User contributions for Mike Ross
Jump to navigation
Jump to search
- 07:15, 13 April 2010 diff hist +180 Phase III - Final Design →Task No. 8 - Submit Specifications and Special Provisions
- 07:12, 13 April 2010 diff hist +43 N File:Using MakeSpec-Instructions.doc Instructions for using the program MakeSpec
- 07:11, 13 April 2010 diff hist +123 N File:III-10c.pdf List of proprietary items for Traffic Signals and Street Lighting to be used in the preparation of plans and specifications
- 07:11, 13 April 2010 diff hist +50 N File:III-10a.pdf sample of City Specifications for a street project
- 07:09, 13 April 2010 diff hist +46 Phase III - Final Design →Task No. 7 - Submit Final Plans for Review Submittal |120px|right
- 07:07, 13 April 2010 diff hist +38 N File:ESC Plan Review Checklist.doc Erosion and Sediment Control Checklist
- 07:05, 13 April 2010 diff hist +3 Phase III - Final Design →Task No. 7 - Submit Final Plans for Review Submittal |120px|right
- 07:04, 13 April 2010 diff hist +254 Phase III - Final Design →Task No. 7 - Submit Final Plans for Review Submittal |120px|right
- 06:59, 13 April 2010 diff hist +52 N File:BLP-memo-06-06.pdf list of information is to be submitted with the PS&E
- 06:59, 13 April 2010 diff hist +44 N File:BLP-memo-06-05.pdf information pertaining to Final Check Plans.
- 06:59, 13 April 2010 diff hist +112 N File:III-7a.pdf letter from CARS accepting plans along with additional information and requirements prior to advertising project
- 06:55, 13 April 2010 diff hist +53 N File:ESC PW Process.doc Erosion and Sediment Control Process for Public Works
- 06:49, 13 April 2010 diff hist +6 Phase III - Final Design →Task No. 6 - Acquire R/W / Easement - Submit KDOT Forms 1306 and 1304
- 06:49, 13 April 2010 diff hist +31 Phase III - Final Design →Task No. 6 - Acquire R/W / Easement - Submit KDOT Forms 1306 and 1304
- 06:48, 13 April 2010 diff hist +159 Phase III - Final Design →Task No. 6 - Acquire R/W / Easement - Submit KDOT Forms 1306 and 1304
- 06:45, 13 April 2010 diff hist +57 Phase III - Final Design →Task No. 6 - Acquire R/W / Easement - Submit KDOT Forms 1306 and 1304
- 06:44, 13 April 2010 diff hist +150 N File:III-8d.dot KDOT Form 1306 - Certification By the City to the Kansas Department of Transportation of Real Property Acquisition Procedures and Utility Arrangements
- 06:44, 13 April 2010 diff hist +153 N File:III-8c.dot KDOT Form 1304 - List of Utilities & Status. (example template) Note: All utilities from Phase II task 9 should be considered when completing form 1304.
- 06:44, 13 April 2010 diff hist +92 N File:III-8b.pdf KDOT Memo B.R.U.D. 84-10 regarding Status of Utility and Railroad Agreements and Adjustments
- 06:44, 13 April 2010 diff hist +116 N File:III-8a.pdf memo from the U.S. Department of Transportation regarding Status of Utility and Railroad Agreements and Adjustments.
- 06:41, 13 April 2010 diff hist +28 Phase III - Final Design →Task No. 4 - Begin Condemnation Process
- 06:40, 13 April 2010 diff hist +47 N File:III-4a.dot Example transmittal memo condemnation documents
- 06:40, 13 April 2010 diff hist +29 N File:III-8.dot Steps in condemnation process
- 06:38, 13 April 2010 diff hist +33 Phase III - Final Design →Task No. 3 - Begin R/W / Easement Negotiations
- 06:37, 13 April 2010 diff hist +133 Phase III - Final Design →Task No. 3 - Begin R/W / Easement Negotiations
- 06:33, 13 April 2010 diff hist +27 N File:III-5b.dot Sample Log of owner contact
- 06:33, 13 April 2010 diff hist +35 N File:III-5a.dot Real Property Acquisition Checklist
- 06:28, 13 April 2010 diff hist −2 Phase III - Final Design →Task No. 3 - Begin R/W / Easement Negotiations
- 06:28, 13 April 2010 diff hist −68 Phase III - Final Design →Task No. 3 - Begin R/W / Easement Negotiations
- 06:26, 13 April 2010 diff hist −13 Phase III - Final Design →Notes
- 06:25, 13 April 2010 diff hist +15 Phase III - Final Design →Notes
- 06:25, 13 April 2010 diff hist +1 Phase III - Final Design →Notes
- 06:25, 13 April 2010 diff hist −16 Phase III - Final Design →Notes
- 06:21, 13 April 2010 diff hist 0 Phase III - Final Design →Notes
- 06:21, 13 April 2010 diff hist +12 Phase III - Final Design →Notes
- 06:20, 13 April 2010 diff hist +1 Phase III - Final Design →Notes
- 06:19, 13 April 2010 diff hist +102 Phase III - Final Design →Task No. 3 - Begin R/W / Easement Negotiations
- 06:09, 13 April 2010 diff hist +54 Phase III - Final Design →Task No. 3 - Begin R/W / Easement Negotiations
- 06:08, 13 April 2010 diff hist −32 Phase III - Final Design →References
- 06:06, 13 April 2010 diff hist +71 Phase III - Final Design →Task No. 3 - Begin R/W / Easement Negotiations
- 16:15, 12 April 2010 diff hist −1 Phase III - Final Design →Task No. 3 - Begin R/W / Easement Negotiations
- 16:13, 12 April 2010 diff hist +61 Phase III - Final Design →Task No. 3 - Begin R/W / Easement Negotiations
- 16:10, 12 April 2010 diff hist +32 Phase III - Final Design
- 16:10, 12 April 2010 diff hist −14 Phase III - Final Design →Task No. 3 - Begin R/W / Easement Negotiations
- 15:58, 12 April 2010 diff hist +79 Phase III - Final Design →Task No. 3 - Begin R/W / Easement Negotiations
- 14:37, 12 April 2010 diff hist +43 Phase III - Final Design →Task No. 3 - Begin R/W / Easement Negotiations
- 14:35, 12 April 2010 diff hist +1 Phase III - Final Design →Task No. 3 - Begin R/W / Easement Negotiations
- 14:35, 12 April 2010 diff hist 0 Phase III - Final Design →Task No. 3 - Begin R/W / Easement Negotiations
- 14:34, 12 April 2010 diff hist +166 Phase III - Final Design →Task No. 3 - Begin R/W / Easement Negotiations
- 14:33, 12 April 2010 diff hist 0 N File:BLP-memo-06-01.pdf