- 05:47, 14 April 2010 diff hist +73 N File:III-22f.pdf "Example Billing" for reimbursement of Construction Engineering Services
- 05:47, 14 April 2010 diff hist +39 N File:III-22e.pdf letter from BLP accepting overhead rate
- 05:47, 14 April 2010 diff hist +34 N File:III-22d.pdf Force Account Equipment Rate Table
- 05:47, 14 April 2010 diff hist +74 N File:III-22c.pdf "Consultant Selection Guide for Construction Engineering on LPA Projects".
- 05:47, 14 April 2010 diff hist +94 N File:III-22b.pdf example of "Exhibit A" referred to in the above Proposal for Construction Engineering Services
- 05:47, 14 April 2010 diff hist +46 N File:III-22a.dot Proposal For Construction Engineering Services
- 13:19, 13 April 2010 diff hist +93 Phase III - Final Design →Task No. 18 - Request / Receive Obligation of Funds from KDOT
- 13:17, 13 April 2010 diff hist +93 N File:III-19.pdf example letter from KDOT approving Obligation of Funds and authorization to bid the contract.
- 13:17, 13 April 2010 diff hist +45 N File:III-14.dot example letter requesting Obligation of Funds
- 13:17, 13 April 2010 diff hist +14 N File:BLP-memo-99-11.PDF BLP Memo 99-11
- 13:14, 13 April 2010 diff hist +26 Phase III - Final Design →Task No. 17- Obtain Agency Plan Approvals
- 13:12, 13 April 2010 diff hist 0 Phase III - Final Design →Task No. 16 - Prepare Design Summary Document
- 13:12, 13 April 2010 diff hist +35 N File:III-13a.dot KDOT "Design Summary Document" form
- 13:11, 13 April 2010 diff hist +91 Phase III - Final Design →Task No. 16 - Prepare Design Summary Document
- 13:10, 13 April 2010 diff hist +2 Phase III - Final Design →Task No. 13 - Schedule Third Public Information Meeting
- 13:09, 13 April 2010 diff hist +194 Phase III - Final Design →Task No. 13 - Schedule Third Public Information Meeting
- 13:07, 13 April 2010 diff hist +81 Phase III - Final Design →Task No. 11 - Complete Utility Relocations
- 13:06, 13 April 2010 diff hist +64 Phase III - Final Design →Task No. 10 - Schedule Fourth Utility Meeting
- 13:05, 13 April 2010 diff hist +67 Phase III - Final Design →For KDOT (Federally Funded) projects, the City’s Standard Contract Documents shall be supplemented with the following:
- 13:04, 13 April 2010 diff hist +350 Phase III - Final Design →For KDOT (Federally Funded) projects, the City’s Standard Contract Documents shall be supplemented with the following:
- 13:00, 13 April 2010 diff hist +28 N File:BLP-memo-10-04.pdf BLP memo 10-04, Buy American
- 12:56, 13 April 2010 diff hist +241 Phase III - Final Design →For KDOT (Federally Funded) projects, the City’s Standard Contract Documents shall be supplemented with the following:
- 12:50, 13 April 2010 diff hist +64 Phase III - Final Design →For KDOT (Federally Funded) projects, the City’s Standard Contract Documents shall be supplemented with the following:
- 12:04, 13 April 2010 diff hist +201 Phase III - Final Design →For CDBG projects, the City’s Standard Contract Documents shall be supplemented with the following:
- 12:02, 13 April 2010 diff hist +116 Phase III - Final Design →For CDBG projects, the City’s Standard Contract Documents shall be supplemented with the following:
- 12:01, 13 April 2010 diff hist +46 N File:CDBG Statement of compliance.pdf Statement of Compliance, Form WH-348 (3 pages)
- 11:59, 13 April 2010 diff hist +99 Phase III - Final Design →For CDBG projects, the City’s Standard Contract Documents shall be supplemented with the following:
- 11:56, 13 April 2010 diff hist +39 N File:CDBG Conflict of interest certification city.doc CDBG Conflict of Interest Certification
- 11:56, 13 April 2010 diff hist +14 N File:CDBG Checklist city.xls CDBG Checklist
- 11:56, 13 April 2010 diff hist +35 N File:CDBG Standards of conduct.pdf CDBG Standards of Conduct (2 pages)
- 11:56, 13 April 2010 diff hist +38 N File:CDBG Notice to all employees.pdf CDBG Notice To All Employees (2 pages)
- 11:41, 13 April 2010 diff hist +211 Phase III - Final Design →For CDBG projects, the City’s Standard Contract Documents shall be supplemented with the following:
- 11:37, 13 April 2010 diff hist +337 Phase III - Final Design →100px Task No. 9 - Submit Contract Documents and Insurance
- 11:30, 13 April 2010 diff hist +39 N File:CDBG Federal labor standards.pdf CDBG Federal labor standards provisions
- 11:30, 13 April 2010 diff hist +22 N File:CDBG Non discrimination.doc CDBG Nondiscrimination
- 11:30, 13 April 2010 diff hist +21 N File:CDBG Section 3 Clause.doc CDBG Section 3 clause
- 11:30, 13 April 2010 diff hist +47 N File:CDBG Equal employment.pdf CDBG Equal Employment Opportunity Certification
- 11:30, 13 April 2010 diff hist +37 N File:CDBG Certification-lobbying.doc CDBG Certification regarding Lobbying
- 11:30, 13 April 2010 diff hist +19 N File:CDBG Debarment.pdf CDBG Debarment form
- 11:30, 13 April 2010 diff hist +60 N File:III-11a-13.dot List of utilities and status of same for contracts over $50k
- 11:30, 13 April 2010 diff hist +52 N File:III-11a-12.dot Appointment of Service Agent for contracts over $50k
- 11:22, 13 April 2010 diff hist +42 N File:III-11a-11.dot Special Conditions for contracts over $50k
- 11:22, 13 April 2010 diff hist +57 N File:III-9a-10b.dot Table of Contents (CDBG projects) for contracts over $50k
- 11:22, 13 April 2010 diff hist +57 N File:III-9a-10a.dot Table of Contents (KDOT projects) for contracts over $50k
- 11:22, 13 April 2010 diff hist +40 N File:III-11a-8.dot Performance Bond for contracts over $50k
- 11:22, 13 April 2010 diff hist +41 N File:III-11a-10.dot Table of Contents for contracts over $50k
- 11:22, 13 April 2010 diff hist +38 N File:III-11a-9.dot Statutory Bond for contracts over $50k
- 11:22, 13 April 2010 diff hist +55 N File:III-11a-7.dot Labor and Material Payment Bond for contracts over $50k
- 11:22, 13 April 2010 diff hist +48 N File:III-9a-6b.dot Notice to bidders (CDBG) for contracts over $50k
- 11:22, 13 April 2010 diff hist +48 N File:III-9a-6a.dot Notice to bidders (KDOT) for contracts over $50k
- 11:22, 13 April 2010 diff hist +41 N File:III-11a-6.dot Notice to bidders for contracts over $50k
- 11:22, 13 April 2010 diff hist +41 N File:III-11a-5.dot Insurance Options for contracts over $50k
- 11:22, 13 April 2010 diff hist +56 N File:III-9a-4c.dot Instructions to bidders Option C for contracts over $50k
- 11:22, 13 April 2010 diff hist +56 N File:III-9a-4b.dot Instructions to bidders Option B for contracts over $50k
- 11:22, 13 April 2010 diff hist +56 N File:III-9a-4a.dot Instructions to bidders Option A for contracts over $50k
- 11:22, 13 April 2010 diff hist +42 N File:III-9a-3.dot General Conditions for contracts over $50k
- 11:22, 13 April 2010 diff hist +43 N File:III-9a-2b.dot Bid (CDBG projects) for contracts over $50k
- 11:22, 13 April 2010 diff hist +43 N File:III-9a-2a.dot Bid (KDOT projects) for contracts over $50k
- 11:22, 13 April 2010 diff hist +27 N File:III-11a-2.dot Bid for contracts over $50k
- 11:22, 13 April 2010 diff hist +33 N File:III-11a-1.dot Agreement for contracts over $50k
- 11:06, 13 April 2010 diff hist +2 Phase III - Final Design →Notes
- 10:49, 13 April 2010 diff hist +15 Phase III - Final Design →Task No. 16 - Prepare Design Summary Document
- 10:47, 13 April 2010 diff hist +54 N File:III-13b.pdf example of a completed KDOT "Design Summary Document".
- 09:38, 13 April 2010 diff hist +5 Template:Navbar
- 09:30, 13 April 2010 diff hist −2 Template:Navbar
- 09:29, 13 April 2010 diff hist −28 Template:Navbar
- 09:29, 13 April 2010 diff hist −1 Template:Navbar
- 09:28, 13 April 2010 diff hist +31 Template:Navbar
- 08:29, 13 April 2010 diff hist 0 Template:Note2 current
- 08:28, 13 April 2010 diff hist +2 Phase III - Final Design →100px Task No. 9 - Submit Contract Documents and Insurance
- 08:27, 13 April 2010 diff hist +158 N Template:Note2 Created page with '{|style="background:#D4FFD4; color:#002AFF" align="center" border="0" cellpadding="5" width="70%" |- |50px||'''Note:''' {{{1}}} |}'
- 07:58, 13 April 2010 diff hist +17 Phase III - Final Design →For KDOT (Federally Funded) projects, the City’s Standard Contract Documents shall be supplemented with the following:
- 07:57, 13 April 2010 diff hist +13 Phase III - Final Design →For CDBG projects, the City’s Standard Contract Documents shall be supplemented with the following:
- 07:55, 13 April 2010 diff hist +26 Phase III - Final Design →100px Task No. 9 - Submit Contract Documents and Insurance
- 07:51, 13 April 2010 diff hist +35 Phase III - Final Design →100px Task No. 9 - Submit Contract Documents and Insurance
- 07:51, 13 April 2010 diff hist +101 Phase III - Final Design →100px Task No. 9 - Submit Contract Documents and Insurance
- 07:49, 13 April 2010 diff hist +38 N File:III-9-4c.dot Instructions to Contractors - Option C
- 07:48, 13 April 2010 diff hist +38 N File:III-9-4b.dot Instructions to Contractors - Option B
- 07:35, 13 April 2010 diff hist +177 Phase III - Final Design →100px Task No. 9 - Submit Contract Documents and Insurance
- 07:31, 13 April 2010 diff hist +57 N File:III-9-10.dot List of utilities and status of same contracts under $50k
- 07:31, 13 April 2010 diff hist +49 N File:III-9-9.dot Appointment of Service Agent contracts under $50k
- 07:31, 13 April 2010 diff hist +39 N File:III-9-8.dot Special conditions contracts under $50k
- 07:31, 13 April 2010 diff hist +38 N File:III-9-7.dot Table of Contents contracts under $50k
- 07:31, 13 April 2010 diff hist +37 N File:III-9-6.dot Performance Bond contracts under $50k
- 07:31, 13 April 2010 diff hist +52 N File:III-9-5.dot Labor and Material Payment Bond contracts under $50k
- 07:31, 13 April 2010 diff hist +60 N File:III-9-4a.dot Instructions to Contractors - Option A contracts under $50k
- 07:31, 13 April 2010 diff hist +43 N File:III-9-3.dot General conditions for contracts under $50k
- 07:31, 13 April 2010 diff hist +33 N File:III-9-2.dot Proposal for contracts under $50k
- 07:31, 13 April 2010 diff hist +34 N File:III-9-1.dot Agreement for contracts under $50k
- 07:31, 13 April 2010 diff hist +54 N File:Contract bidding schedules.dot Guidance for planning bid and contract award schedules
- 07:31, 13 April 2010 diff hist +44 N File:Detailed procedures contract prep.dot Detailed Procedures for Contract Preparation
- 07:31, 13 April 2010 diff hist +30 N File:BLP-memo-04-07.pdf Procedures for DBE Involvement
- 07:15, 13 April 2010 diff hist +180 Phase III - Final Design →Task No. 8 - Submit Specifications and Special Provisions
- 07:12, 13 April 2010 diff hist +43 N File:Using MakeSpec-Instructions.doc Instructions for using the program MakeSpec
- 07:11, 13 April 2010 diff hist +123 N File:III-10c.pdf List of proprietary items for Traffic Signals and Street Lighting to be used in the preparation of plans and specifications
- 07:11, 13 April 2010 diff hist +50 N File:III-10a.pdf sample of City Specifications for a street project
- 07:09, 13 April 2010 diff hist +46 Phase III - Final Design →Task No. 7 - Submit Final Plans for Review Submittal |120px|right
- 07:07, 13 April 2010 diff hist +38 N File:ESC Plan Review Checklist.doc Erosion and Sediment Control Checklist
- 07:05, 13 April 2010 diff hist +3 Phase III - Final Design →Task No. 7 - Submit Final Plans for Review Submittal |120px|right
- 07:04, 13 April 2010 diff hist +254 Phase III - Final Design →Task No. 7 - Submit Final Plans for Review Submittal |120px|right