- 08:12, 31 August 2020 diff hist +45 N File:III-11a-7 Labor and Material Payment Bond.docx Labor and Material Payment Bond current
- 08:08, 31 August 2020 diff hist 0 File:III-11a-3 General Conditions.docx Irina Idelson uploaded a new version of File:III-11a-3 General Conditions.docx
- 08:06, 31 August 2020 diff hist +25 Phase III - Final Design →Task No. 11 - Submit Contract Documents and Insurance
- 08:06, 31 August 2020 diff hist +17 N File:III-11a-2 Bid - use for hard copy bids.docx Bid current
- 07:44, 31 August 2020 diff hist 0 File:III-11a-1 Agreement.docx Irina Idelson uploaded a new version of File:III-11a-1 Agreement.docx current
- 07:41, 31 August 2020 diff hist 0 File:III-11-1 Agreement.docx Irina Idelson uploaded a new version of File:III-11-1 Agreement.docx
- 13:52, 27 August 2020 diff hist +29 Phase V - Construction →Task No. 11 - Complete Submittals Review
- 16:43, 26 August 2020 diff hist −2 Phase IV - Pre-Construction →Task No. 4 - Publish Legal Advertisement
- 16:43, 26 August 2020 diff hist −54 Phase IV - Pre-Construction
- 16:42, 26 August 2020 diff hist +56 Phase IV - Pre-Construction →Task No. 4 - Publish Legal Advertisement
- 16:34, 26 August 2020 diff hist −55 Phase IV - Pre-Construction →Task No. 4 - Publish Legal Advertisement
- 16:33, 26 August 2020 diff hist +55 Phase IV - Pre-Construction →Task No. 4 - Publish Legal Advertisement
- 14:32, 26 August 2020 diff hist +3 Phase IV - Pre-Construction →Task No. 12 - Determine and Approve the Lowest and Best Qualified Contractor and Subcontractor Percent of Work
- 14:24, 26 August 2020 diff hist −4 Phase IV - Pre-Construction →Task No. 8 - Determine Contractor Qualifications - KDOT Projects
- 14:03, 26 August 2020 diff hist −35 Phase IV - Pre-Construction →Task No. 4 - Publish Legal Advertisement
- 13:45, 26 August 2020 diff hist +35 Phase IV - Pre-Construction →Task No. 4 - Publish Legal Advertisement
- 09:48, 26 August 2020 diff hist +1 Phase III - Final Design →Task No. 5 - Begin Right-of-Way / Easement Negotiations
- 09:18, 26 August 2020 diff hist 0 Phase II - Preliminary Design →Task No. 18 - Submit Request for Design Exception to KDOT
- 10:23, 20 August 2020 diff hist −88 Phase V - Construction →Task No. 2 - Submit Agency Cash Flow Projection
- 11:47, 18 August 2020 diff hist +23 Phase VI - Retrospect →Task No. 1 - Procedures for Final Cost and Project Close Out