Phase IV - Pre-Construction

From PPM Wiki - City of Overland Park Projects and Procedures Manual Pages
Revision as of 06:49, 7 April 2010 by Mike Ross (talk | contribs) (Created page with '{{Navbar}} == Task No. 1 - Complete Plans, Specifications and Estimate == The Consultant/Project Manager shall make all final plan revisions, complete the specifications and prep…')
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.
Home I-Vision II-Preliminary Design III-Final Design IV-Pre-Construction V-Construction VI-Retrospect

Task No. 1 - Complete Plans, Specifications and Estimate

The Consultant/Project Manager shall make all final plan revisions, complete the specifications and prepare the final Engineer’s construction cost estimate. The City project team and consultant will determine what submittals the contractor will be required to submit during the construction phase and who will be responsible for reviewing and approving the submittals.

A Stormwater Pollution and Prevention Plan (SWPPP) must be prepared by the project team. See SWPPP Template for assembling the SWPPP notebook.

Project Manager will coordinate with Stormwater Section for LDP application process. See Land Disturbace Permit Application. See sample of a City's Land Disturbance Permit.

See BLP Memo 03-12 Engineer's Professional Seal and Signature on Plans.

Exhibit No. IV-1a is a contractor submittals checklist.

Exhibit No. IV-1b is an approved products listing for signals, street lighting, fiber optics, ITS, traffic control, pavement marking and signing.