Task No. 28 - Approve Contractor Final Pay and Surety Release

The Consultant/Project Manager in conjunction with the Contract Specialist will prepare the Contractor’s final pay and the final change order.

The following will accompany this final pay document to the Finance Department:

Consent of Surety to Final Payment,

Contractor Project Completion Certification (see Phase V, Task No. 21), and

Certificate of Engineer as to Completion (see Phase V, Task No. 22).

Exhibit No. V-28 is a sample transmittal letter with final Change Order/Explanation, Final Contractor Pay Estimate, Certificate of Engineer as to Completion and Surety Release.