- 11:05, 1 June 2012 diff hist +9 Phase II - Preliminary Design →Task No. 23 - Distribute Plans for Field Check
- 11:04, 1 June 2012 diff hist +9 Phase II - Preliminary Design →Task No. 22 - Prepare Preliminary Cash Flow Projection (update)
- 11:04, 1 June 2012 diff hist +9 Phase II - Preliminary Design →Task No. 21 - Prepare Preliminary Cost Estimate (update)
- 11:04, 1 June 2012 diff hist +9 Phase II - Preliminary Design →Task No. 20 - Distribute Plans to Utility Companies. Schedule Second Utility Meeting.
- 11:04, 1 June 2012 diff hist +9 Phase II - Preliminary Design →Task No. 19 - Prepare Field Check Plans
- 11:04, 1 June 2012 diff hist +9 Phase II - Preliminary Design →Task No. 18 - Submit Request for Design Exception to KDOT
- 11:03, 1 June 2012 diff hist +9 Phase II - Preliminary Design →Task No. 17 - Begin Geotechnical Report Process
- 11:03, 1 June 2012 diff hist +9 Phase II - Preliminary Design →Task No. 16 - Begin Title Report Process
- 11:02, 1 June 2012 diff hist +1 Phase II - Preliminary Design →Task No. 15 - Schedule First Public Information Meeting
- 11:02, 1 June 2012 diff hist −1 Phase II - Preliminary Design →Task No. 15 - Schedule First Public Information Meeting
- 11:02, 1 June 2012 diff hist +1 Phase II - Preliminary Design →Task No. 15 - Schedule First Public Information Meeting
- 11:01, 1 June 2012 diff hist −2 Phase II - Preliminary Design →Task No. 15 - Schedule First Public Information Meeting
- 11:01, 1 June 2012 diff hist +2 Phase II - Preliminary Design →Task No. 15 - Schedule First Public Information Meeting
- 11:01, 1 June 2012 diff hist +8 Phase II - Preliminary Design →Task No. 15 - Schedule First Public Information Meeting
- 11:00, 1 June 2012 diff hist +9 Phase II - Preliminary Design →Task No. 14 - Continue Environmental Process
- 10:59, 1 June 2012 diff hist +9 Phase II - Preliminary Design →Task No. 13 - Conduct Field Surveys
- 10:59, 1 June 2012 diff hist −1 Phase II - Preliminary Design →Task No. 12 - Agency Agreement (if Applicable)
- 10:58, 1 June 2012 diff hist +10 Phase II - Preliminary Design →Task No. 12 - Agency Agreement (if Applicable)
- 10:58, 1 June 2012 diff hist +9 Phase II - Preliminary Design →Task No. 11 - SMAC Preliminary Study
- 10:58, 1 June 2012 diff hist +9 Phase II - Preliminary Design →Task No. 10 - Standard Details