Project Development Procedures for Non-NHS Projects - Checklist
| Activity | LPA Target Date  | 
LPA Action  | 
BLP Target Date  | 
BLP Action  | 
|---|---|---|---|---|
| INITIATION, SCOPING AND SCHEDULING PHASE | - | - | - | |
| Project Request(A1) | ________ | __________ | ||
| Project Authorization (A2) | ________ | ________ | ||
| Consultant Selection (A3) | ________ | ________ | ||
| Consultant Selection Certificate (A4) | Not applicable unless federal funds are requested for design services | |||
| PRELIMINARY DESIGN PHASE
 
  |