- 16:2216:22, 3 January 2023 diff hist +104 Phase II - Preliminary Design →Task No. 7 - Initiate Utility Coordination. Schedule Utility Meeting (optional)
28 December 2022
- 10:1710:17, 28 December 2022 diff hist +348 Phase II - Preliminary Design →Task No. 21 - Update Preliminary Cost Estimate
26 October 2022
- 13:3913:39, 26 October 2022 diff hist −7 Phase IV - Pre-Construction →Task No. 8 - Determine Contractor/Sub-Contractor Qualifications - KDOT Projects
2 August 2022
- 10:5510:55, 2 August 2022 diff hist 0 File:V-19a.docx Joe Archer uploaded a new version of File:V-19a.docx
14 June 2022
- 15:2815:28, 14 June 2022 diff hist −86 Main Page →Overview
27 April 2022
- 14:4914:49, 27 April 2022 diff hist 0 File:Creating Table of Contents and Project Specific Special Provisions.pdf Joe Archer uploaded a new version of File:Creating Table of Contents and Project Specific Special Provisions.pdf current
11 April 2022
- 07:3707:37, 11 April 2022 diff hist 0 File:II-3o.xlsx Joe Archer uploaded a new version of File:II-3o.xlsx current
22 March 2022
- 15:0615:06, 22 March 2022 diff hist +14 Bid item list No edit summary current Tag: Visual edit: Switched
3 March 2022
- 15:5215:52, 3 March 2022 diff hist −41 Approved Materials - Storm Drainage →Underdrains current
- 15:5115:51, 3 March 2022 diff hist −41 Approved Materials - Storm Drainage →Class III Concrete Pipe
- 15:4915:49, 3 March 2022 diff hist −41 Approved Materials - Storm Drainage →Manhole Rings & Lids
- 15:4615:46, 3 March 2022 diff hist −41 Approved Materials - Storm Drainage →Manhole Steps
- 15:4115:41, 3 March 2022 diff hist −41 Approved Materials - Concrete Work →ADA Detectable Warning Plates current
- 15:3815:38, 3 March 2022 diff hist −41 Approved Materials - Concrete Work →Median Pavers
- 15:3615:36, 3 March 2022 diff hist +1 Approved Materials - Concrete Work →Expansion Joint Material
- 15:3415:34, 3 March 2022 diff hist +1 Approved Materials - Concrete Work →Expansion Joint Material
- 15:2815:28, 3 March 2022 diff hist −41 Approved Materials - Concrete Work →Expansion Joint Material
- 15:0415:04, 3 March 2022 diff hist −39 Approved Materials - Concrete Work No edit summary
25 February 2022
- 08:3408:34, 25 February 2022 diff hist −44 Phase II - Preliminary Design →Task No. 26 - Coordinate Electrical Service for Traffic Signals, Street Lighting and other City Facilities
21 February 2022
- 12:5012:50, 21 February 2022 diff hist 0 Phase III - Final Design →For KDOT (Federally Funded) projects, the City’s Standard Contract Documents shall be supplemented with the following required contract provisions:
- 12:4912:49, 21 February 2022 diff hist +2 Phase III - Final Design →For KDOT (Federally Funded) projects, the City’s Standard Contract Documents shall be supplemented with the following required contract provisions:
- 12:4812:48, 21 February 2022 diff hist −7 Phase III - Final Design →For KDOT (Federally Funded) projects, the City’s Standard Contract Documents shall be supplemented with the following required contract provisions:
- 12:4212:42, 21 February 2022 diff hist −133 Phase III - Final Design →For CDBG projects, the City’s Standard Contract Documents shall be supplemented with the following:
- 12:3912:39, 21 February 2022 diff hist −38 Phase III - Final Design →For CDBG projects, the City’s Standard Contract Documents shall be supplemented with the following:
- 12:3712:37, 21 February 2022 diff hist −76 Phase III - Final Design →For KDOT (Federally Funded) projects, the City’s Standard Contract Documents shall be supplemented with the following required contract provisions:
- 12:3612:36, 21 February 2022 diff hist −31 Phase III - Final Design →For KDOT (Federally Funded) projects, the City’s Standard Contract Documents shall be supplemented with the following required contract provisions:
- 12:2412:24, 21 February 2022 diff hist −7 Editor Test Page →For CDBG projects, the City’s Standard Contract Documents shall be supplemented with the following: current
- 12:2212:22, 21 February 2022 diff hist −133 Editor Test Page →For CDBG projects, the City’s Standard Contract Documents shall be supplemented with the following:
24 January 2022
- 11:2311:23, 24 January 2022 diff hist 0 File:II-7.docx Joe Archer uploaded a new version of File:II-7.docx
4 January 2022
- 16:0616:06, 4 January 2022 diff hist 0 File:Phase II Checklist.docx Joe Archer uploaded a new version of File:Phase II Checklist.docx current
3 December 2021
- 16:4216:42, 3 December 2021 diff hist +1 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 16:3316:33, 3 December 2021 diff hist +830 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 16:1016:10, 3 December 2021 diff hist +173 Phase II - Preliminary Design →Task No. 9 - Design Criteria
23 November 2021
- 09:5709:57, 23 November 2021 diff hist 0 File:V-19a.docx Joe Archer uploaded a new version of File:V-19a.docx
8 November 2021
- 08:4908:49, 8 November 2021 diff hist +5 Phase II - Preliminary Design →Task No. 9 - Design Criteria
1 November 2021
- 08:4708:47, 1 November 2021 diff hist 0 File:II-7.docx Joe Archer uploaded a new version of File:II-7.docx
27 October 2021
- 15:2915:29, 27 October 2021 diff hist 0 File:IV-2a.docx Joe Archer uploaded a new version of File:IV-2a.docx current
- 15:2915:29, 27 October 2021 diff hist 0 File:IV-5b.docx Joe Archer uploaded a new version of File:IV-5b.docx
- 15:2815:28, 27 October 2021 diff hist 0 File:II-3o.xlsx Joe Archer uploaded a new version of File:II-3o.xlsx
18 October 2021
- 14:4514:45, 18 October 2021 diff hist 0 File:V-19a.docx Joe Archer uploaded a new version of File:V-19a.docx
23 September 2021
- 12:1312:13, 23 September 2021 diff hist −70 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 12:0912:09, 23 September 2021 diff hist −43 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 12:0712:07, 23 September 2021 diff hist −212 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 12:0512:05, 23 September 2021 diff hist −40 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 12:0012:00, 23 September 2021 diff hist 0 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 11:2411:24, 23 September 2021 diff hist +44 Phase IV - Pre-Construction →Task No. 12 - Determine and Approve the Lowest and Best Qualified Contractor and Subcontractor Percent of Work
17 September 2021
- 11:2711:27, 17 September 2021 diff hist −127 Phase V - Construction →Task No. 10 - Issue Notice to Proceed
- 11:2311:23, 17 September 2021 diff hist −6 Phase V - Construction →Task No. 10 - Issue Notice to Proceed
- 11:2211:22, 17 September 2021 diff hist +1 Phase V - Construction →Task No. 10 - Issue Notice to Proceed
- 11:2111:21, 17 September 2021 diff hist +132 Phase V - Construction →Task No. 10 - Issue Notice to Proceed