User contributions for Joe Archer
Jump to navigation
Jump to search
This user is currently blocked. The latest block log entry is provided below for reference:
- 15:06, 5 July 2024 Dan Hurley talk contribs blocked Joe Archer talk contribs with an expiration time of indefinite (account creation disabled, autoblock disabled, email disabled, cannot edit own talk page) (No longer employed)
- 10:06, 1 August 2012 diff hist +31 N File:III-11a-7.docx Labor and Material Payment Bond
- 10:06, 1 August 2012 diff hist +5 Phase III - Final Design →Task No. 11 - Submit Contract Documents and Insurance
- 09:50, 1 August 2012 diff hist +17 N File:III-11a-5.docx Insurance Options
- 09:50, 1 August 2012 diff hist +1 Phase III - Final Design →Task No. 11 - Submit Contract Documents and Insurance
- 09:39, 1 August 2012 diff hist +3 N File:III-11a-2.docx Bid
- 09:38, 1 August 2012 diff hist +1 Phase III - Final Design →Task No. 11 - Submit Contract Documents and Insurance
- 15:00, 4 June 2012 diff hist +4 Phase IV - Pre-Construction →Task No. 6 - Distribute Plans, Contract Documents and Estimate
- 15:00, 4 June 2012 diff hist +4 Phase IV - Pre-Construction →Task No. 6 - Distribute Plans, Contract Documents and Estimate
- 14:59, 4 June 2012 diff hist −5 Phase IV - Pre-Construction →Task No. 6 - Distribute Plans, Contract Documents and Estimate
- 14:59, 4 June 2012 diff hist 0 Phase IV - Pre-Construction →Task No. 6 - Distribute Plans, Contract Documents and Estimate
- 14:58, 4 June 2012 diff hist +8 Phase IV - Pre-Construction →Task No. 6 - Distribute Plans, Contract Documents and Estimate
- 14:55, 4 June 2012 diff hist +1 Phase IV - Pre-Construction →Task No. 6 - Distribute Plans, Contract Documents and Estimate
- 14:54, 4 June 2012 diff hist −1 Phase IV - Pre-Construction →Task No. 6 - Distribute Plans, Contract Documents and Estimate
- 14:53, 4 June 2012 diff hist −54 Phase IV - Pre-Construction →Task No. 6 - Distribute Plans, Contract Documents and Estimate
- 14:52, 4 June 2012 diff hist +46 Phase IV - Pre-Construction →Task No. 6 - Distribute Plans, Contract Documents and Estimate
- 14:51, 4 June 2012 diff hist −1 Phase IV - Pre-Construction →Task No. 6 - Distribute Plans, Contract Documents and Estimate
- 14:50, 4 June 2012 diff hist +1 Phase IV - Pre-Construction →Task No. 6 - Distribute Plans, Contract Documents and Estimate
- 14:50, 4 June 2012 diff hist 0 Phase IV - Pre-Construction →Task No. 6 - Distribute Plans, Contract Documents and Estimate
- 14:48, 4 June 2012 diff hist 0 Phase IV - Pre-Construction →Task No. 6 - Distribute Plans, Contract Documents and Estimate
- 14:31, 4 June 2012 diff hist 0 File:IV-5l.doc Jearcher uploaded a new version of "File:IV-5l.doc": list of plan rooms associated with DBE contractors
- 09:20, 16 May 2012 diff hist 0 File:II-9.dot uploaded a new version of "File:II-9.dot": list of Johnson County utility and pipeline companies, possible contacts, address and phone numbers current
- 14:52, 7 May 2012 diff hist +24 Phase II - Preliminary Design →Task No. 34 - Prepare R/W and Easement Documents
- 14:51, 7 May 2012 diff hist +1 Phase II - Preliminary Design →Task No. 34 - Prepare R/W and Easement Documents
- 14:50, 7 May 2012 diff hist +3 Phase II - Preliminary Design →Task No. 34 - Prepare R/W and Easement Documents
- 14:45, 7 May 2012 diff hist +30 N File:Administrative Settlement Form.dot Administrative Settlement Form
- 14:40, 7 May 2012 diff hist +78 Phase II - Preliminary Design →Task No. 34 - Prepare R/W and Easement Documents
- 08:33, 23 April 2012 diff hist 0 File:II-3b(2).dot uploaded a new version of "File:II-3b(2).dot": City’s standard Supplemental Agreement for Professional Engineering Services. (Second and beyond
- 08:32, 23 April 2012 diff hist 0 File:II-3b(1).dot uploaded a new version of "File:II-3b(1).dot": City’s standard Supplemental Agreement for Professional Engineering Services. (First
- 15:23, 17 April 2012 diff hist 0 File:I-1.pdf uploaded a new version of "File:I-1a.pdf": Standard Bid Items
- 15:14, 17 April 2012 diff hist 0 Phase I - Vision →Task 1 - Prepare Preliminary Plans/Cost Estimate
- 18:09, 7 March 2012 diff hist 0 File:III-9a-3.dot uploaded a new version of "File:III-9a-3.dot": General Conditions for contracts over $50k
- 16:26, 28 February 2012 diff hist 0 File:II-3-4b.dot uploaded a new version of "File:II-3-4b.dot": Std. Engineering/Architectural agreement current
- 13:04, 22 February 2012 diff hist 0 File:IV-5l.doc uploaded a new version of "File:IV-5l.doc": list of plan rooms associated with DBE contractors
- 12:15, 6 February 2012 diff hist 0 File:III-9a-8a.dot uploaded a new version of "File:III-9a-8a.dot": Maintenance Bond for contracts over $50k
- 12:15, 6 February 2012 diff hist 0 File:III-11a-8.dot uploaded a new version of "File:III-9a-8.dot": Performance Bond for contracts over $50k
- 12:13, 6 February 2012 diff hist +35 N File:III-9a-8a.dot Performance Bond contracts over 50k
- 12:11, 6 February 2012 diff hist +57 Phase III - Final Design →100px Task No. 9 - Submit Contract Documents and Insurance
- 12:05, 6 February 2012 diff hist 0 File:III-9a-4c.dot uploaded a new version of "File:III-9a-4c.dot": Instructions to bidders Option C for contracts over $50k
- 12:04, 6 February 2012 diff hist 0 File:III-9a-4b.dot uploaded a new version of "File:III-9a-4b.dot": Instructions to bidders Option B for contracts over $50k
- 12:03, 6 February 2012 diff hist 0 File:III-9a-4a.dot uploaded a new version of "File:III-9a-4a.dot": Instructions to bidders Option A for contracts over $50k
- 12:02, 6 February 2012 diff hist 0 File:III-9a-3.dot uploaded a new version of "File:III-9a-3.dot": General Conditions for contracts over $50k
- 11:52, 6 February 2012 diff hist 0 File:III-11a-2.dot uploaded a new version of "File:III-9a-2.dot": Bid for contracts over $50k
- 11:49, 6 February 2012 diff hist 0 File:III-11a-1.dot uploaded a new version of "File:III-9a-1.dot": Agreement for contracts over $50k
- 10:58, 6 February 2012 diff hist −112 Phase III - Final Design →100px Task No. 9 - Submit Contract Documents and Insurance
- 10:52, 6 February 2012 diff hist +7 Phase III - Final Design →100px Task No. 9 - Submit Contract Documents and Insurance
- 10:50, 6 February 2012 diff hist −7 Phase III - Final Design →100px Task No. 9 - Submit Contract Documents and Insurance
- 10:39, 6 February 2012 diff hist −8 Phase III - Final Design →100px Task No. 9 - Submit Contract Documents and Insurance
- 10:39, 6 February 2012 diff hist −38 Phase III - Final Design →100px Task No. 9 - Submit Contract Documents and Insurance
- 10:25, 6 February 2012 diff hist 0 Phase III - Final Design →100px Task No. 9 - Submit Contract Documents and Insurance
- 10:24, 6 February 2012 diff hist +28 Phase III - Final Design →100px Task No. 9 - Submit Contract Documents and Insurance