Activity | LPA Target Date |
LPA Action |
BLP Target Date |
BLP Action |
---|---|---|---|---|
INITIATION, SCOPING AND SCHEDULING PHASE | ||||
Project Request(A1) | __________ | __________ | ||
Project Authorization (A2) | __________ | __________ | ||
Consultant Selection (A3) | __________ | __________ | ||
Consultant Selection Certificate (A4) | Not applicable unless federal funds are requested for design services | |||
PRELIMINARY DESIGN PHASE
|