23 August 2012
- 08:5408:54, 23 August 2012 diff hist −75 Phase III - Final Design →Task No. 18 - Schedule Third Public Information Meeting
- 08:4608:46, 23 August 2012 diff hist −38 Phase III - Final Design →Task No. 18 - Schedule Third Public Information Meeting
- 08:4508:45, 23 August 2012 diff hist −153 Phase III - Final Design →Task No. 17 - Complete Utility Relocations
- 08:4408:44, 23 August 2012 diff hist +1 Phase III - Final Design →Task No. 17 - Complete Utility Relocations
- 08:4408:44, 23 August 2012 diff hist +9 Phase III - Final Design →Task No. 17 - Complete Utility Relocations
- 08:3308:33, 23 August 2012 diff hist +106 Phase III - Final Design →Task No. 14 - Submit PS&E Package
- 08:2808:28, 23 August 2012 diff hist 0 File:III-13a.dot Irina Idelson uploaded a new version of "File:III-13a.dot": KDOT "Design Summary Document" form
22 August 2012
- 16:3716:37, 22 August 2012 diff hist 0 File:III-13b.pdf Irina Idelson uploaded a new version of "File:III-13b.pdf": Example of a completed Design Summary Document
- 16:1416:14, 22 August 2012 diff hist +69 Phase III - Final Design →Task No. 12- Prepare the Engineer’s Cost Estimate
- 16:1116:11, 22 August 2012 diff hist +2 Phase III - Final Design →Task No. 12- Submit the Engineer’s Cost Estimate
- 14:5514:55, 22 August 2012 diff hist 0 Phase III - Final Design →Task No. 11 - Submit Contract Documents and Insurance
- 14:5414:54, 22 August 2012 diff hist −1 Phase III - Final Design →Task No. 15 - PS&E Review
- 14:5414:54, 22 August 2012 diff hist +51 Phase III - Final Design →Task No. 15 - PS&E Review
- 14:4814:48, 22 August 2012 diff hist +33 Phase III - Final Design →Task No. 15 - PS&E Review
- 14:4614:46, 22 August 2012 diff hist +116 Phase III - Final Design →Task No. 15 - PS&E Review
- 14:2414:24, 22 August 2012 diff hist +38 Phase III - Final Design →Task No. 11 - Submit Contract Documents and Insurance
- 14:1814:18, 22 August 2012 diff hist −83 Phase III - Final Design →Task No. 11 - Submit Contract Documents and Insurance
- 14:0414:04, 22 August 2012 diff hist −20 Phase III - Final Design →For CDBG projects, the City’s Standard Contract Documents shall be supplemented with the following:
- 14:0314:03, 22 August 2012 diff hist −9 Phase III - Final Design →For CDBG projects, the City’s Standard Contract Documents shall be supplemented with the following:
- 14:0214:02, 22 August 2012 diff hist −64 Phase III - Final Design →For CDBG projects, the City’s Standard Contract Documents shall be supplemented with the following:
- 13:5113:51, 22 August 2012 diff hist −7 Phase III - Final Design →For CDBG projects, the City’s Standard Contract Documents shall be supplemented with the following:
- 13:4813:48, 22 August 2012 diff hist −33 Phase III - Final Design →For CDBG projects, the City’s Standard Contract Documents shall be supplemented with the following:
- 13:4213:42, 22 August 2012 diff hist −44 Phase III - Final Design →For CDBG projects, the City’s Standard Contract Documents shall be supplemented with the following:
- 13:4113:41, 22 August 2012 diff hist −67 Phase III - Final Design →For CDBG projects, the City’s Standard Contract Documents shall be supplemented with the following:
- 13:3813:38, 22 August 2012 diff hist −17 Phase III - Final Design →For CDBG projects, the City’s Standard Contract Documents shall be supplemented with the following:
- 13:1413:14, 22 August 2012 diff hist −20 Phase III - Final Design →For CDBG projects, the City’s Standard Contract Documents shall be supplemented with the following:
- 13:0813:08, 22 August 2012 diff hist −84 Phase III - Final Design →For KDOT (Federally Funded) projects, the City’s Standard Contract Documents shall be supplemented with the following required contract provisions:
- 11:3411:34, 22 August 2012 diff hist 0 File:III-10a.pdf Irina Idelson uploaded a new version of "File:III-10a.pdf": Sample of City Specifications
- 11:2411:24, 22 August 2012 diff hist −29 Phase III - Final Design →Task No. 9 - Submit Final Plans for Review
- 11:2311:23, 22 August 2012 diff hist −1 Phase III - Final Design →Task No. 9 - Submit Final Plans for Review
- 11:2311:23, 22 August 2012 diff hist −100 Phase III - Final Design →Task No. 9 - Submit Final Plans for Review
- 11:2111:21, 22 August 2012 diff hist +414 Phase III - Final Design →Task No. 9 - Submit Final Plans for Review
- 10:3910:39, 22 August 2012 diff hist −78 Phase III - Final Design →Task No. 9 - Submit Final Plans for Review
- 08:5108:51, 22 August 2012 diff hist −248 Phase III - Final Design →Task No. 8 - Acquire Right-of-Way / Easements - Submit KDOT Forms 1306 and 1304
- 08:5008:50, 22 August 2012 diff hist +220 Phase III - Final Design →Task No. 8 - Acquire Right-of-Way / Easements - Submit KDOT Forms 1306 and 1304
- 08:4308:43, 22 August 2012 diff hist 0 Phase III - Final Design →Task No. 8 - Acquire Right-of-Way / Easements - Submit KDOT Forms 1306 and 1304
- 08:4208:42, 22 August 2012 diff hist +29 N File:III-6a.pdf Irina Idelson moved page File:III-6a.pdf to File:III-8a.pdf current
- 08:4208:42, 22 August 2012 diff hist 0 m File:III-8a.pdf Irina Idelson moved page File:III-6a.pdf to File:III-8a.pdf
- 08:3708:37, 22 August 2012 diff hist +1 Phase III - Final Design →Task No. 8 - Acquire R/W / Easement - Submit KDOT Forms 1306 and 1304 {{KDOT}}
21 August 2012
- 17:1717:17, 21 August 2012 diff hist +86 Condemnation Process No edit summary
- 17:1517:15, 21 August 2012 diff hist −1 Condemnation Process No edit summary
- 17:1517:15, 21 August 2012 diff hist +1,712 N Condemnation Process Created page with " Steps in the Eminent Domain Process Involving Public Works In order to begin the condemnation process, the Law Department needs Public Works to provide the following: #Le..."
- 17:1317:13, 21 August 2012 diff hist −19 Phase III - Final Design →Task No. 6 - Begin Condemnation Process
- 16:2416:24, 21 August 2012 diff hist +7 Phase III - Final Design →Task No. 5 - Begin Right-of-Way / Easement Negotiations
- 16:2316:23, 21 August 2012 diff hist −100 Phase III - Final Design →Task No. 5 - Begin Right-of-Way / Easement Negotiations
- 16:2216:22, 21 August 2012 diff hist +101 Phase III - Final Design →Task No. 5 - Begin Right-of-Way / Easement Negotiations
- 16:1716:17, 21 August 2012 diff hist −515 Phase III - Final Design →Task No. 5 - Begin Right-of-Way / Easement Negotiations
- 16:1616:16, 21 August 2012 diff hist −28 Phase III - Final Design →Task No. 5 - Begin Right-of-Way / Easement Negotiations
- 16:0716:07, 21 August 2012 diff hist −4 Phase III - Final Design →Task No. 5 - Begin Right-of-Way / Easement Negotiations
- 16:0616:06, 21 August 2012 diff hist +2 Phase III - Final Design →Task No. 5 - Begin Right-of-Way / Easement Negotiations