- 10:5510:55, 21 March 2017 diff hist +123 Phase III - Final Design →Task No. 11 - Submit Contract Documents and Insurance
- 10:5310:53, 21 March 2017 diff hist +41 N File:III-11a-4C 2 eBid-Instructions to Bidders-Opt C.docx Instructions to Bidders (ebid) - Option C current
- 10:5210:52, 21 March 2017 diff hist +2 Phase III - Final Design →Task No. 11 - Submit Contract Documents and Insurance
- 10:5110:51, 21 March 2017 diff hist +2 Phase III - Final Design →Task No. 11 - Submit Contract Documents and Insurance
- 10:5010:50, 21 March 2017 diff hist +34 N File:III-11a-4C 1 Instructions to Bidders-Option C.docx Instructions to Bidders - Option C current
- 10:4910:49, 21 March 2017 diff hist +124 Phase III - Final Design →Task No. 11 - Submit Contract Documents and Insurance
- 10:4710:47, 21 March 2017 diff hist +41 N File:III-11a-4B 2 eBid-Instructions to Bidders-Opt B.docx Instructions to Bidders (ebid) - Option B current
- 10:4610:46, 21 March 2017 diff hist +4 Phase III - Final Design →Task No. 11 - Submit Contract Documents and Insurance
- 10:4510:45, 21 March 2017 diff hist +34 N File:III-11a-4B 1 Instructions to Bidders-Option B.docx Instructions to Bidders - Option B current
- 10:4110:41, 21 March 2017 diff hist +3 Phase III - Final Design →Task No. 11 - Submit Contract Documents and Insurance
- 10:4110:41, 21 March 2017 diff hist +123 Phase III - Final Design →Task No. 11 - Submit Contract Documents and Insurance
- 10:3810:38, 21 March 2017 diff hist +44 N File:III-11a-4A 2 eBid- Instructions to Bidders-Opt A.docx Instructions to Bidders - Electronic Bidding current
- 10:3710:37, 21 March 2017 diff hist +2 Phase III - Final Design →Task No. 11 - Submit Contract Documents and Insurance
- 10:3610:36, 21 March 2017 diff hist +23 N File:III-11a-4A 1 Instructions to Bidders-Option A.docx Instructions to Bidders current
- 10:3010:30, 21 March 2017 diff hist +2 Phase III - Final Design →Task No. 11 - Submit Contract Documents and Insurance
- 10:2910:29, 21 March 2017 diff hist +23 N File:III-11a-4A Instructions to Bidders-Option A.docx Instructions to Bidders current
- 10:2110:21, 21 March 2017 diff hist 0 File:III-11a-3 General Conditions.docx Irina Idelson uploaded a new version of "File:III-11a-3 General Conditions.docx"
- 10:1910:19, 21 March 2017 diff hist −4 Phase III - Final Design →Task No. 11 - Submit Contract Documents and Insurance
- 10:1810:18, 21 March 2017 diff hist +8 Phase III - Final Design →Task No. 11 - Submit Contract Documents and Insurance
- 10:1710:17, 21 March 2017 diff hist +3 N File:III-11a-2 Bid.docx Bid current
- 10:1510:15, 21 March 2017 diff hist −10 Phase III - Final Design →Task No. 11 - Submit Contract Documents and Insurance
- 10:1410:14, 21 March 2017 diff hist 0 Phase III - Final Design →Task No. 11 - Submit Contract Documents and Insurance
- 10:1410:14, 21 March 2017 diff hist +25 N File:III-11a-1 Agreement.docx City_Contractor Agreement
14 February 2017
- 10:2410:24, 14 February 2017 diff hist −44 Phase II - Preliminary Design →Task No. 33 - Prepare R/W and Easement Documents
- 10:0410:04, 14 February 2017 diff hist +40 N File:Restoration Agreement-Exhibit A template.docx Restoration Agreement Exhibit A Template current
- 09:5409:54, 14 February 2017 diff hist +1 Phase II - Preliminary Design →Task No. 33 - Prepare R/W and Easement Documents
- 09:5309:53, 14 February 2017 diff hist +30 N File:Restoration Agreement template.docx Restoration Agreement Template current
7 December 2016
- 15:2615:26, 7 December 2016 diff hist 0 Phase V - Construction →Task No. 12 - On-Going Inspections
- 15:1515:15, 7 December 2016 diff hist +1 Phase V - Construction →Task No. 12 - On-Going Inspections
- 15:1415:14, 7 December 2016 diff hist 0 Phase V - Construction →Task No. 12 - On-Going Inspections
- 15:1115:11, 7 December 2016 diff hist −250 Phase V - Construction →Task No. 12 - On-Going Inspections
- 15:0915:09, 7 December 2016 diff hist +28 Phase V - Construction →Task No. 12 - On-Going Inspections
- 15:0815:08, 7 December 2016 diff hist +28 N File:Final Inspection of Erosion and Sediment Control Form.pdf Final Inspection of ESC form current
- 14:5714:57, 7 December 2016 diff hist −2 Phase V - Construction →Task No. 12 - On-Going Inspections
- 14:5414:54, 7 December 2016 diff hist −302 Phase V - Construction →Task No. 12 - On-Going Inspections
- 14:5014:50, 7 December 2016 diff hist −1 Phase V - Construction →Task No. 8 - Complete Contractor Permits
- 14:4714:47, 7 December 2016 diff hist −532 Phase V - Construction →Task No. 8 - Complete Contractor Permits
- 14:3714:37, 7 December 2016 diff hist +6 Phase V - Construction →Task No. 7 - Schedule Pre-Construction Conference/Project Sign Confirmation
- 14:3414:34, 7 December 2016 diff hist 0 Phase IV - Pre-Construction →Task No. 1 - Complete Plans, Specifications and Estimate
- 14:3314:33, 7 December 2016 diff hist −73 Phase IV - Pre-Construction →Task No. 1 - Complete Plans, Specifications and Estimate
- 14:3014:30, 7 December 2016 diff hist +40 N File:SWPPP Template 12-01-16.docx Stormwater Pollution and Prevention Plan current
- 14:2614:26, 7 December 2016 diff hist −3 Phase IV - Pre-Construction →Task No. 1 - Complete Plans, Specifications and Estimate
- 14:2514:25, 7 December 2016 diff hist +86 Phase IV - Pre-Construction →Task No. 1 - Complete Plans, Specifications and Estimate
- 14:2014:20, 7 December 2016 diff hist −253 Phase III - Final Design →Task No. 9 - Submit Final Plans for Review
- 11:3111:31, 7 December 2016 diff hist −1,246 Phase II - Preliminary Design →Task No. 24 - Submit Required Permit Applications
6 December 2016
- 14:2014:20, 6 December 2016 diff hist 0 Phase III - Final Design →Task No. 9 - Submit Final Plans for Review
- 14:0314:03, 6 December 2016 diff hist +1 Phase V - Construction →Task No. 12 - On-Going Inspections
- 13:0813:08, 6 December 2016 diff hist +114 Phase V - Construction →Task No. 12 - On-Going Inspections
- 13:0313:03, 6 December 2016 diff hist +35 N File:SWPPP Inspection Form.pdf Public Work's SWPPP Inspection form current
- 13:0113:01, 6 December 2016 diff hist +13 Phase V - Construction →Task No. 12 - On-Going Inspections