User contributions for Irina Idelson
Jump to navigation
Jump to search
This user is currently blocked. The latest block log entry is provided below for reference:
- 15:06, 5 July 2024 Dan Hurley talk contribs blocked Irina Idelson talk contribs with an expiration time of indefinite (account creation disabled, autoblock disabled, email disabled, cannot edit own talk page) (No longer employed)
- 10:35, 29 August 2018 diff hist +30 Phase V - Construction →Task No. 7 - Schedule Pre-Construction Conference/Project Sign Confirmation
- 10:34, 29 August 2018 diff hist +52 Phase V - Construction →Task No. 7 - Schedule Pre-Construction Conference/Project Sign Confirmation
- 10:27, 29 August 2018 diff hist +59 Phase V - Construction →Task No. 5 - Complete Sales Tax Exemption Forms
- 09:19, 29 August 2018 diff hist −6 Phase V - Construction →Task No. 3 - Submit Cash Flow Projection to City Finance Department
- 09:19, 29 August 2018 diff hist −6 Phase V - Construction →Task No. 2 - Submit Agency Cash Flow Projection
- 09:02, 29 August 2018 diff hist +26 Phase II - Preliminary Design →Task No. 3 - Consultant Selection/Certification
- 09:01, 29 August 2018 diff hist +27 Phase II - Preliminary Design →Task No. 3 - Consultant Selection/Certification
- 09:00, 29 August 2018 diff hist +27 Phase III - Final Design →Task No. 22 - Confirm Construction Engineering Responsibility
- 08:59, 29 August 2018 diff hist −31 Phase III - Final Design →Task No. 22 - Confirm Construction Engineering Responsibility
- 08:55, 29 August 2018 diff hist +2 Phase III - Final Design →Task No. 18 - Schedule Optional Public Information Meeting
- 08:49, 29 August 2018 diff hist +6 Phase II - Preliminary Design →Task No. 36 - Schedule Second Public Information Meeting
- 08:48, 29 August 2018 diff hist +12 Phase III - Final Design →Task No. 18 - Schedule Optional Public Information Meeting
- 08:47, 29 August 2018 diff hist −90 Phase III - Final Design →Task No. 18 - Schedule Optional Public Information Meeting
- 08:46, 29 August 2018 diff hist +90 Phase III - Final Design →Task No. 18 - Schedule Optional Public Information Meeting
- 08:42, 29 August 2018 diff hist +82 Phase III - Final Design →Task No. 15 - PS&E Review
- 08:32, 29 August 2018 diff hist +84 Phase III - Final Design →For KDOT (Federally Funded) projects, the City’s Standard Contract Documents shall be supplemented with the following required contract provisions:
- 08:21, 29 August 2018 diff hist +101 Phase III - Final Design →For KDOT (Federally Funded) projects, the City’s Standard Contract Documents shall be supplemented with the following required contract provisions:
- 07:48, 29 August 2018 diff hist +6 Phase III - Final Design →Task No. 10 - Submit Specifications and Special Provisions
- 07:46, 29 August 2018 diff hist +27 Phase III - Final Design →Task No. 10 - Submit Specifications and Special Provisions
- 07:37, 29 August 2018 diff hist +6 Phase III - Final Design →Task No. 9 - Submit Final Check Plans for Review
- 07:37, 29 August 2018 diff hist 0 Phase III - Final Design →Task No. 9 - Submit Final Check Plans for Review
- 07:36, 29 August 2018 diff hist +112 Phase III - Final Design →Task No. 9 - Submit Final Check Plans for Review
- 07:33, 29 August 2018 diff hist +55 N File:15.0 LPA-Administered Procedures 2018.pdf Chapter 15 of the KDOT's LPA Project Development Manual current
- 07:30, 29 August 2018 diff hist +10 Phase III - Final Design →Task No. 9 - Submit Final Check Plans for Review
- 07:29, 29 August 2018 diff hist −4 Phase III - Final Design →Task No. 9 - Submit Final Check Plans for Review
- 07:28, 29 August 2018 diff hist +120 Phase III - Final Design →Task No. 9 - Submit Final Check Plans for Review
- 16:59, 28 August 2018 diff hist −6 Phase III - Final Design →Task No. 9 - Submit Final Check Plans for Review
- 16:57, 28 August 2018 diff hist +6 Phase III - Final Design →Task No. 9 - Submit Final Plans for Review
- 16:56, 28 August 2018 diff hist −6 Phase III - Final Design →Task No. 5 - Begin Right-of-Way / Easement Negotiations
- 16:55, 28 August 2018 diff hist +41 Phase III - Final Design →Task No. 8 - Acquire Right-of-Way / Easements - Submit KDOT Forms 1306 and 1304
- 16:54, 28 August 2018 diff hist +6 Phase III - Final Design →Task No. 8 - Acquire Right-of-Way / Easements - Submit KDOT Forms 1306 and 1304
- 16:54, 28 August 2018 diff hist +135 Phase III - Final Design →Task No. 8 - Acquire Right-of-Way / Easements - Submit KDOT Forms 1306 and 1304
- 16:50, 28 August 2018 diff hist +50 N File:7.0 Status of Utilities 2018.pdf Chapter 7 of KDOT's LPA Project Development Manual current
- 16:46, 28 August 2018 diff hist +67 Phase III - Final Design →Task No. 7 - Complete Condemnation Process
- 16:41, 28 August 2018 diff hist +16 Phase III - Final Design →Task No. 5 - Begin Right-of-Way / Easement Negotiations
- 16:32, 28 August 2018 diff hist −1 Phase III - Final Design →Task No. 5 - Begin Right-of-Way / Easement Negotiations
- 16:31, 28 August 2018 diff hist −1 Phase III - Final Design →Task No. 5 - Begin Right-of-Way / Easement Negotiations
- 16:30, 28 August 2018 diff hist −1 Phase III - Final Design →Task No. 5 - Begin Right-of-Way / Easement Negotiations
- 16:28, 28 August 2018 diff hist −4 Phase III - Final Design →Task No. 5 - Begin Right-of-Way / Easement Negotiations
- 16:27, 28 August 2018 diff hist +52 N File:6.0 Right of Way 2018.pdf Chapter 6.0 of KDOT's LPA Project Development Manual current
- 16:17, 28 August 2018 diff hist +25 Phase III - Final Design →Task No. 5 - Begin Right-of-Way / Easement Negotiations
- 16:16, 28 August 2018 diff hist +148 Phase III - Final Design →Task No. 4 - Complete NEPA Documentation
- 16:15, 28 August 2018 diff hist +147 Phase III - Final Design →Task No. 3 - Complete Environmental Process
- 14:13, 28 August 2018 diff hist +17 Phase II - Preliminary Design →Task No. 34 - Hire Appraiser
- 14:12, 28 August 2018 diff hist +46 N File:II-32i.dot Irina Idelson moved page File:II-32i.dot to File:II-34i appraisal review.dot current
- 14:12, 28 August 2018 diff hist 0 m File:II-34i appraisal review.dot Irina Idelson moved page File:II-32i.dot to File:II-34i appraisal review.dot current
- 13:57, 28 August 2018 diff hist +87 Phase II - Preliminary Design →Task No. 34 - Hire Appraiser
- 13:52, 28 August 2018 diff hist 0 Phase II - Preliminary Design →Task No. 34 - Hire Appraiser
- 13:51, 28 August 2018 diff hist +37 N File:II-34h Ranking sheet rw proposals.pdf Ranking Sheet for Appraisal Proposals current
- 13:49, 28 August 2018 diff hist 0 Phase II - Preliminary Design →Task No. 34 - Hire Appraiser