User contributions for Irina Idelson
Results for Irina Idelson talk block log uploads logs
A user with 4,241 edits. Account created on 9 April 2012.
8 June 2012
- 12:4912:49, 8 June 2012 diff hist +30 N File:III-14b.pdf Irina Idelson moved page File:III-14b.pdf to File:III-13b.pdf current
- 12:4912:49, 8 June 2012 diff hist 0 m File:III-13b.pdf Irina Idelson moved page File:III-14b.pdf to File:III-13b.pdf
- 12:4712:47, 8 June 2012 diff hist +30 N File:III-16b.pdf Irina Idelson moved page File:III-16b.pdf to File:III-14b.pdf current
- 12:4712:47, 8 June 2012 diff hist 0 m File:III-13b.pdf Irina Idelson moved page File:III-16b.pdf to File:III-14b.pdf
- 12:4712:47, 8 June 2012 diff hist +30 N File:III-16a.dot Irina Idelson moved page File:III-16a.dot to File:III-14a.dot current
- 12:4712:47, 8 June 2012 diff hist 0 m File:III-13a.dot Irina Idelson moved page File:III-16a.dot to File:III-14a.dot
- 12:2712:27, 8 June 2012 diff hist +2 Phase III - Final Design →Task No. 13 - Prepare Design Summary Document
- 12:2612:26, 8 June 2012 diff hist +129 Phase III - Final Design →Task No. 13 - Prepare Design Summary Document
- 12:2312:23, 8 June 2012 diff hist −14 Phase III - Final Design →Task No. 13 - Prepare Design Summary Document
- 12:2112:21, 8 June 2012 diff hist −18 Phase III - Final Design →Task No. 13 - Prepare Design Summary Document
- 12:1112:11, 8 June 2012 diff hist −113 Phase III - Final Design →Task No. 14 - Submit PS&E Package
- 12:1012:10, 8 June 2012 diff hist +86 Phase III - Final Design →Task No. 14 - Submit PS&E Package
- 12:1012:10, 8 June 2012 diff hist +2 Phase III - Final Design →Task No. 14 - Submit PS&E Package
- 12:1012:10, 8 June 2012 diff hist +30 Phase III - Final Design →Task No. 14 - Submit PS&E Package
- 12:0312:03, 8 June 2012 diff hist 0 N File:Form1307.pdf No edit summary
- 12:0112:01, 8 June 2012 diff hist +81 Phase III - Final Design →Task No. 14 - Submit PS&E Package
- 10:5510:55, 8 June 2012 diff hist −3 Phase III - Final Design →Task No. 17 - Complete Utility Relocations
- 10:5410:54, 8 June 2012 diff hist −80 Phase III - Final Design →Task No. 17 - Complete Utility Relocations
- 10:5410:54, 8 June 2012 diff hist +138 Phase III - Final Design →Task No. 17 - Complete Utility Relocations
- 10:5110:51, 8 June 2012 diff hist 0 Phase III - Final Design →Task No. 15 - PS&E Review
- 10:5110:51, 8 June 2012 diff hist −24 Phase III - Final Design →Task No. 15 - PS&E Review
- 10:4910:49, 8 June 2012 diff hist +84 Phase III - Final Design →Task No. 15 - PS&E Review
- 10:4010:40, 8 June 2012 diff hist +9 Phase III - Final Design →Task No. 15 - PS&E Review
- 10:4010:40, 8 June 2012 diff hist +1 Phase III - Final Design →Task No. 14 - Submit PS&E Package
- 10:4010:40, 8 June 2012 diff hist +6 Phase III - Final Design →Task No. 14 - Submit PS&E Package
- 10:3910:39, 8 June 2012 diff hist +29 N File:III-18a.dot Irina Idelson moved page File:III-18a.dot to File:III-14.dot current
- 10:3910:39, 8 June 2012 diff hist 0 m File:III-14.dot Irina Idelson moved page File:III-18a.dot to File:III-14.dot
- 10:3110:31, 8 June 2012 diff hist −54 Phase III - Final Design →Task No. 22 - Confirm Construction Engineering Responsibility
- 10:3010:30, 8 June 2012 diff hist +187 Phase III - Final Design →Task No. 22 - Confirm Construction Engineering Responsibility
- 10:2910:29, 8 June 2012 diff hist +53 Phase III - Final Design →Task No. 22 - Confirm Construction Engineering Responsibility
- 10:2810:28, 8 June 2012 diff hist 0 File:08.0 CE Consultant Selection and Agreement.pdf Irina Idelson uploaded a new version of "File:08.0 CE Consultant Selection and Agreement.pdf"
- 10:0610:06, 8 June 2012 diff hist −2 Phase III - Final Design →Task No. 22 - Confirm Construction Engineering Responsibility
- 10:0610:06, 8 June 2012 diff hist +21 Phase III - Final Design →Task No. 22 - Confirm Construction Engineering Responsibility
- 10:0310:03, 8 June 2012 diff hist −2 Phase III - Final Design →Task No. 22 - Confirm Construction Engineering Responsibility
- 10:0210:02, 8 June 2012 diff hist −2 Phase III - Final Design →Task No. 22 - Confirm Construction Engineering Responsibility
- 10:0010:00, 8 June 2012 diff hist 0 Phase III - Final Design →Task No. 22 - Confirm Construction Engineering Responsibility
- 09:5809:58, 8 June 2012 diff hist +30 N File:III-19f.pdf Irina Idelson moved page File:III-19f.pdf to File:III-22f.pdf current
- 09:5809:58, 8 June 2012 diff hist 0 m File:III-22f.pdf Irina Idelson moved page File:III-19f.pdf to File:III-22f.pdf
- 09:5709:57, 8 June 2012 diff hist +30 N File:III-19e.pdf Irina Idelson moved page File:III-19e.pdf to File:III-22e.pdf current
- 09:5709:57, 8 June 2012 diff hist 0 m File:III-22e.pdf Irina Idelson moved page File:III-19e.pdf to File:III-22e.pdf
- 08:3108:31, 8 June 2012 diff hist +30 N File:III-19d.pdf Irina Idelson moved page File:III-19d.pdf to File:III-22d.pdf current
- 08:3108:31, 8 June 2012 diff hist 0 m File:III-22d.pdf Irina Idelson moved page File:III-19d.pdf to File:III-22d.pdf
- 08:1908:19, 8 June 2012 diff hist +30 N File:III-19c.pdf Irina Idelson moved page File:III-19c.pdf to File:III-22c.pdf current
- 08:1908:19, 8 June 2012 diff hist 0 m File:III-22c.pdf Irina Idelson moved page File:III-19c.pdf to File:III-22c.pdf
- 08:1908:19, 8 June 2012 diff hist +30 N File:III-19b.pdf Irina Idelson moved page File:III-19b.pdf to File:III-22b.pdf current
- 08:1908:19, 8 June 2012 diff hist 0 m File:III-22b.pdf Irina Idelson moved page File:III-19b.pdf to File:III-22b.pdf
- 08:1708:17, 8 June 2012 diff hist 0 Phase III - Final Design →Task No. 22 - Confirm Construction Engineering Responsibility
- 08:1608:16, 8 June 2012 diff hist +30 N File:III-19a.dot Irina Idelson moved page File:III-19a.dot to File:III-22a.dot current
- 08:1608:16, 8 June 2012 diff hist 0 m File:III-22a.dot Irina Idelson moved page File:III-19a.dot to File:III-22a.dot current