- 15:19, 19 October 2021 diff hist +37 Phase V - Construction →Task No. 21 - Receive Contractor Project Completion Certification
- 15:03, 19 October 2021 diff hist +38 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 14:58, 19 October 2021 diff hist +43 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 14:55, 19 October 2021 diff hist +48 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 14:51, 19 October 2021 diff hist +37 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 14:41, 19 October 2021 diff hist +158 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 14:12, 19 October 2021 diff hist +123 Phase II - Preliminary Design →Task No. 19 - Prepare Field Check Plans
- 14:12, 19 October 2021 diff hist −1 Phase II - Preliminary Design →Task No. 18 - Submit Request for Design Exception to KDOT
- 14:11, 19 October 2021 diff hist +100 Phase II - Preliminary Design →Task No. 19 - Prepare Field Check Plans
- 13:52, 19 October 2021 diff hist +64 Phase II - Preliminary Design →Task No. 18 - Submit Request for Design Exception to KDOT
- 13:36, 19 October 2021 diff hist −71 Phase II - Preliminary Design →Task No. 18 - Submit Request for Design Exception to KDOT
- 13:35, 19 October 2021 diff hist +71 Phase II - Preliminary Design →Task No. 18 - Submit Request for Design Exception to KDOT
- 16:47, 18 October 2021 diff hist −14 Phase IV - Pre-Construction →Task No. 16 - Request Bid Approval from KDOT
- 16:47, 18 October 2021 diff hist +46 N File:Checklist for Authority to Award.pdf Checklist for Authority to Award current
- 16:11, 18 October 2021 diff hist +211 Phase IV - Pre-Construction →Task No. 8 - Determine Contractor Qualifications - KDOT Projects
- 10:27, 6 October 2021 diff hist −80 Phase III - Final Design →Task No. 19 - Receive Obligation of Funds from KDOT
- 09:55, 6 October 2021 diff hist −823 Phase III - Final Design →Task No. 19 - Receive Obligation of Funds from KDOT
- 09:26, 6 October 2021 diff hist −129 Phase IV - Pre-Construction →Task No. 12 - Determine and Approve the Lowest and Best Qualified Contractor and Subcontractor Percent of Work
- 09:25, 6 October 2021 diff hist +1 Phase IV - Pre-Construction →Task No. 12 - Determine and Approve the Lowest and Best Qualified Contractor and Subcontractor Percent of Work
- 09:24, 6 October 2021 diff hist +129 Phase IV - Pre-Construction →Task No. 12 - Determine and Approve the Lowest and Best Qualified Contractor and Subcontractor Percent of Work