- 17:10, 19 November 2014 diff hist +568 Phase II - Preliminary Design
- 10:37, 18 November 2014 diff hist 0 File:II-7.docx Jearcher uploaded a new version of "File:II-7.docx"
- 12:14, 17 November 2014 diff hist 0 File:V-7a contractor submittal checklist.xlsx Jearcher uploaded a new version of "File:V-7a contractor submittal checklist.xlsx"
- 08:34, 21 October 2014 diff hist 0 File:V-19a.docx Jearcher uploaded a new version of "File:V-19a.docx"
- 08:36, 6 October 2014 diff hist +35 N File:III-5a.docx Real Property Acquisition Checklist current
- 08:35, 6 October 2014 diff hist +1 Phase III - Final Design →Task No. 5 - Begin Right-of-Way / Easement Negotiations
- 12:36, 3 October 2014 diff hist +27 Phase III - Final Design →Task No. 14 - Submit PS&E Package
- 12:21, 3 October 2014 diff hist −1 Phase III - Final Design →Task No. 10 - Submit Specifications and Special Provisions
- 12:21, 3 October 2014 diff hist −4 Phase III - Final Design →Task No. 10 - Submit Specifications and Special Provisions
- 12:20, 3 October 2014 diff hist −2 Phase III - Final Design →Task No. 10 - Submit Specifications and Special Provisions
- 12:19, 3 October 2014 diff hist +5 Phase III - Final Design →Task No. 10 - Submit Specifications and Special Provisions
- 12:16, 3 October 2014 diff hist +27 Phase III - Final Design →Task No. 9 - Submit Final Plans for Review
- 12:09, 3 October 2014 diff hist +1 Phase III - Final Design →For KDOT (Federally Funded) projects, the City’s Standard Contract Documents shall be supplemented with the following required contract provisions:
- 12:08, 3 October 2014 diff hist −4 Phase III - Final Design →For KDOT (Federally Funded) projects, the City’s Standard Contract Documents shall be supplemented with the following required contract provisions:
- 12:07, 3 October 2014 diff hist +11 Phase III - Final Design →For KDOT (Federally Funded) projects, the City’s Standard Contract Documents shall be supplemented with the following required contract provisions:
- 12:00, 3 October 2014 diff hist +27 Phase III - Final Design →For KDOT (Federally Funded) projects, the City’s Standard Contract Documents shall be supplemented with the following required contract provisions:
- 08:33, 23 September 2014 diff hist +45 N File:IV-2f.docx Material Sampling and Testing Frequency Chart current
- 08:31, 23 September 2014 diff hist +1 Phase V - Construction →Task No. 13 - On-Going Material Testing
- 10:13, 25 August 2014 diff hist +17 N File:VI-1d.docx Project Close Out current
- 10:11, 25 August 2014 diff hist +1 Phase VI - Retrospect →Task No. 1 - Procedures for Final Cost and Project Close Out
- 10:02, 25 August 2014 diff hist +1 Phase IV - Pre-Construction →Task No. 20 - Submit Letting Summary Document to KDOT
- 10:01, 25 August 2014 diff hist 0 File:IV-20b Letting Summary Document.docx Jearcher uploaded a new version of "File:IV-20b Letting Summary Document.docx" current
- 09:41, 25 August 2014 diff hist −1 Phase IV - Pre-Construction →Task No. 20 - Submit Letting Summary Document to KDOT
- 14:58, 15 July 2014 diff hist +35 N File:Sample streetlight removal proposal.pdf Sample streetlight removal proposal current
- 14:58, 15 July 2014 diff hist +54 N File:Sample letter requesting streetlight removal proposals.pdf Sample letter requesting streetlight removal proposals current
- 14:57, 15 July 2014 diff hist +46 N File:Streetlighting removal procedure during design.pdf Streetlighting Removal Procedure During Design
- 14:52, 15 July 2014 diff hist +477 Phase II - Preliminary Design →Task No. 26a - Coordinate Removal of Streetlights Purchased from KCP&L
- 14:42, 15 July 2014 diff hist −13 Phase II - Preliminary Design →Task No. 26a - Coordinate Electrical Service for Traffic Signals and Street Lighting
- 14:40, 15 July 2014 diff hist −584 Phase II - Preliminary Design
- 14:39, 15 July 2014 diff hist −4 Phase II - Preliminary Design →Task No. 28 - Execute Official Agreement with KDOT
- 14:38, 15 July 2014 diff hist 0 Phase II - Preliminary Design →Task No. 26 - Coordinate Electrical Service for Traffic Signals and Street Lighting
- 14:38, 15 July 2014 diff hist +686 Phase II - Preliminary Design
- 14:33, 15 July 2014 diff hist +1 Phase V - Construction →Task No. 11a - Coordinate Removal of Streetlights Purchased from KCP&L
- 14:26, 15 July 2014 diff hist +68 N File:Sample letter to KCP&L informing.pdf Sample letter to KCP&L informing them of the removal of streetlights current
- 14:26, 15 July 2014 diff hist +65 N File:Sample letter to Black & McDonald holding.pdf Sample letter to Black & McDonald holding release of removal work current
- 14:25, 15 July 2014 diff hist +72 N File:Sample letter to Black & McDonald releasing.pdf Sample letter to Black & McDonald releasing removal work to construction current
- 14:24, 15 July 2014 diff hist +52 N File:Streetlighting removal procedure during construction.pdf Streetlighting Removal Procedure During Construction
- 14:17, 15 July 2014 diff hist +1 Phase V - Construction →Task No. 11a - Coordinate Removal of Streetlights Purchased from KCP&L
- 14:16, 15 July 2014 diff hist −2 Phase V - Construction →Task No. 11a - Coordinate Removal of Streetlights Purchased from KCP&L
- 14:16, 15 July 2014 diff hist +1 Phase V - Construction →Task No. 11a - Coordinate Removal of Streetlights Purchased from KCP&L
- 14:15, 15 July 2014 diff hist +71 Phase V - Construction →Task No. 11a - Coordinate Removal of Streetlights Purchased from KCP&L
- 14:08, 15 July 2014 diff hist −123 Phase V - Construction →Task No. 11a - Coordinate Removal of Streetlights Purchased from KCP&L
- 14:06, 15 July 2014 diff hist +179 Phase V - Construction →Task No. 11a - Coordinate Removal of Streetlights Purchased from KCP&L
- 14:03, 15 July 2014 diff hist +1 Phase V - Construction →Task No. 11a - Coordinate Removal of Streetlights Purchased from KCP&L
- 14:03, 15 July 2014 diff hist −33 Phase V - Construction →Task No. 11a - Coordinate Removal of Streetlights Purchased from KCP&L
- 14:01, 15 July 2014 diff hist +158 Phase V - Construction →Task No. 11a - Coordinate Removal of Streetlights Purchased from KCP&L
- 13:58, 15 July 2014 diff hist +1 Phase V - Construction →Task No. 12 - On-Going Inspections
- 13:58, 15 July 2014 diff hist −2 Phase V - Construction →Task No. 12 - On-Going Inspections
- 13:57, 15 July 2014 diff hist −2 Phase V - Construction →Task No. 12 - On-Going Inspections
- 13:56, 15 July 2014 diff hist −3 Phase V - Construction →Task No. 10 - Issue Notice to Proceed