Project Development Procedures for Non-NHS Projects - Checklist

From PPM Wiki - City of Overland Park Projects and Procedures Manual Pages
Jump to navigation Jump to search

Home

Activity LPA
Target Date
LPA
Action
BLP
Target Date
BLP
Action
INITIATION, SCOPING AND SCHEDULING PHASE
Project Request(A1) _______________ _______________    
Project Authorization (A2)     _______________ _______________
Consultant Selection (A3) _______________ _______________    
Consultant Selection Certificate (A4) Not applicable unless federal funds are requested for design services
 
PRELIMINARY DESIGN PHASE
Field Surveys (B1) _______________ _______________    
Environmental Process Begins (B2) _______________ _______________    
Public Involvement (B3) _______________ _______________    
Field Check Plan Submittal (B4) _______________ _______________    
Field Check Plans Review (B5) _______________ _______________    
Field Check (B6) _______________ _______________    
LPA/State Agreement (B7) _______________ _______________    
 
FINAL DESIGN PHASE
Utilities Activities Initiated (C1) _______________ _______________    
Right of Way Activities Initiated (C2) _______________ _______________    
Environmental Activities Completed for Design (C3) _______________ _______________ _______________ _______________
R/W & Utilities Activities Completed (C4) _______________ _______________    
Public Involvement Process Completed (C5) _______________ _______________    
Engineering Cost Estimate (C6) _______________ _______________    
Design Summary Document (C7) _______________ _______________    
Authorization of Funds (C8)     _______________ _______________
Construction Engineer Agreement (C9) _______________ _______________ _______________ _______________
 
CONSTRUCTION PHASE
Bid Date (D1) _______________ _______________    
Authorization to Award Contract (D2) _______________ _______________ _______________ _______________
Award Contract (D3) _______________ _______________    
Notice to Proceed (D4) _______________ _______________    
Contract Administration (D5) _______________ _______________    
Notice of Acceptance (D6) _______________ _______________    
Materials Certification (D7) _______________ _______________    
Construction Summary Report (D8) _______________ _______________    
Final Acceptance (D9) _______________ _______________    
Project Audit (D10)     _______________ _______________
Final Payment (D11)     _______________ _______________