User contributions for Irina Idelson
Results for Irina Idelson talk block log uploads logs
A user with 4,241 edits. Account created on 9 April 2012.
21 September 2021
- 08:5908:59, 21 September 2021 diff hist +75 Phase II - Preliminary Design →Task No. 7 - Initiate Utility Coordination. Schedule Utility Meeting (optional)
- 08:4808:48, 21 September 2021 diff hist +117 Phase II - Preliminary Design →Task No. 34 - Hire Appraiser
16 September 2021
- 12:2212:22, 16 September 2021 diff hist +37 Phase I - Vision No edit summary
- 10:5510:55, 16 September 2021 diff hist +68 N File:SharingtheFuture.pdf Public Involvement in the Kansas Transportation System current
- 10:5410:54, 16 September 2021 diff hist −2 Phase I - Vision No edit summary
- 10:5010:50, 16 September 2021 diff hist +239 Phase I - Vision No edit summary
- 10:4110:41, 16 September 2021 diff hist −167 Phase I - Vision →Task 13 - Submit KDOT Form 1302 for Project Request. Submit City's Request to Administer the Project
- 10:1410:14, 16 September 2021 diff hist +167 Phase I - Vision →Task 13 - Submit KDOT Form 1302 for Project Request. Submit City's Request to Administer the Project
20 August 2021
- 09:2709:27, 20 August 2021 diff hist 0 Phase III - Final Design →Task No. 4 - Complete NEPA Documentation
- 09:1809:18, 20 August 2021 diff hist 0 Phase V - Construction →Task No. 16 - On-Going Construction Administration
- 09:0109:01, 20 August 2021 diff hist −2 Phase II - Preliminary Design →Task No. 18 - Submit Request for Design Exception to KDOT
- 08:5708:57, 20 August 2021 diff hist −16 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 08:5608:56, 20 August 2021 diff hist −8 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 08:5508:55, 20 August 2021 diff hist +30 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 08:5208:52, 20 August 2021 diff hist 0 Phase IV - Pre-Construction →Task No. 20 - Submit Letting Summary Document to KDOT
- 08:4808:48, 20 August 2021 diff hist 0 Phase IV - Pre-Construction →Task No. 13 - Evaluate Possible Contractor Collusion
- 08:4608:46, 20 August 2021 diff hist 0 Phase IV - Pre-Construction →Task No. 12 - Determine and Approve the Lowest and Best Qualified Contractor and Subcontractor Percent of Work
- 08:1808:18, 20 August 2021 diff hist +2 Phase III - Final Design →Task No. 22 - Confirm Construction Engineering Responsibility
- 08:1508:15, 20 August 2021 diff hist +30 Phase III - Final Design →Task No. 12 - Prepare Engineer’s Cost Estimate
- 08:0708:07, 20 August 2021 diff hist −1 Phase III - Final Design →Task No. 9 - Submit Final Check Plans for Review
- 07:5707:57, 20 August 2021 diff hist 0 Phase III - Final Design →Task No. 8 - Acquire Right-of-Way / Easements - Submit KDOT Forms 1306 and 1304
- 07:5607:56, 20 August 2021 diff hist 0 Phase III - Final Design →Task No. 5 - Begin Right-of-Way / Easement Negotiations
- 07:5407:54, 20 August 2021 diff hist 0 Phase III - Final Design →Task No. 3 - Complete Environmental Process
- 07:5107:51, 20 August 2021 diff hist 0 Phase II - Preliminary Design →Task No. 29 - Continue Environmental Process
- 07:4907:49, 20 August 2021 diff hist 0 Phase II - Preliminary Design →Task No. 18 - Submit Request for Design Exception to KDOT
- 07:4707:47, 20 August 2021 diff hist 0 Phase II - Preliminary Design →Task No. 18 - Submit Request for Design Exception to KDOT
- 07:4607:46, 20 August 2021 diff hist +58 N File:Design Exception Request Summary Form 2020.pdf Design Exception Request_2020_LPA Figure 5.1 current
- 07:3307:33, 20 August 2021 diff hist −2 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 07:1707:17, 20 August 2021 diff hist 0 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 07:1707:17, 20 August 2021 diff hist +57 N File:2020 LPA Manual.pdf LPA Project Development Manual_2020 Edition current
- 07:1507:15, 20 August 2021 diff hist +8 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 07:0907:09, 20 August 2021 diff hist 0 Phase II - Preliminary Design →Task No. 3 - Consultant Selection/Certification
19 August 2021
- 15:3415:34, 19 August 2021 diff hist −2 Phase II - Preliminary Design →Task No. 17 - Begin Geotechnical Report Process
- 15:3215:32, 19 August 2021 diff hist 0 Phase II - Preliminary Design →Task No. 14 - Continue Environmental Process
- 15:2615:26, 19 August 2021 diff hist 0 Phase I - Vision →Task 14 - Receive Project Authorization from KDOT. Begin Environmental Process.
- 15:2515:25, 19 August 2021 diff hist 0 Phase I - Vision →Task 14 - Receive Project Authorization from KDOT. Begin Environmental Process.
- 15:2415:24, 19 August 2021 diff hist 0 Phase I - Vision →Task 13 - Submit KDOT Form 1302 for Project Request. Submit City's Request to Administer the Project
- 15:2415:24, 19 August 2021 diff hist 0 Phase I - Vision →Task 12 - Obtain Priority Evaluation from KDOT
- 15:1215:12, 19 August 2021 diff hist +80 N File:11.0 CE Consultant Selection and Agreement 2020.pdf Chapter 11.0 of KDOT's LPA Project Development Manual_2020 Edition current
- 15:1215:12, 19 August 2021 diff hist +80 N File:10.0 LPA-Administered Procedures 2020.pdf Chapter 10.0 of KDOT's LPA Project Development Manual_2020 Edition current
- 15:1215:12, 19 August 2021 diff hist +79 N File:8.0 Status of Utilities 2020.pdf Chapter 8.0 of KDOT's LPA Project Development Manual_2020 Edition current
- 15:1115:11, 19 August 2021 diff hist +79 N File:7.0 Right of Way 2020.pdf Chapter 7.0 of KDOT's LPA Project Development Manual_2020 Edition current
- 15:1115:11, 19 August 2021 diff hist +79 N File:6.0 Bridge Design 2020.pdf Chapter 6.0 of KDOT's LPA Project Development Manual_2020 Edition current
- 15:1015:10, 19 August 2021 diff hist +79 N File:5.0 Plan Development 2020.pdf Chapter 5.0 of KDOT's LPA Project Development Manual_2020 Edition current
- 15:1015:10, 19 August 2021 diff hist +79 N File:4.0 Environmental 2020.pdf Chapter 4.0 of KDOT's LPA Project Development Manual_2020 Edition current
- 15:0915:09, 19 August 2021 diff hist +79 N File:3.0 PE Consultant Selection and Agreement 2020.pdf Chapter 3.0 of KDOT's LPA Project Development Manual_2020 Edition current
- 15:0815:08, 19 August 2021 diff hist +79 N File:2.0 Programming 2020.pdf Chapter 2.0 of KDOT's LPA Project Development Manual_2020 Edition current