User contributions for Irina Idelson
Results for Irina Idelson talk block log uploads logs
A user with 4,241 edits. Account created on 9 April 2012.
22 January 2020
- 12:1312:13, 22 January 2020 diff hist 0 Phase II - Preliminary Design →Task No. 26 - Coordinate Electrical Service for Traffic Signals, Street Lighting and other Citi Facilities
- 12:0812:08, 22 January 2020 diff hist −101 Phase III - Final Design →Task No. 1 - Schedule Third Utility Meeting
- 12:0712:07, 22 January 2020 diff hist +44 N File:III-1f removal notification letter to Evergy.pdf Removal Notification to Evergy current
- 12:0612:06, 22 January 2020 diff hist +38 Phase III - Final Design →Task No. 1 - Schedule Third Utility Meeting
- 12:0512:05, 22 January 2020 diff hist +71 N File:III-1e Do Not Release to Construction letter.pdf DO NOT Release to Construction Letter to Black & McDonald current
- 12:0312:03, 22 January 2020 diff hist +31 Phase III - Final Design →Task No. 1 - Schedule Third Utility Meeting
- 12:0312:03, 22 January 2020 diff hist +64 N File:III-1d Release to Construction letter.pdf Release to Construction Letter to Black & McDonald current
- 12:0212:02, 22 January 2020 diff hist +38 Phase III - Final Design →Task No. 1 - Schedule Third Utility Meeting
- 12:0212:02, 22 January 2020 diff hist +51 N File:III-1c proposal letter from Black & McDonald.pdf Proposal Letter from Black & McDonald current
- 11:5011:50, 22 January 2020 diff hist +46 Phase III - Final Design →Task No. 1 - Schedule Third Utility Meeting
- 11:4911:49, 22 January 2020 diff hist +48 N File:III-1b letter requesting the removal of streetlights.pdf Request of Removal of Streetlights current
- 11:4611:46, 22 January 2020 diff hist −12 Phase III - Final Design →Task No. 1 - Schedule Third Utility Meeting
- 11:4411:44, 22 January 2020 diff hist +46 N File:III-1a Streetlighting Removal Procedure.pdf Streetlighting Removal Procedure current
- 11:4011:40, 22 January 2020 diff hist +45 Phase III - Final Design →Task No. 1 - Schedule Third Utility Meeting
- 11:4011:40, 22 January 2020 diff hist +46 N File:Exhibit No. III-1a Streetlighting Removal Procedure.pdf Streetlighting Removal Procedure current
- 10:4510:45, 22 January 2020 diff hist +24 Phase III - Final Design →Task No. 1 - Schedule Third Utility Meeting
- 10:4210:42, 22 January 2020 diff hist +19 Phase III - Final Design →Task No. 1 - Schedule Third Utility Meeting
- 10:3710:37, 22 January 2020 diff hist −45 Phase III - Final Design →Task No. 1 - Schedule Third Utility Meeting
21 January 2020
- 12:4112:41, 21 January 2020 diff hist +159 Phase II - Preliminary Design →Task No. 10 - Standard Details
15 January 2020
- 09:1809:18, 15 January 2020 diff hist +1 Phase II - Preliminary Design →Task No. 34 - Hire Appraiser
- 09:1709:17, 15 January 2020 diff hist +55 N File:II-34d Appraiser Agreement under 10K rev 1-14-20.docx Appraisal Agreement for fee under $10,000 current
- 09:1509:15, 15 January 2020 diff hist +1 Phase II - Preliminary Design →Task No. 34 - Hire Appraiser
- 09:1509:15, 15 January 2020 diff hist +54 N File:II-34e Appraiser Agreement over $10K rev 1-14-20.docx Appraisal Agreement for Fee over $10,000 current
- 09:0109:01, 15 January 2020 diff hist +10 Phase II - Preliminary Design →Task No. 3 - Consultant Selection/Certification
- 09:0009:00, 15 January 2020 diff hist +56 N File:II-3d Supplemental to Consulting Services 1-14-20.docx Supplemental Agreement_non-design projects current
- 08:5608:56, 15 January 2020 diff hist 0 Phase II - Preliminary Design →Task No. 3 - Consultant Selection/Certification
- 08:5508:55, 15 January 2020 diff hist +58 N File:II-3c Consultant Agreement-non design rev 1-14-20.docx Consultant Agreement fro non-design projects current
- 08:5008:50, 15 January 2020 diff hist 0 File:II-3b(2) Supplemental to Eng Arch Services-second and beyond 1-14-20.docx Irina Idelson uploaded a new version of File:II-3b(2) Supplemental to Eng Arch Services-second and beyond 1-14-20.docx current
- 08:4308:43, 15 January 2020 diff hist 0 File:II-3b(2) Supplemental to Eng Arch Services-second and beyond 1-14-20.docx Irina Idelson uploaded a new version of File:II-3b(2) Supplemental to Eng Arch Services-second and beyond 1-14-20.docx
14 January 2020
- 17:3417:34, 14 January 2020 diff hist 0 Phase II - Preliminary Design →Task No. 3 - Consultant Selection/Certification
- 17:3317:33, 14 January 2020 diff hist +95 N File:II-3b(2) Supplemental to Eng Arch Services-second and beyond 1-14-20.docx Supplemental Agreement for Professional Engineering Services. (Second and beyond)
- 17:3017:30, 14 January 2020 diff hist +62 Phase II - Preliminary Design →Task No. 3 - Consultant Selection/Certification
- 17:2917:29, 14 January 2020 diff hist +68 N File:II-3b(1) Supplemental to Engineering Architectural Services - 1-14-20.docx Supplemental to Engineering Services Agreement (First) current
- 17:2617:26, 14 January 2020 diff hist +1 Phase II - Preliminary Design →Task No. 3 - Consultant Selection/Certification
- 17:2517:25, 14 January 2020 diff hist +60 N File:II-3a Engineering Architectural Services Agreement rev 12-10-19.docx Engineering / Architectural Services Agreement current
- 15:4215:42, 14 January 2020 diff hist 0 Phase II - Preliminary Design →Task No. 35 - Prepare R/W and Easement Documents
- 15:4115:41, 14 January 2020 diff hist +35 N File:Restoration Agreement template 01.14.2020.docx Restoration Agreement current
- 09:3509:35, 14 January 2020 diff hist +168 Phase II - Preliminary Design →Task No. 31 - Complete Public Interest Finding
- 09:2509:25, 14 January 2020 diff hist +35 Phase II - Preliminary Design →Task No. 13 - Conduct Field Surveys
- 09:2409:24, 14 January 2020 diff hist +33 N File:Flooding Questionnaire Template.doc Flood Questionnaire current
- 09:2209:22, 14 January 2020 diff hist +174 Phase II - Preliminary Design →Task No. 13 - Conduct Field Surveys
12 January 2020
- 00:2400:24, 12 January 2020 diff hist +229 Phase III - Final Design →Task No. 17 - Complete Utility Relocations
- 00:1800:18, 12 January 2020 diff hist −33 Phase III - Final Design →Task No. 17 - Complete Utility Relocations
26 December 2019
- 12:3712:37, 26 December 2019 diff hist −50 Phase III - Final Design →Task No. 1 - Schedule Third Utility Meeting
- 12:1512:15, 26 December 2019 diff hist −1 Right-of-Way Permits - Plan Submission Requirements No edit summary current
- 12:1012:10, 26 December 2019 diff hist +4 Right-of-Way Permits - Plan Submission Requirements No edit summary
- 11:4511:45, 26 December 2019 diff hist +52 Right-of-Way Permits - Plan Submission Requirements No edit summary
- 11:3711:37, 26 December 2019 diff hist −1 Right-of-Way Permits - Plan Submission Requirements No edit summary
- 11:3411:34, 26 December 2019 diff hist +1 Right-of-Way Permits - Plan Submission Requirements No edit summary
- 11:3311:33, 26 December 2019 diff hist +116 Phase III - Final Design →Task No. 1 - Schedule Third Utility Meeting