- 09:1509:15, 24 August 2012 diff hist +48 N Planning Bid and Contract Award Schedules Created page with " == Planning Bid and Contract Award Schedules =="
- 09:1509:15, 24 August 2012 diff hist +45 Phase IV - Pre-Construction →Task No. 3 - Set Bid Opening Date - Schedule Room
- 09:0209:02, 24 August 2012 diff hist +1 Phase III - Final Design →Task No. 6 - Begin Condemnation Process
- 09:0209:02, 24 August 2012 diff hist +72 Phase III - Final Design →Task No. 6 - Begin Condemnation Process
- 08:5608:56, 24 August 2012 diff hist −21 Phase III - Final Design →Task No. 6 - Begin Condemnation Process
- 08:5408:54, 24 August 2012 diff hist +9 Phase III - Final Design →Task No. 6 - Begin Condemnation Process
- 08:5208:52, 24 August 2012 diff hist +14 Condemnation Process No edit summary
- 08:5008:50, 24 August 2012 diff hist +9 Condemnation Process No edit summary
- 08:4208:42, 24 August 2012 diff hist +62 Phase IV - Pre-Construction →Task No. 1 - Complete Plans, Specifications and Estimate
- 08:4108:41, 24 August 2012 diff hist −11 Phase IV - Pre-Construction →Task No. 1 - Complete Plans, Specifications and Estimate
- 08:3808:38, 24 August 2012 diff hist +37 Phase IV - Pre-Construction →Task No. 1 - Complete Plans, Specifications and Estimate
23 August 2012
- 11:2311:23, 23 August 2012 diff hist +1 Phase V - Construction →Task No. 12 - On-Going Inspections
- 11:2211:22, 23 August 2012 diff hist 0 Phase V - Construction →Task No. 12 - On-Going Inspections
- 11:2211:22, 23 August 2012 diff hist −19 Phase V - Construction →Task No. 12 - On-Going Inspections
- 11:2111:21, 23 August 2012 diff hist +38 N File:Commercial Building Permit Application.pdf Commercial Building Permit Application
- 11:1911:19, 23 August 2012 diff hist +41 Phase V - Construction →Task No. 12 - On-Going Inspections
- 11:1811:18, 23 August 2012 diff hist +36 N File:V-12 Electrical Service Permit Procedures for Streetlighting Controllers or Traffic Signal Constrollers.pdf Electrical Service Permit Procedures
- 11:1411:14, 23 August 2012 diff hist −23 Phase II - Preliminary Design →Task No. 26 - Coordinate Electrical Service for Traffic Signals and Street Lighting
- 11:1311:13, 23 August 2012 diff hist +37 N File:II-26 Electrical Services Address Procedures.pdf Electrical Service Address Procedures
- 11:0511:05, 23 August 2012 diff hist +3 Phase II - Preliminary Design →Task No. 33 - Prepare R/W and Easement Documents
- 11:0411:04, 23 August 2012 diff hist +134 Phase II - Preliminary Design →Task No. 33 - Prepare R/W and Easement Documents
- 10:3210:32, 23 August 2012 diff hist +1 Phase III - Final Design →Task No. 21- Obtain Agency Plan Approvals
- 09:5009:50, 23 August 2012 diff hist −3 Phase III - Final Design →Task No. 12- Prepare the Engineer’s Cost Estimate
- 09:0409:04, 23 August 2012 diff hist −4 Phase III - Final Design →Task No. 22 - Confirm Construction Engineering Responsibility
- 09:0309:03, 23 August 2012 diff hist 0 Phase III - Final Design →Task No. 21- Obtain Agency Plan Approvals
- 08:5808:58, 23 August 2012 diff hist +2 Phase III - Final Design →Task No. 21- Obtain Agency Plan Approvals
- 08:5608:56, 23 August 2012 diff hist +1 Phase III - Final Design →Task No. 19 - Receive Obligation of Funds from KDOT
- 08:5408:54, 23 August 2012 diff hist −75 Phase III - Final Design →Task No. 18 - Schedule Third Public Information Meeting
- 08:4608:46, 23 August 2012 diff hist −38 Phase III - Final Design →Task No. 18 - Schedule Third Public Information Meeting
- 08:4508:45, 23 August 2012 diff hist −153 Phase III - Final Design →Task No. 17 - Complete Utility Relocations
- 08:4408:44, 23 August 2012 diff hist +1 Phase III - Final Design →Task No. 17 - Complete Utility Relocations
- 08:4408:44, 23 August 2012 diff hist +9 Phase III - Final Design →Task No. 17 - Complete Utility Relocations
- 08:3308:33, 23 August 2012 diff hist +106 Phase III - Final Design →Task No. 14 - Submit PS&E Package
- 08:2808:28, 23 August 2012 diff hist 0 File:III-13a.dot Irina Idelson uploaded a new version of "File:III-13a.dot": KDOT "Design Summary Document" form
22 August 2012
- 16:3716:37, 22 August 2012 diff hist 0 File:III-13b.pdf Irina Idelson uploaded a new version of "File:III-13b.pdf": Example of a completed Design Summary Document
- 16:1416:14, 22 August 2012 diff hist +69 Phase III - Final Design →Task No. 12- Prepare the Engineer’s Cost Estimate
- 16:1116:11, 22 August 2012 diff hist +2 Phase III - Final Design →Task No. 12- Submit the Engineer’s Cost Estimate
- 14:5514:55, 22 August 2012 diff hist 0 Phase III - Final Design →Task No. 11 - Submit Contract Documents and Insurance
- 14:5414:54, 22 August 2012 diff hist −1 Phase III - Final Design →Task No. 15 - PS&E Review
- 14:5414:54, 22 August 2012 diff hist +51 Phase III - Final Design →Task No. 15 - PS&E Review
- 14:4814:48, 22 August 2012 diff hist +33 Phase III - Final Design →Task No. 15 - PS&E Review
- 14:4614:46, 22 August 2012 diff hist +116 Phase III - Final Design →Task No. 15 - PS&E Review
- 14:2414:24, 22 August 2012 diff hist +38 Phase III - Final Design →Task No. 11 - Submit Contract Documents and Insurance
- 14:1814:18, 22 August 2012 diff hist −83 Phase III - Final Design →Task No. 11 - Submit Contract Documents and Insurance
- 14:0414:04, 22 August 2012 diff hist −20 Phase III - Final Design →For CDBG projects, the City’s Standard Contract Documents shall be supplemented with the following:
- 14:0314:03, 22 August 2012 diff hist −9 Phase III - Final Design →For CDBG projects, the City’s Standard Contract Documents shall be supplemented with the following:
- 14:0214:02, 22 August 2012 diff hist −64 Phase III - Final Design →For CDBG projects, the City’s Standard Contract Documents shall be supplemented with the following:
- 13:5113:51, 22 August 2012 diff hist −7 Phase III - Final Design →For CDBG projects, the City’s Standard Contract Documents shall be supplemented with the following:
- 13:4813:48, 22 August 2012 diff hist −33 Phase III - Final Design →For CDBG projects, the City’s Standard Contract Documents shall be supplemented with the following:
- 13:4213:42, 22 August 2012 diff hist −44 Phase III - Final Design →For CDBG projects, the City’s Standard Contract Documents shall be supplemented with the following: