Difference between revisions of "Phase IV - Pre-Construction"

From PPM Wiki - City of Overland Park Projects and Procedures Manual Pages
Jump to navigation Jump to search
Line 15: Line 15:


== Task No. 2 - Distribute Material Testing Proposals ==
== Task No. 2 - Distribute Material Testing Proposals ==
{{Top}}
The Project Manager shall prepare and distribute RFPs to at least three qualified private material testing companies.
The Project Manager shall prepare and distribute RFPs to at least three qualified private material testing companies.
Exhibit No. IV-2a is a list of materials testing / geotechnical service companies.
Exhibit No. IV-2a is a list of materials testing / geotechnical service companies.
Line 33: Line 35:


Exhibit No. IV-2h is the Supplemental Agreement for Construction Material Testing Services
Exhibit No. IV-2h is the Supplemental Agreement for Construction Material Testing Services
== Task No. 3 - Set Bid Opening Date - Schedule Room ==
{{Top}}
The Project Manager in conjunction with the Contract Specialist will determine the bid opening date. Consideration of publishing the legal advertisement(s) (see Task No. IV-4) will be taken into consideration. The Contract Specialist will schedule a room for receiving bids. The room location will be included in the legal publication.
The Project Manager shall determine if a pre-bid conference is required prior to preparing the notice to bidders. If one is required, it shall be scheduled approximately one week prior to the bid opening. The Notice to Bidders shall give this date as information to potential bidders and will serve as the invitation to this meeting. It shall be determined by the Project Manager whether attendance will be a requirement for submitting a bid.
Also See: Guidance for Planning Bid and Contract Award Schedules
== Task No. 4 - Publish Legal Advertisement ==
{{Top}}
Generally, the project shall be advertised approximately 3 weeks prior to the scheduled bid opening for construction projects and 12 days for equipment and material bids. The Project Manager is to provide the Contract Specialist  the notice to bidders electronically by 3:00 pm Friday so they can arrange for publication in the Wednesday edition of the Overland Park Sun newspaper.  The Contract Specialist shall check the newspaper on the day of scheduled publication to make sure the notice was published.
Exhibit No. IV-4a is a sample transmittal memorandum to the City Clerk's office.
Exhibit No. IV-4b is a sample Notice to Bidders.
Exhibit No. IV-4c is a sample legal publication affidavit for the Johnson County Sun and Kansas Register.
For KDOT projects, advertisement shall also be in the Kansas Register, 30 days prior to the scheduled bid opening.  Kansas Register publications are released on Thursdays.  The notice to bidders shall be received by the Kansas Register one week prior to scheduled advertisement.
The Notice shall be e-mailed to: [email protected]
Office of the Secretary of State
Attn: Nancy Reddy
Memorial Hall, 1st Floor
120 SW 10th Avenue
Topeka, KS 66612-1594
785-296-3489
785-291-3051 (fax)
Exhibit No. IV-4d is a sample e-mail cover sheet to the Office of the Secretary of State. (Kansas Register)

Revision as of 05:52, 7 April 2010

Home I-Vision II-Preliminary Design III-Final Design IV-Pre-Construction V-Construction VI-Retrospect

Task No. 1 - Complete Plans, Specifications and Estimate

The Consultant/Project Manager shall make all final plan revisions, complete the specifications and prepare the final Engineer’s construction cost estimate. The City project team and consultant will determine what submittals the contractor will be required to submit during the construction phase and who will be responsible for reviewing and approving the submittals.

A Stormwater Pollution and Prevention Plan (SWPPP) must be prepared by the project team. See SWPPP Template for assembling the SWPPP notebook.

Project Manager will coordinate with Stormwater Section for LDP application process. See Land Disturbace Permit Application. See sample of a City's Land Disturbance Permit.

See BLP Memo 03-12 Engineer's Professional Seal and Signature on Plans.

Exhibit No. IV-1a is a contractor submittals checklist.

Exhibit No. IV-1b is an approved products listing for signals, street lighting, fiber optics, ITS, traffic control, pavement marking and signing.


Task No. 2 - Distribute Material Testing Proposals

Top

The Project Manager shall prepare and distribute RFPs to at least three qualified private material testing companies. Exhibit No. IV-2a is a list of materials testing / geotechnical service companies.

Exhibit No. IV-2b is a sample RFP transmittal letter to material testing companies.

Exhibit No. IV-2c is the material testing proposal instructions (Exhibit A).

Exhibit No. IV-2d is the material testing proposal (Exhibit B). (word version)

Exhibit No. IV-2d is the material testing proposal (Exhibit B). (excel version)

Exhibit No. IV-2e is the material and testing specifications (Exhibit C).

Exhibit No. IV-2f is the Material Sampling and Testing Frequency Chart (Exhibit D).

Exhibit No. IV-2g is the Agreement for Construction Material Testing Services.

Exhibit No. IV-2h is the Supplemental Agreement for Construction Material Testing Services


Task No. 3 - Set Bid Opening Date - Schedule Room

Top

The Project Manager in conjunction with the Contract Specialist will determine the bid opening date. Consideration of publishing the legal advertisement(s) (see Task No. IV-4) will be taken into consideration. The Contract Specialist will schedule a room for receiving bids. The room location will be included in the legal publication.

The Project Manager shall determine if a pre-bid conference is required prior to preparing the notice to bidders. If one is required, it shall be scheduled approximately one week prior to the bid opening. The Notice to Bidders shall give this date as information to potential bidders and will serve as the invitation to this meeting. It shall be determined by the Project Manager whether attendance will be a requirement for submitting a bid.

Also See: Guidance for Planning Bid and Contract Award Schedules


Task No. 4 - Publish Legal Advertisement

Top

Generally, the project shall be advertised approximately 3 weeks prior to the scheduled bid opening for construction projects and 12 days for equipment and material bids. The Project Manager is to provide the Contract Specialist the notice to bidders electronically by 3:00 pm Friday so they can arrange for publication in the Wednesday edition of the Overland Park Sun newspaper. The Contract Specialist shall check the newspaper on the day of scheduled publication to make sure the notice was published.

Exhibit No. IV-4a is a sample transmittal memorandum to the City Clerk's office.

Exhibit No. IV-4b is a sample Notice to Bidders.

Exhibit No. IV-4c is a sample legal publication affidavit for the Johnson County Sun and Kansas Register.


For KDOT projects, advertisement shall also be in the Kansas Register, 30 days prior to the scheduled bid opening. Kansas Register publications are released on Thursdays. The notice to bidders shall be received by the Kansas Register one week prior to scheduled advertisement.

The Notice shall be e-mailed to: [email protected]

Office of the Secretary of State

Attn: Nancy Reddy Memorial Hall, 1st Floor 120 SW 10th Avenue Topeka, KS 66612-1594

785-296-3489

785-291-3051 (fax)

Exhibit No. IV-4d is a sample e-mail cover sheet to the Office of the Secretary of State. (Kansas Register)