- 08:3608:36, 25 July 2012 diff hist +1 Phase II - Preliminary Design →Task No. 17 - Begin Geotechnical Report Process
- 08:3508:35, 25 July 2012 diff hist +47 N File:IV-2a.docx Material Testing/Geotechnical Service Companies
- 08:1708:17, 25 July 2012 diff hist +9 Phase II - Preliminary Design →Task No. 15 - Schedule First Public Information Meeting
- 08:1608:16, 25 July 2012 diff hist +6 Phase II - Preliminary Design →Task No. 15 - Schedule First Public Information Meeting
- 08:1508:15, 25 July 2012 diff hist +22 N File:II-15d flyer.pdf Publoc Meeting Handout
- 08:1108:11, 25 July 2012 diff hist +23 Phase II - Preliminary Design →Task No. 15 - Schedule First Public Information Meeting
- 08:0708:07, 25 July 2012 diff hist 0 File:II-15c.dot Irina Idelson uploaded a new version of "File:II-15c.dot": Public Meeting Citizen Comment Form
- 07:4607:46, 25 July 2012 diff hist 0 File:II-15a.dot Irina Idelson uploaded a new version of "File:II-15a.dot": Notice of Public Information Meeting
- 07:4107:41, 25 July 2012 diff hist 0 File:II-15.dot Irina Idelson uploaded a new version of "File:II-15.dot": 1st Public Meeting Invitation
- 07:3007:30, 25 July 2012 diff hist −5 Phase II - Preliminary Design →Task No. 15 - Schedule First Public Information Meeting
- 07:3007:30, 25 July 2012 diff hist −5 Phase III - Final Design →Task No. 18 - Schedule Third Public Information Meeting
24 July 2012
- 15:5815:58, 24 July 2012 diff hist +1 Phase II - Preliminary Design →Task No. 14 - Continue Environmental Process
- 15:5815:58, 24 July 2012 diff hist +98 Phase II - Preliminary Design →Task No. 14 - Continue Environmental Process
- 15:5415:54, 24 July 2012 diff hist +26 Phase II - Preliminary Design →Task No. 14 - Continue Environmental Process
- 15:5315:53, 24 July 2012 diff hist +32 Phase II - Preliminary Design →Task No. 14 - Continue Environmental Process
- 15:4615:46, 24 July 2012 diff hist 0 Phase II - Preliminary Design →Task No. 14 - Continue Environmental Process
- 15:4515:45, 24 July 2012 diff hist −10 Phase II - Preliminary Design →Task No. 13 - Conduct Field Surveys
- 15:4215:42, 24 July 2012 diff hist +19 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 15:3215:32, 24 July 2012 diff hist −4 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 15:3215:32, 24 July 2012 diff hist +28 N File:II-11e.pdf Irina Idelson moved page File:II-11e.pdf to File:II-9d.pdf current
- 15:3215:32, 24 July 2012 diff hist 0 m File:II-9d.pdf Irina Idelson moved page File:II-11e.pdf to File:II-9d.pdf
- 15:3115:31, 24 July 2012 diff hist +28 N File:II-11d.pdf Irina Idelson moved page File:II-11d.pdf to File:II-9c.pdf current
- 15:3115:31, 24 July 2012 diff hist 0 m File:II-9c.pdf Irina Idelson moved page File:II-11d.pdf to File:II-9c.pdf
- 15:2915:29, 24 July 2012 diff hist −2 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 15:2915:29, 24 July 2012 diff hist +28 N File:II-11c.pdf Irina Idelson moved page File:II-11c.pdf to File:II-9b.pdf current
- 15:2915:29, 24 July 2012 diff hist 0 m File:II-9b.pdf Irina Idelson moved page File:II-11c.pdf to File:II-9b.pdf
- 15:2715:27, 24 July 2012 diff hist −2 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 15:2715:27, 24 July 2012 diff hist +28 N File:II-11b.dot Irina Idelson moved page File:II-11b.dot to File:II-9a.dot current
- 15:2715:27, 24 July 2012 diff hist 0 m File:II-9a.dot Irina Idelson moved page File:II-11b.dot to File:II-9a.dot
- 15:0715:07, 24 July 2012 diff hist 0 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 15:0315:03, 24 July 2012 diff hist −5 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 14:5914:59, 24 July 2012 diff hist 0 File:II-7n.pdf Irina Idelson uploaded a new version of "File:II-7n.pdf": Service Territory Map current
- 14:4614:46, 24 July 2012 diff hist +20 Phase II - Preliminary Design →Task No. 7 - Schedule First Utility Meeting
- 14:4314:43, 24 July 2012 diff hist 0 Phase II - Preliminary Design →Task No. 7 - Schedule First Utility Meeting
- 14:3414:34, 24 July 2012 diff hist −32 Phase II - Preliminary Design →Task No. 4 - Submit Project Description to Law Department. Execute Ordinances-Resolution.
- 14:3314:33, 24 July 2012 diff hist +2 Phase II - Preliminary Design →Task No. 4 - Submit Project Description to Law Department. Execute Ordinances-Resolution.
- 14:3314:33, 24 July 2012 diff hist −120 Phase II - Preliminary Design →Task No. 4 - Submit Project Description to Law Department. Execute Ordinances-Resolution.
- 14:2814:28, 24 July 2012 diff hist +16 Phase II - Preliminary Design →Task No. 3 - Consultant Selection/Certification
- 14:2514:25, 24 July 2012 diff hist 0 File:II-3c(1).dot Irina Idelson uploaded a new version of "File:II-3c(1).dot": Supplemental to consulting services agreement
- 14:2314:23, 24 July 2012 diff hist 0 File:II-3c.dot Irina Idelson uploaded a new version of "File:II-3c.dot": Consultant Agreement for non-design projects
- 14:2214:22, 24 July 2012 diff hist 0 File:II-3c.dot Irina Idelson uploaded a new version of "File:II-3c.dot": Cosultant Agreement for non-design projects
- 14:2014:20, 24 July 2012 diff hist 0 File:II-3b(2).dot Irina Idelson uploaded a new version of "File:II-3b(2).dot": Supplemental to Engineering/Architectural Services Agreement (Second and Beyond)
- 14:1814:18, 24 July 2012 diff hist 0 File:II-3b(2).dot Irina Idelson uploaded a new version of "File:II-3b(2).dot": Suuplemental to Engineering/Archtectural Services Agreement (Second and Beyond)
- 14:1714:17, 24 July 2012 diff hist 0 File:II-3b(1).dot Irina Idelson uploaded a new version of "File:II-3b(1).dot": Supplemental to Engineering Services Agreement (First)
- 14:0814:08, 24 July 2012 diff hist 0 File:II-3b.dot Irina Idelson uploaded a new version of "File:II-3b.dot": Engineering / Architectural Services Agreement
- 13:5513:55, 24 July 2012 diff hist 0 Phase V - Construction →Task No. 16 - On-Going Construction Administration
- 13:4113:41, 24 July 2012 diff hist 0 Phase I - Vision →Task 11 - Execute Local Project Agreements
- 13:4113:41, 24 July 2012 diff hist +31 N File:V-16c.pdf Staff Billing Report to Finance
- 13:3013:30, 24 July 2012 diff hist −485 Phase I - Vision →Task 15 - Submit City Request to KDOT to Administer Federal Funded Projects
- 13:2913:29, 24 July 2012 diff hist +3 Phase I - Vision →Task 13 Submit KDOT Form 1302 for Project Request. Submit City's Request to Administer the Project