- 09:53, 18 September 2019 diff hist +194 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 09:47, 18 September 2019 diff hist +1 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 09:47, 18 September 2019 diff hist +199 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 09:45, 18 September 2019 diff hist 0 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 09:44, 18 September 2019 diff hist +412 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 09:35, 18 September 2019 diff hist 0 File:Design exceptions.docx Irina Idelson uploaded a new version of "File:Design exceptions.docx" current
- 09:32, 18 September 2019 diff hist 0 File:Design exceptions.docx Irina Idelson uploaded a new version of "File:Design exceptions.docx"
- 09:20, 18 September 2019 diff hist +6 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 09:14, 18 September 2019 diff hist +18 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 09:06, 18 September 2019 diff hist +12 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 09:05, 18 September 2019 diff hist +22 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 09:01, 18 September 2019 diff hist −22 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 08:51, 18 September 2019 diff hist +68 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 08:49, 18 September 2019 diff hist +168 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 08:48, 18 September 2019 diff hist +124 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 08:41, 18 September 2019 diff hist −5 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 08:32, 18 September 2019 diff hist +81 Phase II - Preliminary Design →Task No. 8 - Pre-Design Meeting
- 07:39, 18 September 2019 diff hist +318 Phase II - Preliminary Design →Task No. 8 - Pre-Design Meeting
- 07:33, 18 September 2019 diff hist +119 Phase II - Preliminary Design →Task No. 8 - Pre-Design Meeting
- 07:16, 18 September 2019 diff hist +23 Phase II - Preliminary Design →Task No. 8 - Pre-Design Meeting
- 07:09, 18 September 2019 diff hist −36 Phase II - Preliminary Design →Task No. 8 - Pre-Design Meeting
- 15:15, 17 September 2019 diff hist +33 Phase II - Preliminary Design →Task No. 7 - Schedule First Utility Meeting
- 15:13, 17 September 2019 diff hist +22 N File:MS1273 Invoice Packet.pdf Payment Invoice to JCW current
- 14:50, 17 September 2019 diff hist +39 Phase II - Preliminary Design →Task No. 6 - Submit Cash Flow Projections (Engineering Cost)
- 14:48, 17 September 2019 diff hist +14 N File:Cash Flow TH-1027 6-2019 Rome.xlsx Cash Flow form current
- 14:45, 17 September 2019 diff hist −105 Phase II - Preliminary Design →Task No. 6 - Submit Cash Flow Projections (Engineering Cost)
- 14:41, 17 September 2019 diff hist −25 Phase II - Preliminary Design →Task No. 5 - Prepare Project Schedule
- 14:40, 17 September 2019 diff hist +65 Phase II - Preliminary Design →Task No. 4 - Submit Project Description to Law Department. Execute Ordinances-Resolution.
- 14:33, 17 September 2019 diff hist +64 N File:CO 2-20-2017 Ordinance MTI-3159 (TH-1665) Publication.pdf Ordinance providing for public improvements of a Main Trafficway current
- 16:18, 11 September 2019 diff hist +17 Phase III - Final Design →Task No. 3 - Complete Environmental Process
- 16:03, 11 September 2019 diff hist +39 Phase III - Final Design →Task No. 3 - Complete Environmental Process
- 16:02, 11 September 2019 diff hist −7 Phase III - Final Design →Task No. 3 - Complete Environmental Process
- 16:01, 11 September 2019 diff hist +103 Phase III - Final Design →Task No. 3 - Complete Environmental Process
- 15:36, 11 September 2019 diff hist +6 Phase V - Construction →Task No. 12 - On-Going Inspections
- 15:34, 11 September 2019 diff hist +30 N File:SWPPP-ConstructionSiteIntspectionReport-Final.pdf Final PW ESC Inspection Report current
- 15:33, 11 September 2019 diff hist +18 Phase V - Construction →Task No. 12 - On-Going Inspections
- 15:31, 11 September 2019 diff hist +24 N File:SWPPP-ConstructionSiteIntspectionReport.pdf PW ESC Inspection Report current
- 15:29, 11 September 2019 diff hist +46 Phase V - Construction →Task No. 7 - Schedule Pre-Construction Conference/Project Sign Confirmation
- 15:07, 11 September 2019 diff hist +31 N File:SWPPP-Contractor'sCertificationForm.pdf Contractor's Certification Form current
- 14:13, 3 September 2019 diff hist +12 Phase IV - Pre-Construction →Task No. 5 - Notice to Contractors/DBE Firms
- 14:12, 3 September 2019 diff hist +50 N File:IV-5l Plan Rooms.docx List of Plan Rooms associated with DBE Contractors
- 13:28, 3 September 2019 diff hist 0 File:IV-5l.docx Irina Idelson uploaded a new version of "File:IV-5l.docx"
- 11:20, 3 September 2019 diff hist 0 File:IV-5l.docx Irina Idelson uploaded a new version of "File:IV-5l.docx"
- 11:19, 3 September 2019 diff hist 0 File:IV-5j.docx Irina Idelson uploaded a new version of "File:IV-5j.docx"
- 11:17, 3 September 2019 diff hist 0 File:IV-5i.docx Irina Idelson uploaded a new version of "File:IV-5i.docx"
- 11:17, 3 September 2019 diff hist 0 File:IV-5h.docx Irina Idelson uploaded a new version of "File:IV-5h.docx"
- 11:15, 3 September 2019 diff hist 0 File:IV-5g.docx Irina Idelson uploaded a new version of "File:IV-5g.docx"
- 11:14, 3 September 2019 diff hist 0 File:IV-5f.docx Irina Idelson uploaded a new version of "File:IV-5f.docx"
- 11:13, 3 September 2019 diff hist 0 File:IV-5e.docx Irina Idelson uploaded a new version of "File:IV-5e.docx"
- 11:12, 3 September 2019 diff hist 0 File:IV-5d.docx Irina Idelson uploaded a new version of "File:IV-5d.docx"