Difference between revisions of "Project Development Procedures for Non-NHS Projects - Checklist"

From PPM Wiki - City of Overland Park Projects and Procedures Manual Pages
Jump to navigation Jump to search
Line 12: Line 12:
|width="100"|  
|width="100"|  
|-
|-
||Project Request(A1)||________||__________
||Project Request(A1)||________||__________||   || 
|-
|-
||Project Authorization (A2)|| || ||________||________
||Project Authorization (A2)|| || ||________||________

Revision as of 10:02, 5 April 2010

Activity LPA
Target Date
LPA
Action
BLP
Target Date
BLP
Action
INITIATION, SCOPING AND SCHEDULING PHASE
Project Request(A1) ________ __________    
Project Authorization (A2) ________ ________
Consultant Selection (A3) ________ ________
Consultant Selection Certificate (A4) Not applicable unless federal funds are requested for design services
PRELIMINARY DESIGN PHASE