- 14:24, 9 July 2012 diff hist −119 Phase V - Construction →Task No. 10 - Issue Notice to Proceed
- 14:24, 9 July 2012 diff hist 0 Phase V - Construction →Task No. 10 - Issue Notice to Proceed
- 14:23, 9 July 2012 diff hist +1 Phase V - Construction →Task No. 10 - Issue Notice to Proceed
- 14:21, 9 July 2012 diff hist +81 Phase V - Construction →Task No. 10 - Issue Notice to Proceed
- 14:18, 9 July 2012 diff hist +85 Phase V - Construction →Task No. 10 - Issue Notice to Proceed
- 14:08, 9 July 2012 diff hist +19 Phase V - Construction →Task No. 10 - Issue Notice to Proceed
- 14:07, 9 July 2012 diff hist +36 N File:V-10 notice to proceed.docx Notice to Proceed to the Contractior
- 14:05, 9 July 2012 diff hist +55 Phase V - Construction →Task No. 10 - Issue Notice to Proceed
- 13:58, 9 July 2012 diff hist −39 Phase V - Construction →Task No. 9 - Send Information Letter to Residents. Schedule 4th Public Information Meeting.
- 13:53, 9 July 2012 diff hist −40 Phase V - Construction →Task No. 9 - Send Information Letter to Residents. Schedule 4th Public Information Meeting.
- 13:52, 9 July 2012 diff hist +27 N File:V-9b.dot Irina Idelson moved page File:V-9b.dot to File:V-9c.dot current
- 13:52, 9 July 2012 diff hist 0 m File:V-9c.dot Irina Idelson moved page File:V-9b.dot to File:V-9c.dot
- 13:49, 9 July 2012 diff hist −18 Phase V - Construction →Task No. 9 - Send Information Letter to Residents. Schedule 4th Public Information Meeting.
- 13:47, 9 July 2012 diff hist +36 N File:V-9b public meeting notice.pdf Notice of Public Information Meeting
- 13:45, 9 July 2012 diff hist +1 Phase V - Construction →Task No. 9 - Send Information Letter to Residents. Schedule 4th Public Information Meeting.
- 13:44, 9 July 2012 diff hist −6 Phase V - Construction →Task No. 9 - Send Information Letter to Residents. Schedule 4th Public Information Meeting.
- 13:43, 9 July 2012 diff hist −8 Phase V - Construction →Task No. 9 - Send Information Letter to Residents. Schedule 4th Public Information Meeting.
- 13:42, 9 July 2012 diff hist +4 Phase V - Construction →Task No. 9 - Send Information Letter to Residents. Schedule 4th Public Information Meeting.
- 13:41, 9 July 2012 diff hist −2 Phase V - Construction →Task No. 9 - Send Information Letter to Residents. Schedule 4th Public Information Meeting.
- 13:37, 9 July 2012 diff hist 0 File:V-9a public meeting invitation.docx Irina Idelson uploaded a new version of "File:V-9a public meeting invitation.docx": Public Meeting Invitation
- 13:37, 9 July 2012 diff hist 0 N File:V-9a public meeting invitation.docx
- 13:35, 9 July 2012 diff hist −101 Phase V - Construction →Task No. 9 - Send Information Letter to Residents. Schedule 4th Public Information Meeting.
- 13:35, 9 July 2012 diff hist +1 Phase V - Construction →Task No. 9 - Send Information Letter to Residents. Schedule 4th Public Information Meeting.
- 13:34, 9 July 2012 diff hist +63 Phase V - Construction →Task No. 9 - Send Information Letter to Residents. Schedule 4th Public Information Meeting.
- 13:29, 9 July 2012 diff hist −41 Phase V - Construction →Task No. 9 - Send Information Letter to Residents. Schedule 4th Public Information Meeting.
- 13:29, 9 July 2012 diff hist +121 Phase V - Construction →Task No. 9 - Send Information Letter to Residents. Schedule 4th Public Information Meeting.
- 13:28, 9 July 2012 diff hist +2 Phase III - Final Design →Task No. 18 - Schedule Third Public Information Meeting
- 13:26, 9 July 2012 diff hist −446 Phase V - Construction →Task No. 9 - Send Information Letter to Residents. Schedule 4th Public Information Meeting.
- 11:34, 9 July 2012 diff hist +1 Phase V - Construction →Task No. 7 - Schedule Pre-Construction Conference/Project Sign Confirmation
- 11:13, 9 July 2012 diff hist 0 Phase V - Construction →Task No. 4 - Distribute Executed Contract Documents
- 11:04, 9 July 2012 diff hist −43 Phase V - Construction →Task No. 4 - Distribute Executed Contract Documents
- 11:03, 9 July 2012 diff hist +49 Phase V - Construction →Task No. 4 - Distribute Executed Contract Documents
- 10:57, 9 July 2012 diff hist +4 Phase V - Construction →Task No. 4 - Distribute Executed Contract Documents
- 10:56, 9 July 2012 diff hist −38 Phase V - Construction →Task No. 4 - Distribute Executed Contract Documents
- 16:57, 5 July 2012 diff hist −4 Phase V - Construction →Task No. 9 - Send Information Letter to Residents. Schedule 4th Public Information Meeting.
- 16:55, 5 July 2012 diff hist 0 Phase V - Construction →Task No. 8 - Send Information Letter to Residents. Schedule 4th Public Information Meeting.
- 16:55, 5 July 2012 diff hist −1,779 Phase V - Construction →Task No. 9 - Schedule 4th Public Information Meeting
- 16:55, 5 July 2012 diff hist +1,712 Phase V - Construction →Task No. 8 - Send Information Letter to Residents. Schedule 4th Public Information Meeting.
- 16:54, 5 July 2012 diff hist +42 Phase V - Construction →Task No. 8 - Send Information Letter to Residents
- 16:27, 5 July 2012 diff hist +1 Phase V - Construction →Task No. 7 - Schedule Pre-Construction Conference/Project Sign Confirmation
- 16:25, 5 July 2012 diff hist −52 Phase V - Construction →Task No. 7 - Schedule Pre-Construction Conference/Project Sign Confirmation
- 16:23, 5 July 2012 diff hist +2 Phase V - Construction →Task No. 7 - Schedule Pre-Construction Conference/Project Sign Confirmation
- 16:23, 5 July 2012 diff hist +59 N File:V-7 contractor submittal checklist.xlsx Irina Idelson moved page File:V-7 contractor submittal checklist.xlsx to File:V-7a contractor submittal checklist.xlsx current
- 16:23, 5 July 2012 diff hist 0 m File:V-7a contractor submittal checklist.xlsx Irina Idelson moved page File:V-7 contractor submittal checklist.xlsx to File:V-7a contractor submittal checklist.xlsx
- 16:22, 5 July 2012 diff hist +99 Phase V - Construction →Task No. 7 - Schedule Pre-Construction Conference/Project Sign Confirmation
- 16:18, 5 July 2012 diff hist +31 N File:V-7a contractor submittal checklist.xlsx contractors submittal checklist
- 16:16, 5 July 2012 diff hist −8 Phase V - Construction →Task No. 7 - Schedule Pre-Construction Conference/Project Sign Confirmation
- 16:15, 5 July 2012 diff hist −27 Phase V - Construction →Task No. 7 - Schedule Pre-Construction Conference/Project Sign Confirmation
- 16:14, 5 July 2012 diff hist +27 N File:V-7a.dot Irina Idelson moved page File:V-7a.dot to File:V-7b.dot current
- 16:14, 5 July 2012 diff hist 0 m File:V-7b.dot Irina Idelson moved page File:V-7a.dot to File:V-7b.dot