- 10:1310:13, 29 June 2012 diff hist 0 Phase IV - Pre-Construction →Task No. 19 - Award Contract by City Council
- 10:1110:11, 29 June 2012 diff hist −162 Phase IV - Pre-Construction →Task No. 19 - Award Contract by City Council
- 10:1010:10, 29 June 2012 diff hist +163 Phase IV - Pre-Construction →Task No. 19 - Award Contract by City Council
- 10:0910:09, 29 June 2012 diff hist 0 Phase IV - Pre-Construction →Task No. 19 - Award Contract by City Council
- 10:0810:08, 29 June 2012 diff hist 0 Phase IV - Pre-Construction →Task No. 19 - Award Contract by City Council
- 10:0710:07, 29 June 2012 diff hist 0 Phase IV - Pre-Construction →Task No. 20 - Submit Letting Summary Document to KDOT
- 10:0410:04, 29 June 2012 diff hist 0 Phase IV - Pre-Construction →Task No. 17 - Receive Concurrence and Award from KDOT
- 10:0310:03, 29 June 2012 diff hist 0 Phase IV - Pre-Construction →Task No. 17 - Receive Concurrence and Award from KDOT
- 10:0310:03, 29 June 2012 diff hist +28 N File:Iv-19.pdf Irina Idelson moved page File:Iv-19.pdf to File:IV-17.pdf current
- 09:1109:11, 29 June 2012 diff hist 0 Phase IV - Pre-Construction →Task No. 18 - Submit Staff Recommendation for Contract Award
- 09:1009:10, 29 June 2012 diff hist +29 N File:IV-16a.pdf Irina Idelson moved page File:IV-16a.pdf to File:IV-18a.pdf
- 09:1009:10, 29 June 2012 diff hist 0 m File:IV-18a.pdf Irina Idelson moved page File:IV-16a.pdf to File:IV-18a.pdf
- 09:0409:04, 29 June 2012 diff hist +1 Phase IV - Pre-Construction →Task No. 16 - Receive Bid Approval from KDOT
- 09:0209:02, 29 June 2012 diff hist +29 N File:Iv-18a.dot Irina Idelson moved page File:Iv-18a.dot to File:IV-16a.dot current
- 09:0209:02, 29 June 2012 diff hist 0 m File:IV-16a.dot Irina Idelson moved page File:Iv-18a.dot to File:IV-16a.dot
- 08:5108:51, 29 June 2012 diff hist −540 Phase IV - Pre-Construction →Task No. 19 - Receive Concurrence and Award from KDOT
- 08:5008:50, 29 June 2012 diff hist 0 Phase IV - Pre-Construction →Task No. 17 - Award Contract by City Council
- 08:4908:49, 29 June 2012 diff hist 0 Phase IV - Pre-Construction →Task No. 16 - Submit Staff Recommendation for Contract Award
- 08:4808:48, 29 June 2012 diff hist +539 Phase IV - Pre-Construction →Task No. 16 - Receive Bid Approval from KDOT
- 08:4708:47, 29 June 2012 diff hist −477 Phase IV - Pre-Construction →Task No. 18 - Receive Bid Approval from KDOT
- 08:4608:46, 29 June 2012 diff hist 0 Phase IV - Pre-Construction →Task No. 18 - Receive Bid Approval from KDOT
- 08:4608:46, 29 June 2012 diff hist +476 Phase IV - Pre-Construction →Task No. 15 - Obtain Project Temporary Financing
28 June 2012
- 17:0817:08, 28 June 2012 diff hist 0 Phase IV - Pre-Construction →Task No. 12 - Determine and Approve the Lowest and Best Qualified Contractor and Sub-Contractor Percent of Work
- 17:0417:04, 28 June 2012 diff hist 0 Phase IV - Pre-Construction →Task No. 12 - Determine and Approve the Lowest and Best Qualified Contractor and Sub-Contractor Percent of Work
- 17:0317:03, 28 June 2012 diff hist +20 Phase IV - Pre-Construction →Task No. 12 - Determine and Approve the Lowest and Best Qualified Contractor and Sub-Contractor Percent of Work
- 16:5816:58, 28 June 2012 diff hist −136 Phase IV - Pre-Construction →Task No. 12 - Determine and Approve the Lowest and Best Qualified Contractor and Sub-Contractor Percent of Work
- 16:5616:56, 28 June 2012 diff hist +30 N File:15.0 LPA-Administered Procedures 10-2011.pdf LPA Project Development Manual
- 16:5516:55, 28 June 2012 diff hist +348 Phase IV - Pre-Construction →Task No. 12 - Determine and Approve the Lowest and Best Qualified Contractor and Sub-Contractor Percent of Work
- 16:4016:40, 28 June 2012 diff hist −857 Phase IV - Pre-Construction →Task No. 14 - Evaluate Possible Contractor Collusion
- 16:4016:40, 28 June 2012 diff hist 0 Phase IV - Pre-Construction →Task No. 13 - Determine Disadvantaged Business Enterprises (DBE) Involvement
- 16:4016:40, 28 June 2012 diff hist 0 Phase IV - Pre-Construction →Task No. 14 - Evaluate Possible Contractor Collusion
- 16:3916:39, 28 June 2012 diff hist +857 Phase IV - Pre-Construction →Task No. 13 - Determine Disadvantaged Business Enterprises (DBE) Involvement
- 16:2916:29, 28 June 2012 diff hist 0 Phase IV - Pre-Construction →Task No. 12 - Determine and Approve the Lowest and Best Qualified Contractor and Sub-Contractor Percent of Work
- 16:2916:29, 28 June 2012 diff hist 0 Phase IV - Pre-Construction →Task No. 12 - Determine and Approve the Lowest and Best Qualified Contractor and Sub-Contractor Percent of Work
- 16:2016:20, 28 June 2012 diff hist +2 Phase IV - Pre-Construction →Task No. 11 - Complete Detailed Bid Tabulation
- 16:1916:19, 28 June 2012 diff hist +30 N File:IV-11.xlsx sample detailed bid tabulation
- 16:0916:09, 28 June 2012 diff hist 0 File:IV-11.xlt Irina Idelson uploaded a new version of "File:IV-11.xlt": sample detailed bid tabulation
- 16:0316:03, 28 June 2012 diff hist 0 File:IV-11.xlt Irina Idelson uploaded a new version of "File:IV-11.xlt": sample bid tabulation form
- 16:0016:00, 28 June 2012 diff hist 0 File:IV-10.dot Irina Idelson uploaded a new version of "File:IV-10.dot": sample bid tabulation form
- 15:4815:48, 28 June 2012 diff hist +9 Phase IV - Pre-Construction →Task No. 9 - Prepare Contract Addendum
- 15:4715:47, 28 June 2012 diff hist +2 Phase IV - Pre-Construction →Task No. 9 - Prepare Contract Document/Addendum
- 15:2415:24, 28 June 2012 diff hist 0 File:IV-7.dot Irina Idelson uploaded a new version of "File:IV-7.dot"
- 15:1915:19, 28 June 2012 diff hist +8 Phase IV - Pre-Construction →Task No. 6 - Distribute Plans, Contract Documents and Estimate
- 15:1915:19, 28 June 2012 diff hist +37 N File:Exhibit IV-6.docx Engineer's construction cost estimate
- 15:1715:17, 28 June 2012 diff hist 0 Phase IV - Pre-Construction →Task No. 6 - Distribute Plans, Contract Documents and Estimate
- 15:1615:16, 28 June 2012 diff hist 0 N File:Exibit IV-6.docx No edit summary
- 15:0315:03, 28 June 2012 diff hist 0 File:IV-6.dot Irina Idelson uploaded a new version of "File:IV-6.dot"
- 14:1814:18, 28 June 2012 diff hist −13 Phase III - Final Design →Task No. 11 - Submit Contract Documents and Insurance
- 14:1614:16, 28 June 2012 diff hist 0 File:III-11a-2a Bid-KDOT.docx Irina Idelson uploaded a new version of "File:III-11a-2a Bid-KDOT.docx"
- 14:1414:14, 28 June 2012 diff hist 0 File:III-11a-6 Notice to Bidders.docx Irina Idelson uploaded a new version of "File:III-11a-6 Notice to Bidders.docx"