV - Pre-Construction →Task No. 5 - Notice to Contractors/DBE Firms
- 14:28, 13 October 2022 diff hist +55 N File:IV-5i 10-13-22.docx List of Contractors for Building Projects current
- 14:26, 13 October 2022 diff hist +1 Phase IV - Pre-Construction →Task No. 5 - Notice to Contractors/DBE Firms
- 14:26, 13 October 2022 diff hist +61 N File:IV-5e 10-13-22.docx List of Contractors for Traffic Signal Projects current
- 14:14, 13 October 2022 diff hist +1 Phase II - Preliminary Design →Task No. 3 - Consultant Selection/Certification
- 14:13, 13 October 2022 diff hist +38 N File:II-3o 10-13-22.xlsx List of Consulting Firms current
- 09:31, 26 July 2022 diff hist −2,757 Contract Documents for CDBG Projects current
- 09:27, 26 July 2022 diff hist +462 Contract Documents for CDBG Projects
- 09:16, 26 July 2022 diff hist −2,378 Phase III - Final Design →Task No. 11 - Submit Contract Documents and Insurance
- 06:56, 26 July 2022 diff hist +4,867 N Contract Documents for CDBG Projects Created page with "'''City's Standard Contract Documents''' {{Exhibit|III-11a-1 Agreement.docx|No. III-11a-1|Agreement}} {{Exhibit|III-11a-2 Bid - use for hard copy bids.docx|No. III-11a-2|Bid (use for hard copy bids)}} {{Exhibit|III-11a-2a Bid items (eBid).xlsx|No. III-11a-2a|Bid (use for all ebid projects, including KDOT and CDBG)}} {{Exhibit|III-11a-2c eBid Certification Form KDOT.docx|No. III-11a-2c|eBid Certification Form for KDOT projects}} {{Exhibit|III-11a-3 General Conditions rev..."
- 06:45, 26 July 2022 diff hist 0 File:III-11a-10a Table of Contents KDOT Projects.docx Irina Idelson uploaded a new version of File:III-11a-10a Table of Contents KDOT Projects.docx
- 14:16, 22 July 2022 diff hist +8 Phase IV - Pre-Construction →Task No. 5 - Notice to Contractors/DBE Firms
- 14:15, 22 July 2022 diff hist +61 N File:IV-5e 7-21-22.docx List of Contractors for Traffic Signal Projects current
- 14:14, 22 July 2022 diff hist +8 Phase IV - Pre-Construction →Task No. 5 - Notice to Contractors/DBE Firms
- 14:13, 22 July 2022 diff hist +58 N File:IV-5d 7-21-22.docx List of Contractors for Streetlight Projects current
- 14:11, 22 July 2022 diff hist +1 Phase IV - Pre-Construction →Task No. 5 - Notice to Contractors/DBE Firms
- 14:05, 22 July 2022 diff hist +58 N File:IV-5b 7-21-22.docx List of Contractors for Storm Sewer Projects current
- 14:01, 22 July 2022 diff hist +1 Phase IV - Pre-Construction →Task No. 5 - Notice to Contractors/DBE Firms
- 14:00, 22 July 2022 diff hist +64 N File:IV-5a 7-21-22.docx List of Contractors for Street and Bridge Projects current
- 13:51, 22 July 2022 diff hist +8 Phase II - Preliminary Design →Task No. 3 - Consultant Selection/Certification
- 13:50, 22 July 2022 diff hist +38 N File:II-3o 7-21-22.xlsx List of Consulting Firms current
- 15:11, 11 July 2022 diff hist −1 Phase IV - Pre-Construction →Task No. 2 - Selection of Material Testing Firm
- 15:10, 11 July 2022 diff hist +40 N File:IV-2g Testing Services Agreement - rev 7-5-22.docx Testing Services Agreement current
- 15:09, 11 July 2022 diff hist +11 Phase III - Final Design →Task No. 11 - Submit Contract Documents and Insurance
- 15:08, 11 July 2022 diff hist +55 N File:III-11a-4C 2 eBid-Instructions to Bidders-Opt C rev 7-5-22.docx Instructions to Bidders (ebid) - Option C current
- 15:07, 11 July 2022 diff hist +11 Phase III - Final Design →Task No. 11 - Submit Contract Documents and Insurance
- 15:05, 11 July 2022 diff hist +55 N File:III-11a-4B 2 eBid-Instructions to Bidders-Opt B rev 7-5-22.docx Instructions to Bidders (ebid) - Option B current
- 15:04, 11 July 2022 diff hist +11 Phase III - Final Design →Task No. 11 - Submit Contract Documents and Insurance
- 15:02, 11 July 2022 diff hist +58 N File:III-11a-4A 2 eBid- Instructions to Bidders-Opt A rev 7-5-22.docx Instructions to Bidders - Electronic Bidding current
- 14:56, 11 July 2022 diff hist +11 Phase III - Final Design →Task No. 11 - Submit Contract Documents and Insurance
- 14:55, 11 July 2022 diff hist +40 N File:III-11a-3 General Conditions rev 7-5-22.docx Project General Conditions current