Phase IV - Pre-Construction
Home | I-Vision | II-Preliminary Design | III-Final Design | IV-Pre-Construction | V-Construction | VI-Retrospect |
Task No. 1 - Complete Plans, Specifications and Estimate
The Consultant/Project Manager shall make all final plan revisions, complete the specifications and prepare the final Engineer’s construction cost estimate. The City project team and consultant will determine what submittals the contractor will be required to submit during the construction phase and who will be responsible for reviewing and approving the submittals.
A Stormwater Pollution and Prevention Plan (SWPPP) must be prepared by the project team. See SWPPP Template for assembling the SWPPP notebook.
Project Manager will coordinate with Stormwater Section for LDP application process. See Land Disturbace Permit Application. See sample of a City's Land Disturbance Permit.
See BLP Memo 03-12 Engineer's Professional Seal and Signature on Plans.
Exhibit No. IV-1a is a contractor submittals checklist.
Exhibit No. IV-1b is an approved products listing for signals, street lighting, fiber optics, ITS, traffic control, pavement marking and signing.