18 June 2024
|
13:26 | Phase III - Final Design 2 changes history +25 [Alisha Holcomb (2×)] | |||
|
13:26 (cur | prev) +16 Alisha Holcomb talk contribs →City's Standard Contract Documents: | ||||
|
13:23 (cur | prev) +9 Alisha Holcomb talk contribs →City's Standard Contract Documents: |
|
13:25 | (Upload log) [Alisha Holcomb (3×)] | |||
|
13:25 Alisha Holcomb talk contribs uploaded File:07 III-11a-1 Agreement-KDOT Fed funds clean 1-5-22.docx | ||||
|
13:23 Alisha Holcomb talk contribs uploaded File:05 III-11a-1 Agreement clean.docx | ||||
|
08:45 Alisha Holcomb talk contribs uploaded File:II-3a Engineering Architectural Services Agreement rev 5-29-24.docx |
08:46 | Phase II - Preliminary Design diffhist 0 Alisha Holcomb talk contribs →Task No. 3 - Consultant Selection/Certification |
7 June 2024
11:35 | Approved Materials - Traffic Signals diffhist −94 Brian Geiger talk contribs →Power Transfer Switches: Updated from SPH-302 to SPH-303 bypass switch. |
|
11:34 | (Upload log) [Brian Geiger (2×)] | |||
|
11:34 Brian Geiger talk contribs uploaded a new version of File:TRF PQL TS MEM Clary PowerTransferSwitch.pdf (File uploaded with MsUpload) | ||||
|
11:34 Brian Geiger talk contribs uploaded a new version of File:TRF PQL TS CAT Clary PowerTransferSwitch.pdf (File uploaded with MsUpload) |
6 June 2024
15:29 | User rights log Dan Hurley talk contribs changed group membership for Tiesha Morgan from (none) to administrator and bureaucrat |
15:14 | User creation log User account Tiesha Morgan talk contribs was created by Dan Hurley talk contribs |
m 09:48 | Approved Materials - Traffic Signals diffhist +85 Brian Geiger talk contribs →Power Transfer Switches: Notes about discontinuation of SPH-302 with Jim Cole on a phone call with Hightower. |
31 May 2024
14:59 | Phase V - Construction diffhist +12 Alisha Holcomb talk contribs →Task No. 14 - On-Going Contractor Payments |
10:17 | Phase IV - Pre-Construction diffhist +1 Alisha Holcomb talk contribs →Task No. 2 - Selection of Material Testing Firm |
10:17 | Upload log Alisha Holcomb talk contribs uploaded File:IV-2g Testing Services Agreement - rev 5-31-24.docx |