== Task No. 1 - Identify Project Team ==
{{Top}}


== Task No. 1 - Identify Project Team ==
When a project is scheduled to begin the design phase, the Project Team is to be identified by the City Engineer and/or the City Traffic Engineer, depending on the scope of the project. The purpose of this team is to provide input, information, support, and execution throughout the project planning, design, and construction. The Project Team will generally include the following members: Project Manager, Traffic Engineer, Construction Inspector, Traffic Maintenance Technician, Maintenance Representative, Engineering Technician, Contract Specialist, Law Department Representative, and Finance Representative.
When a project is scheduled to begin the design phase, the Project Team is to be identified by the City Engineer and/or the City Traffic Engineer, depending on the scope of the project. The purpose of this team is to provide input, information, support, and execution throughout the project planning, design, and construction. The Project Team will generally include the following members: Project Manager, Traffic Engineer, Construction Inspector, Traffic Maintenance Technician, Maintenance Representative, Engineering Technician, Contract Specialist, Law Department Representative, and Finance Representative.


== Task No. 2 - Decide if City Staff to Design ==
== Task No. 2 - Decide if City Staff to Design ==
{{Top}}
The City Engineer and/or the City Traffic Engineer in consultation with the Project Team will decide whether the project will be designed by the City Staff or by a Consulting Engineer.
The City Engineer and/or the City Traffic Engineer in consultation with the Project Team will decide whether the project will be designed by the City Staff or by a Consulting Engineer.


== Task No. 3-4 - Hire Consultant ==
== Task No. 3 - Consultant Selection/Certification ==
{{top}}
{{top}}


MARC's rules and regulations do not permit federal dollars to be used for project design services. Therefore, Consultant selection certification, to KDOT, is not applicable as long as this MARC rule is in effect.
The City shall select and negotiate with a consultant for project design in accordance with the [http://online.encodeplus.com/regs/overlandpark-ks-gbp/doc-viewer.aspx#secid-103 '''City Resolution No. 4550'''] if the design is funded solely with local funds. If federal or state funds are used for the design, the City will use an approved list of consultants furnished by the BLP and will follow the current BLP Consultant Selection Procedures. If the City intends to use federal funds in the construction engineering, and use the same consultant for both preliminary engineering (PE) and construction engineering (CE), following the current BLP Consultant Selection Procedure for the PE will satisfy the requirements for the CE selection.
 
Prior to the beginning of the selection process, Project Manager shall notify via email DPW and CE of upcoming RFQ for consulting services. The project name, list of firms to receive the RFQ and any other pertinent information will be provided.
 
For more information see Chapter [[Media:3.0 PE Consultant Selection and Agreement 2020.pdf|'''3.0 Preliminary Engineering (PE) Consultant Selection and Agreement''']] and Chapter [[Media:11.0 CE Consultant Selection and Agreement 2020.pdf|'''11.0 Construction Engineering (CE) Consultant Selection and Agreement''']] of KDOT's LPA Project Development Manual.
 
When federal funds are used in the preliminary engineering, the City will provide KDOT a certification that appropriate steps have been completed and the process complied with all applicable regulations. Any work done prior to obligation of federal funds will be non-participating.
   
   
{{Note|The flow diagrams included in this Manual will be provided to the Consultant during the negotiating process. When negotiating an agreement with a consulting firm a narrative of services and a fee schedule is required (examples below).}}
{{Note|''This Manual will be provided to the Consultant during the negotiating process. When negotiating an agreement with a consulting firm a narrative of services and a fee schedule is required (examples below'').}}
 
{{Exhibit|II-3-4a.pdf|No. II-3-4a|is City Resolution No. 3506 sets forth the policies and procedures for the selection of Professional Consulting Services.}}


{{Exhibit|II-3-4b.dot|No. II-3-4b|City’s standard Engineering / Architectural services agreement for design projects.}}
{{Exhibit|II-3a Engineering Architectural Services Agreement rev 9-18-23.docx|No. II-3a|City’s standard Engineering / Architectural services agreement for design projects.}}


{{Exhibit|II-3-4b(1).dot|No. II-3-4b(1)|City’s standard Supplemental Agreement for Professional Engineering Services.}}
{{Exhibit|II-3b(1) Supplemental to Engineering Architectural Services - 1-14-20.docx|No. II-3b(1)|City’s standard Supplemental Agreement for Professional Engineering Services. (First)}}


{{Exhibit|II-3-4c.dot|No. II-3-4c|City’s standard Consultant Agreement for non-design projects.}}
{{Exhibit|II-3b(2) Supplemental to Eng Arch Services-second and beyond 1-14-20.docx|No. II-3b(2)|City’s standard Supplemental Agreement for Professional Engineering Services. (Second and beyond)}}


{{Exhibit|II-3-4c(1).dot|No. II-3-4c(1)|City’s standard Supplemental Agreement to the Consultant Agreement for non-design projects.}}
{{Exhibit|II-3c Consultant Agreement-non design rev 7-5-22.docx|No. II-3c|City’s standard Consultant Agreement for non-design projects.}}


{{Exhibit|II-3-4e.dot|No. II-3-4e|City’s standard Scope of Services.}}
{{Exhibit|II-3d Supplemental to Consulting Services 1-14-20.docx|No. II-3d|City’s standard Supplemental Agreement to the Consultant Agreement for non-design projects.}}


:[[media:BLP-Memo-05-15.pdf|'''BLP Memo 05-15 Geotechnical Bridge Foundation Investigation Practice''']] ''is to be used when writing contracts for projects involving bridge construction.''
{{Exhibit|II-3e.dot|No. II-3e| is a sample of City’s standard Scope of Services.}}
:(When writing contracts for projects involving bridge construction, refer to Chapter [[media:6.0 Bridge Design 2020.pdf|'''6.0 Bridge Design''']] of KDOT's LPA Project Development Manual).


{{Exhibit|II-3-4e(1).dot|No. II-3-4e(1)|City’s standard Scope of Services for a Street Lighting project.}}
{{Exhibit|II-3e(1).dot|No. II-3e(1)|City’s standard Scope of Services for a Street Lighting project.}}


{{Exhibit|II-3-4e(2).dot|No. II-3-4e(2)|City’s standard Scope of Services for a Traffic Signal project.}}
{{Exhibit|II-3e(2).dot|No. II-3e(2)|City’s standard Scope of Services for a Traffic Signal project.}}


{{Exhibit|II-3-4f.xlt|No. II-3-4f|City’s standard fee schedule for engineering services agreement.}}
{{Exhibit|II-3f.xlt|No. II-3f|City’s standard fee schedule for engineering services agreement.}}


{{Exhibit|II-3-4g.dot|No. II-3-4g|is a sample RFP letter to Consulting Firms.}}
{{Exhibit|II-3g RFQ packet for consulting services.pdf|No. II-3g|is a sample RFQ packet for consulting services.}}


{{Exhibit|II-3-4h.dot|No. II-3-4h|is a sample Ranking Memo to Consultant Selection Committee.}}
{{Exhibit|II-3h Memo to Selection Committee.pdf|No. II-3h|is a sample Ranking Memo to Consultant Selection Committee.}}


{{Exhibit|II-3-4i.xlt|No. II-3-4i|is a sample Ranking Sheet to be completed by the Consultant Selection Committee.}}
{{Exhibit|II-3i.xlt|No. II-3i|is a sample Ranking Sheet to be completed by the Consultant Selection Committee.}}


{{Exhibit|II-3-4j.dot|No. II-3-4j|is a sample Interview Memo to Consultant Selection Committee.}}
{{Exhibit|II-3j.dot|No. II-3j|is a sample Interview Memo to Consultant Selection Committee.}}


{{Exhibit|II-3-4k.xlt|No. II-3-4k|is a sample of a compiled Ranking Sheet.}}
{{Exhibit|II-3k.xlt|No. II-3k|is a sample of a compiled Ranking Sheet.}}


{{Exhibit|II-3-4l.dot|No. II-3-4l|is a sample letter requesting interview of short list Consulting Firms.}}
{{Exhibit|II-3l.dot|No. II-3l|is a sample letter requesting interview of short list Consulting Firms.}}
   
   
The selection committee shall meet after ranking sheets are completed and any interviews have been held.  This meeting is to ensure consensus of the selection committee prior to letters being sent to consultants.
The selection committee shall meet after ranking sheets are completed and any interviews have been held.  This meeting is to ensure consensus of the selection committee prior to letters being sent to consultants.


{{Exhibit|II-3-4m.dot|No. II-3-4m|is a sample letter to selected Consulting Firm.}}
{{Exhibit|II-3m.dot|No. II-3m|is a sample letter to selected Consulting Firm.}}


{{Exhibit|II-3-4n.dot|No. II-3-4n|is a sample letter to Consulting Firms not selected.}}
{{Exhibit|II-3n.dot|No. II-3n|is a sample letter to Consulting Firms not selected.}}


{{Exhibit|II-3-4o.xlt|No. II-3-4o|is a list of Consulting Firms.}}
{{Exhibit|II-3o CONSULTING FIRMS 6-9-23.xlsx|No. II-3o|is a list of Consulting Firms.}}
 
== Task No. 4 - Submit Project Description to Law Department. Execute Ordinances-Resolution. ==
{{Top}}


== Task No. 5 - Submit Project Description to Law Department ==
The physical location of the project and a description of what is to be constructed is to be submitted to the Law Department. A feasibility report shall include the physical location of the project, a description of what is to be constructed, a cost estimate, and other necessary information required by the Law Department. The description project centerline shall include the permanent improvements (not tapers for street projects).
The physical location of the project and a description of what is to be constructed is to be submitted to the Law Department. A feasibility report shall include the physical location of the project, a description of what is to be constructed, a cost estimate, and other necessary information required by the Law Department. The description project centerline shall include the permanent improvements (not tapers for street projects).


An example of a project description is as follows:
An example of a project description is as follows:


:<font color="green">''The reconstruction and widening of certain portions of Nall Avenue from 369 feet south of 119th Street to 135th Street, and the reconstruction and widening of certain portions of 127th Street from Nall Avenue to 500 feet west of Nall Avenue. Construction will include a dual 28 foot roadway with a 24 foot median located in 120 feet of right-of-way, including left turn lanes at required locations, construction of a new bridge on Nall Avenue over Tomahawk Creek, street lighting, storm sewers, a 4 foot concrete sidewalk on one side of the roadway and an 8 foot asphalt sidewalk on the other side of the roadway.</font>
:<font color="green">'''''The construction of Switzer Road from  north of the centerline of 159th Street to south of the centerline of 151st Street. Construction will include a dual roadway with a median.  Left turn lanes will be located at side streets as required.  Concrete sidewalks will be located on the west side of Switzer Road.  An asphalt bike and pedestrian trail will be located on the east side of Switzer Road.  The project also includes construction of storm sewers, street lights, restoration, and other items incidental to the street construction.'''''</font>
''
''
The Project Manager, in conjunction with the Law Department, will determine if all necessary City ordinances or resolutions have been executed in order to authorize the project. Examples of possible documents are:
{{Exhibit|II-4a.dot|No. II-4a| Resolution on advisability of the creation of an Improvement District,}}
{{Exhibit|II-4b.dot|No. II-4b| Resolution authorizing and providing for the creation of an Improvement District,}}
:[[Media:CO 2-20-2017 Ordinance MTI-3159 (TH-1665) Publication.pdf|'''Exhibit No. II-4c''']] ''Ordinance providing for the public improvement of a Main Trafficway''.
== Task No. 5 - Prepare Project Schedule ==
{{Top}}


== Task No. 6 - Prepare Project Schedule ==
If a Consultant is to be hired, the anticipated construction time period shall be provided. The Consultant shall submit a schedule, indicating the design phases, R/W / easement submittal, meetings, bid opening date and construction time period. If the City Staff is designing the project, a similar schedule shall be prepared by the City Project Manager.
If a Consultant is to be hired, the anticipated construction time period shall be provided. The Consultant shall submit a schedule, using Microsoft Project, indicating the design phases, R/W / easement submittal, meetings, bid opening date and construction time period. If the City Staff is designing the project, a similar schedule shall be prepared by the City Project Manager.


== Task No. 7 - Submit Cash Flow Projections (Engineering Cost) ==
== Task No. 6 - Submit Cash Flow Projections (Engineering Cost) ==
Subsequent to executing a contract with a Consultant or when the City Staff is selected to provide engineering services, a cash flow projection for engineering services shall be submitted to the City Finance Department.
{{Top}}
 
When requested, a cash flow projection for engineering services shall be submitted to the City Finance Department.
   
   
{{Exhibit|II-7.xlt|No. II-7|is the standard cash flow form.}}
:[[Media:Cash Flow TH-1027 6-2019 Rome.xlsx|'''Exhibit II-6''']] ''is the standard cash flow form.''
 
== Task No. 7 - Initiate Utility Coordination. Schedule Utility Meeting (optional) ==
{{Top}}
 
Early in the preliminary design phase, the Project Manager will contact all public and private utility officials, informing them of the upcoming project (project limits and schedule) and requesting the information on their facilities (location maps, existing utility easements and any other pertinent information) in the vicinity.
 
{{Exhibit|II-7 email to utility companies links.docx|No. II-7|is a sample email (initial contact) to the utilities.}}
:([[media:Project location map for utilities.pdf|'''Project Location Map''']] and [[media:Utility Response Form.pdf|'''Utility Response Forms''']] should be attached to the email).


== Task No. 8 - Execute Ordinances-Resolution ==
If the Project Manager chooses to hold a meeting, an agenda should be prepared and distributed in advance of the meeting to all scheduled attendees.
The Project Manager, in conjunction with the Law Department, will determine if all necessary City ordinances or resolutions have been executed in order to authorize the project. Examples of possible documents are:
*creating an improvement district,
*financing with the thoroughfare statute, and
*temporary bond financing.


== Task No. 9 - Schedule First Utility Meeting ==
The typical agenda items are as follows:
Early in the preliminary design phase, the Consultant or Project Manager shall schedule a meeting with all public and private utility officials. A meeting agenda shall be prepared and distributed in advance of the meeting to all scheduled attendees. Meeting minutes shall also be prepared following the meeting and distributed to all scheduled attendees, including those who were invited but did not attend.
{{Note|In an effort to avoid scheduling conflicts with other called utility meetings an Outlook calendar has been created called PW Utilities. PW Utilities shall be invited as an attendee to all utility meetings, pre-bid conferences and pre-construction conferences or any meeting requesting utility company attendance.}}


The purpose of the first utility meeting is as follows:
*utility location maps/information;
*existing utility easements;
*project schedule;
*possible critical out-of-service time periods;
*utility representatives contact information.


*obtain utility location maps/information,
Meeting minutes shall also be prepared following the meeting and distributed to all scheduled attendees, including those who were invited but did not attend.
*obtain copies of existing utility easements,
{{Note|''When scheduling utility meeting in Google calendar, in order to avoid conflicts with other utility meetings, CH-PW Utilities (found under Rooms tab) shall be "invited" as an attendee to all meetings, pre-bid conferences and pre-construction conferences or any meetings that require utility company attendance''.}}
*present the project schedule,
*determine if there are critical out-of-service time periods, and
*confirm utility representative contacts and phone numbers.


{{Exhibit|II-9.dot|No. II-9|is a list of Johnson County utility and pipeline companies, possible contacts, address and phone numbers.}}
{{Exhibit|II-7.docx|No. II-7a|is a list of utility companies.}}


{{Exhibit|II-9a.dot|No. II-9a|is a copy of the City's Utility Relocation Guidelines.}}
{{Exhibit|II-7b utility info request.pdf|No. II-7b|is a sample request for utility plans and easement documents.}}


{{Exhibit|II-9b.dot|No. II-9b|is a sample invitation letter for Utility Coordination Meeting.}}
{{Exhibit|II-7c Utility Meeting Request.pdf|No. II-7c|is a sample invitation letter for Utility Coordination Meeting.}}


{{Exhibit|II-9c.dot|No. II-9c|sample agenda for Utility Coordination Meeting.}}
{{Exhibit|II-7d utility meeting agenda.pdf|No. II-7d|sample agenda for Utility Coordination Meeting.}}


{{Exhibit|II-9d.dot|No. II-9d|meeting sign in sheet.}}
{{Exhibit|II-7e Sign in sheet.docx|No. II-7e|meeting sign in sheet.}}


{{Exhibit|II-9e.dot|No. II-9e|sample of utility coordination meeting minutes.}}
{{Exhibit|II-7f Utility Meeting Minutes.pdf|No. II-7f|sample of utility coordination meeting minutes.}}
   
   
'''Johnson County Wastewater'''
'''Johnson County Wastewater'''


{{Exhibit|II-9f.pdf|No. II-9f|Right-Of-Way Agreement}}
{{Exhibit|II-7g.pdf|No. II-7g|Right-Of-Way Agreement}}


{{Exhibit|II-9g.pdf|No. II-9g|Right-Of-Way Agreement, Reference Sheet}}
{{Exhibit|II-7h.pdf|No. II-7h|Right-Of-Way Agreement, Reference Sheet}}


{{Exhibit|II-9h.pdf|No. II-9h|Right-Of-Way Agreement, Project Checklist}}
{{Exhibit|II-7i.pdf|No. II-7i|Right-Of-Way Agreement, Project Checklist}}


{{Exhibit|II-9i.xlt|No. II-9i|Payment invoice to JCW for reimbursement of relocation costs.}}
:[[Media:MS1273 Invoice Packet.pdf|'''Exhibit No. II-7j''']] ''Payment invoice to JCW for reimbursement of relocation costs.''


'''Water District No.1 of Johnson County'''
'''Water District No.1 of Johnson County'''


{{Exhibit|II-9j.pdf|No. II-9j|Right-Of -Way Agreement}}
{{Exhibit|II-7k.pdf|No. II-7k|Right-Of -Way Agreement}}
 
'''Transmission Pipe Line'''
 
{{Exhibit|II-7l.pdf|No. II-7l| is a sample of Encroachment Guidelines.}}
 
'''Evergy'''
 
{{Exhibit|II-7m KCP&L Contacts.xlsx|No. II-7m|Governmental Relocation Contact List}}
 
{{Exhibit|II-7n.pdf|No. II-7n|Service Territory Map}}
 
For Verizon inquiries see Memorandum [[Media:Verizon Inquiries.pdf|'''Request for OSP facility records''']].


'''Williams Pipe Line'''
Refer to the City's [[Utility_Relocation_Guidelines|'''Utility Relocation Guidelines''']] for all relocation planning.


{{Exhibit|II-9k.pdf|No. II-9k|Encroachment Guidelines.}}
Refer to [https://www2.opkansas.org/files/dw/api/Docs/11697 '''Manual of Infrastructure Standards'''] for excavation and safety requirements.


'''KCPL'''
For federally funded projects refer to Chapter [[Media:8.0 Status of Utilities 2020.pdf|'''8.0 Status of Utilities''']] of KDOT's '''LPA Project Development Manual''' for additional information.


{{Exhibit|II-9l.pdf|No. II-9l|Governmental Relocation Contact List}}
== Task No. 8 - Pre-Design Meeting ==
{{Top}}


{{Exhibit|II-9m.pdf|No. II-9m|Service Territory Map}}
A pre-design meeting shall be scheduled prior to commencing any significant design work. A meeting agenda shall be prepared and distributed in advance of the meeting to the scheduled attendees. Meeting minutes shall be prepared and distributed to all attendees. The purpose of this meeting is to discuss varies anticipated design issues:


== Task No. 10 - Pre-Design Meeting ==
*specific limits of improvements;
A pre-design meeting shall be scheduled prior to commencing any significant design work. A meeting agenda shall be prepared and distributed in advance of the meeting to the scheduled attendees. Meeting minutes shall be prepared and distributed to all attendees. The purpose of this meeting is to discuss and resolve as many anticipated design issues as possible as follows:
*median openings and left/right turn storage lengths;
*utility conflicts;


*specific limits of improvements,
{{Note|''All utilities within construction limits will be shown on the [https://www.ksdot.org/Assets/wwwksdotorg/bureaus/burLocalProj/Forms/1304.pdf '''1304 Form''']''.}}
*median openings and left/right turn storage lengths,
*detailed schedule;
*detailed schedule,
*design criteria as described in [[#Task No. 9 - Design Criteria| '''Phase II, Task No. 9''']];
*confirmation of appropriate design criteria as described in Task No. 11,  
*necessary permits, such as
*determine if the project will need a Land Disturbance Permit (LDP),
::[https://www.opkansas.org/city-services/permits-licenses-inspections-directory/'''Land Disturbance Permit'''];
*determine detours/street closings, and
::[http://www.kdheks.gov/water/download/tech/2017_ready_mix_permit/A6.pdf '''KDHE Stormwater NOI'''];
*project phasing/traffic control,
::[https://www.epa.gov/cwa-404/permit-program-under-cwa-section-404 Corps of Engineers '''404 Permit'''];
*identify equipment or material on critical path, see note below, and
::[https://agriculture.ks.gov/divisions-programs/dwr/stream-and-floodplain-permits '''Kansas DWR'''];
*distribute City's Standard Bid Items to be used during design.  
::[https://www.opkansas.org/city-services/permits-licenses-inspections-directory/'''Floodplain Development Permit'''];
*detours/street closings;
*project phasing/traffic control;
*identify equipment or material on critical path (see note below);
*distribute City's Standard Bid Items to be used during design;
*coordinate with Engineering Services for development projects permitted in the area.  


{{Note|It may be necessary to purchase equipment or material in advance of actual project letting date. Generally this will involve separate purchasing contracts for signal poles, LED's, signal cabinets, controllers and load switches. Items on the critical path that could delay the project completion date should be identified and the need for separate purchasing contracts discussed.}}
{{Note|''It may be necessary to purchase equipment or material in advance of actual project letting date. Generally this will involve separate purchasing contracts for signal poles, LED's, signal cabinets, controllers and load switches. Items on the critical path that could delay the project completion date should be identified and the need for separate purchasing contracts discussed. The BLP project manager should also be included in discussions to make sure federal/state requirements are met for the pre-purchased items''.}}


== Task No. 11 - Design Criteria ==
== Task No. 9 - Design Criteria ==
Streets shall be designed in accordance with the following:
{{Top}}
*Current edition of the A Policy on Geometric Design of Highways and Streets by the American Association of State Highway and Transportation officials.


*[http://www.ksdot.org:9080/burConsMain/specprov/2007SSDefault.asp Current edition of the Standard Specifications for State Road and Bridge Construction for KDOT.]
:Project design shall be in accordance with accepted engineering practices and all applicable state, AASHTO and federal Criteria. These criteria include, but not limited to the following references:
*Current edition of the Non-NHS Local Road and Street Plan for KDOT.
 
*[http://www.opkansas.org/Overland-Park-Municipal-Code Current City of Overland Park Municipal Code.]
*'''Public and Private Streets'''
**[http://www.opkansas.org/App_/ROOT/Module/CityGovernment/Engine/DocumentForm/StreamFile.ashx?documentId=1302-Materials-Material-Tests-and-Inspections Municipal Code Chapter 13.02 Materials, Materials Tests, and Inspections]
 
**[http://www.opkansas.org/App_/ROOT/Module/CityGovernment/Engine/DocumentForm/StreamFile.ashx?documentId=1303-Street-Construction-Standards Municipal Code Chapter 13.03 Street Construction Standards]
::Current edition of AASHTO's [https://store.transportation.org'''A Policy on Geometric Design of Highways and Streets''' 2018, 7th Edition] (Green Book). (See ''K:\Library\References\AASHTO'')
**[http://www.opkansas.org/App_/ROOT/Module/CityGovernment/Engine/DocumentForm/StreamFile.ashx?documentId=1305-Street-Lighting Municipal Code Chapter 13.05 Street Lighting]
::Current edition of KDOT's [https://www.ksdot.org/bureaus/burConsMain/specprov/2015specprov.asp '''Standard Specifications for State Road and Bridge Construction'''.]
**[http://www.opkansas.org/App_/ROOT/Module/CityGovernment/Engine/DocumentForm/StreamFile.ashx?documentId=1308-Sidewalk-Construction-and-Repair Municipal Code Chapter 13.08 Sidewalk Construction and Repair.]
::Current edition of KDOT's [[Media:2020 LPA Manual.pdf|'''LPA Project Development Manual''']].
**[http://www.opkansas.org/App_/ROOT/Module/CityGovernment/Engine/DocumentForm/StreamFile.ashx?documentId=1312-Construction-on-Rights-of-Way Municipal Code Chapter 13.12 Construction on Rights-of-Way.]
::Current City of Overland Park [http://online.encodeplus.com/regs/overlandpark-ks/doc-viewer.aspx#secid-1 '''Municipal Code'''.]
**[http://www.opkansas.org/App_/ROOT/Module/CityGovernment/Engine/DocumentForm/StreamFile.ashx?documentId=1510-Stormwater-Management-Program-Standards-and-Permitting Municipal Code Chapter 15.10 Stormwater Management Program - Standards and Permitting]
:::[http://online.encodeplus.com/regs/overlandpark-ks/doc-viewer.aspx#secid-3613 '''Chapter 13.10''' Public Street, Streetlighting and Sidewalk Requirements]
*'''Stormwater Management'''
:::[http://online.encodeplus.com/regs/overlandpark-ks/doc-viewer.aspx#secid-3641 '''Chapter 13.12''' Construction on Rights-of-Way.]
**Design Criteria - Stormwater Management Facilities This is the City Engineer's Minimum Stormwater Standards and is a supplement to APWA Section 5600.
:::[http://online.encodeplus.com/regs/overlandpark-ks/doc-viewer.aspx#secid-4036 '''Chapter 15.10''' Stormwater Management Program - Standards and Permitting]
::Current City of Overland Park Design and Construction Standards [[Media:2021 Design Criteria Volume 1 - as Posted to website 06.11.2021.pdf|'''Volume 1 Design Criteria''']] and [[Media:2021 Design Criteria Volume 2 - Specifications as posted to website 06.15.2021.pdf|'''Volume 2 Construction Specifications''']]
*'''Stormwater Conveyance and Treatment Facilities'''
:Current City of Overland Park Design and Construction Standards [[Media:2021 Design Criteria Volume 1 - as Posted to website 06.11.2021.pdf|'''Volume 1 Design Criteria''']] and [[Media:2021 Design Criteria Volume 2 - Specifications as posted to website 06.15.2021.pdf|'''Volume 2 Construction Specifications''']] as a supplement to [http://kcmetro.apwa.net/content/chapters/kcmetro.apwa.net/file/Specifications/APWA5600.pdf'''APWA Section 5600'''].
*'''Erosion and Sediment Control'''
*'''Erosion and Sediment Control'''
**Design Criteria - Erosion and Sediment Control This is the City Erosion and Sediment Control Standards and is a supplement to APWA Section 5100.
:Current City of Overland Park Design and Construction Standards [[Media:2021 Design Criteria Volume 1 - as Posted to website 06.11.2021.pdf|'''Volume 1 Design Criteria''']] and [[Media:2021 Design Criteria Volume 2 - Specifications as posted to website 06.15.2021.pdf|'''Volume 2 Construction Specifications''']] as a supplement to [http://kcmetro.apwa.net/content/chapters/kcmetro.apwa.net/file/Specifications/APWA5100.pdf'''APWA Section 5100'''].
**For an additional resource refer to Designing Erosion Control on a Thoroughfare or Public Works Project. This resource provides guidelines on preparing erosion control strategies and plans.
*'''Traffic Signals'''
*Traffic signals, signing and pavement markings shall be designed in accordance with the latest edition of Manual on Uniform Traffic Control Devices.
:Traffic signals shall be designed in accordance with the latest edition of the [http://mutcd.fhwa.dot.gov/kno_2009r1r2.htm '''Manual on Uniform Traffic Control Devices''']. Traffic signal mast arm poles shall be designed in accordance with the [http://www.tsp2.org/2013/05/29/aashto-releases-new-specifications-for-structural-supports-for-highway-signs-luminaries-and-traffic-signals/ '''2013 AASHTO Standard Specifications for Structural Supports for Highway Signs, Luminaires and Traffic Signals, Sixth Edition, LTS-6'''].
*Streetlights shall be designed in accordance with Resolution No. 2827 and the City’s Streetlighting Design Guide.
*'''Permanent Traffic Control Signs'''
{{Exhibit2|II-11a.dot|No. II-11a|is a two page instructional letter with references regarding the design of street lights.}}
:Permanent traffic control signs shall be designed in accordance with the latest edition of the [http://mutcd.fhwa.dot.gov/kno_2009r1r2.htm '''Manual on Uniform Traffic Control Devices'''] and the City's [http://ppm.opkansas.org/wiki/index.php/Traffic_Sign_Design_Guidelines '''Traffic Sign Design Manual'''].
*Work Zone Traffic Control shall be designed in accordance with the City’s Traffic Control Handbook.
*'''Pavement Markings'''
*City of Overland Park Bridge Design Information
:Pavement markings shall be designed in accordance with the latest edition of the [http://mutcd.fhwa.dot.gov/kno_2009r1r2.htm '''Manual on Uniform Traffic Control Devices'''] and the City's [http://ppm.opkansas.org/wiki/index.php/Pavement_Marking_Design_Manual#top '''Pavement Marking Design Manual'''].
*'''Streetlights'''
:Streetlights shall be designed in accordance with [http://online.encodeplus.com/regs/overlandpark-ks-gbp/doc-viewer.aspx#secid-198 '''Resolution No. 4036'''] and the City's [http://ppm.opkansas.org/wiki/index.php/Streetlight_Design_Manual '''Streetlighting Design Manual'''].
 
:Current City of Overland Park Design and Construction Standards [[Media:2021 Design Criteria Volume 1 - as Posted to website 06.11.2021.pdf|'''Volume 1 Design Criteria''']]. Refer to Part F for the design criteria for all streetlighting projects.
*'''Traffic Control'''
:Work Zone Traffic Control shall be designed in accordance with the City’s [[Media:Traffic-Control-Handbook-July-2016.pdf| '''Traffic Control Handbook''']].
*'''Bridges'''
:City of Overland Park Bridge Design Information
{{Exhibit2|II-9a.docx|No. II-9a|is a list of bridge design information.}}
{{Exhibit2|2018 Bridge Inventory SOP.pdf|No. II-9b|is Public Works Department Bridge Asset Inventory Procedure (February 2018).}}
:Also see
::Chapter [[Media:6.0 Bridge Design 2020.pdf|'''6.0 Bridge Design]] of KDOT's '''LPA Project Development Manual'''
::[https://kart.ksdot.org '''LRFD Bridge Design Manual, Volume III'''], KDOT, current edition. (See ''K:\Library\References\KDOT Design Manual\KDOT Bridge Design Manual December 2021.pdf'')
::[https://store.transportation.org '''LRFD Bridge Design Specifications'''], AASHTO, current edition


{{Exhibit2|II-11b.dot|No. II-11b|is a list of bridge design information.}}
{{Exhibit2|II-11c.pdf|No. II-11c|is Public Works Department Bridge Asset Inventory Procedure (January 2007).}}
::[[media:BLP-Memo-05-15.pdf|'''BLP Memo 05-15 Geotechnical Bridge Foundation Investigation Practice.''']]
*'''Johnson County Wastewater'''
*'''Johnson County Wastewater'''
{{Exhibit2|II-11d.pdf|No. II-11d|Designers Checklist for City Streets and Stormwater Improvements.}}
{{Exhibit2|II-9c.pdf|No. II-9c|Designers Checklist for City Streets and Stormwater Improvements.}}
{{Exhibit2|II-11e.pdf|No. II-11e|Memo from JCW on existing brick manholes with new cone sections.}}
{{Exhibit2|II-9d.pdf|No. II-9d|Memo from JCW on existing brick manholes with new cone sections.}}
:*For city street or stormwater improvement projects that require sanitary sewer relocation or extension, full sanitary sewer design plans per JCW minimum plan requirements must be approved by JCW. See Procedures for Privately Financed Gravity Sewer Main Extension and Minimum Plan Requirements.
:For city street or stormwater improvement projects that require sanitary sewer relocation or extension, full sanitary sewer design plans per JCW plan requirements and specifications must be approved by JCW. See below for requirements.
:*For the status of sanitary sewer plan submittals and projects see Johnson County Wastewater Sewer Project Status page.  
 
:*Also see [[#Task No. 9 - Schedule First Utility Meeting | Phase II, Task No. 9]] for Right-Of-Way agreement between JCW and City of Overland Park.
::[https://www.jocogov.org/sites/default/files/documents/JCW/Procedures%20Privately%20Fin%20Gravity%20Main%20Projects%20Web.pdf '''Procedures for Privately Financed Gravity Sewer Main Projects''']
*Current Johnson County Stormwater Management Program Policy and Procedures.
::[https://www.jocogov.org/sites/default/files/documents/JCW/Minimum%20Plan%20Requirements%20for%20Private%20Main%20Projects%20FINAL%20VERSION%204-6-17.pdf '''Minimum Plan Requirements for Gravity Sewer Main Projects''']
 
::[https://jocogov.org/sites/default/files/documents/JCW/2019_approved_jcw_const_and_mat_specs.pdf '''Construction and Material Specifications for Sanitary Sewers''']
 
::[https://www.jocogov.org/sites/default/files/documents/JCW/JCW-00%20Sanitary%20Sewer%20Standard%20Details.pdf '''Sanitary Sewer Standard Details'''].
:For the status of sanitary sewer plan submittals and projects see Johnson County Wastewater [https://www.jocogov.org/dept/wastewater/development-and-permitting/permitting/commercial '''Commercial Permitting'''] page.  
:Also see [[#Task No. 7 - Initiate Utility Coordination. Schedule Utility Meeting (optional)| '''Phase II, Task No. 7''']] for Right-Of-Way agreement between JCW and City of Overland Park.
*'''Current Johnson County Stormwater Management Program Policy and Procedures'''
::See [[Phase_I_-_Vision#Task_3_-_Prepare_SMAC_Project_Addition_Study_.28Form.29 |'''Phase I, Task No. 3''']]
*'''Additional Design Guidance for Reference:
::[https://store.transportation.org '''"Roadside Design Guide"'''], AASHTO, current edition;
::[http://www.trb.org/Main/Blurbs/175169.aspx '''"Highway Capacity Manual"'''](HCM), current edition;
::[https://store.transportation.org/search?q=guide%20for%20the%20development%20of%20bicycle%20facilities&categoryCode=&index=storeitem&type=All&pageNum=1&pageSize=10&sortBy=Relevance&itemType=All"'''Guide for the Development of Bicycle Facilities'''"], AASHTO, current edition. (See ''K:\Projects\Manual\AASHTO Guide for the Development of Bicycle Facilities 2012.pdf'').
::[https://www.access-board.gov/guidelines-and-standards '''American with Disabilities Act (ADA) Guidelines and Standards'''], United States Access Board;
::[https://www.access-board.gov/guidelines-and-standards/streets-sidewalks/public-rights-of-way/proposed-rights-of-way-guidelines '''Proposed Guidelines for Pedestrian Facilities in the Public Right-of-Way (PROWAG)'''], United States Access Board;
::[https://nacto.org/publication/urban-street-design-guide '''"Urban Street Design Guide"'''] NACTO, current edition;
::[https://nacto.org/wp-content/uploads/2013/10/Vega-BarachowitzDavid_DesigningCitiesPHX.pdf '''"Urban Bikeway Design Guide"'''] NACTO, current edition;
::[https://www.ksdot.org/bureaus/burTrafficEng/Roundabouts/Roundabout_Guide/RoundaboutGuide.asp '''"Kansas Roundabout Guide"'''] KDOT, current edition;
::[https://www2.opkansas.org/files/dw/api/Docs/10346?_ga=2.223749341.794450718.1632400335-1136848853.1626367100'''Greenway Linkages Plan for Overland Park'''];
::[https://www2.opkansas.org/files/dw/api/Docs/9412?_ga=2.224313565.794450718.1632400335-1136848853.1626367100'''South Overland Park Transportation Plan'''];
::[https://www.opkansas.org/city-services/traffic-roads-transportation/bicycling/'''Overland Park Bicycle Master Plan'''];
::[https://nacto.org/docs/usdg/nchrprpt672.pdf'''FHA Roundabouts Informational Guide'''].
*'''Design Exceptions:
:If, during the development of plans for proposed project, it is determined that there are circumstances that may make it impractical to meet the applicable guidelines, the Consultant/Project Manager shall fill out the following forms:
 
:Use [[Media:Design exceptions.docx|'''Design Exceptions''']] form to document all design exceptions and save it to the project preliminary design folder.
 
:Use [[Media:Design deviations.docx|'''Design Deviations''']] form to document design deviations, revisions to the standard design that do not adversely impact the design intent, and save to the project preliminary design folder.
 
: See [[#Task No. 18 - Submit Request for Design Exception to KDOT| '''Phase II, Task No. 18''']] for design exceptions on federally funded projects.
 
== Task No. 10 - Standard Details ==
{{Top}}
 
The City's Public Works Department maintains and updates [https://www.opkansas.org/city-services/building-construction/civil-engineering/construction-standards/ '''Standard Details'''] for publicly funded projects under the direction of the City Engineer.
If Johnson County Wastewater facilities are involved in the project, [https://www.jocogov.org/sites/default/files/documents/JCW/JCW-00%20Sanitary%20Sewer%20Standard%20Details.pdf '''Sanitary Sewer Standard Details'''] shall be incorporated into the plans.
 
Also, the following are typical thoroughfare sections to be used for the infrastructure improvements as recommended by [https://dw.opkansas.org/public/FileCabinets/2fa13812-70a3-4126-848b-3a20df7175c3/Documents/9412/FileDownload?targetFileType=Auto&keepAnnotations=false '''South Overland Park Transportation Plan''']:
 
[[Media:Thoroughfare Ultimate 4- and 3-Lane Sections March-2022.pdf|'''Ultimate 4- and 3-Lane Thoroughfare Sections''']];
 
[[Media:Thoroughfare Ultimate 2-Lane Sections March-2022.pdf|'''Ultimate 2-Lane Thoroughfare Sections''']];
 
[[Media:Thoroughfare Interim Sections March-2022.pdf|'''Interim Thoroughfare Sections''']].


See [[Phase_I_-_Vision#Task_3_-_Prepare_SMAC_Project_Addition_Study_.28Form.29 |Phase I, Task No. 3]]
== Task No. 11 - SMAC Preliminary Study ==
{{Top}}


== Task No. 12 - Standard Details ==
For SMAC funded projects a preliminary study should be prepared and delivered to Johnson County SMAC officials prior to beginning any design work.  
Standard details have been compiled for the City Public Works Department. The standard details can be downloaded from


http://www.opkansas.org/_Bus/Pre-construction_Resources/detaildraw.cfm
See [[Phase_I_-_Vision#Task_3_-_Prepare_SMAC_Project_Addition_Study_.28Form.29|'''Phase I, Task No. 3''']] for details and checklist for preparing this study.


If Johnson County Wastewater facilities are involved in the project their standard details shall be incorporated into the plans. JCW standard details can be downloaded from http://www.jcw.org/engforms.htm
== Task No. 12 - Other Agency Agreements (if Applicable) ==
{{Top}}


== Task No. 13 - SMAC Preliminary Study ==
Local government agency agreements should be executed under [[Phase_I_-_Vision#Task_11_-_Execute_Other_Agency_Agreements|'''Phase I, Task No. 11''']]. If these agreements were not executed prior to beginning of design, execution shall be completed at this time in the preliminary design phase.
SMAC Preliminary Study - A preliminary study should be prepared and delivered to Johnson County SMAC officials prior to beginning any design work.  


See [[Phase_I_-_Vision#Task_3_-_Prepare_SMAC_Project_Addition_Study_.28Form.29|Phase I, Task No. 3]] for details and checklist for preparing this study.
== Task No. 13 - Conduct Field Surveys ==
{{Top}}


== Task No. 14 - Agency Agreement (if Applicable) ==
Sufficient and required data necessary for design purposes shall be collected. The field survey shall be in accordance with state statutes, and current accepted and required surveying practices. Prior to the beginning of land survey or utility relocation work the letter to the residences adjacent to the project will be mailed out informing property owners of upcoming activities. Included with the letter is flood questionnaire to be used for storm drainage improvements consideration.
Local government agency agreements should be executed under [[Phase_I_-_Vision#Task_23_-_Execute_Local_Project_Agreement_-_CARS|Phase I, Task No. 23]]. If these agreements were not executed prior to beginning design, execution shall be completed at this time in the preliminary design phase.
:[[Media:Pre-survey letter.pdf|'''Exhibit No. II-13a''']] ''is a sample pre-survey letter to residents''.
:[[Media:Flooding Questionnaire Template.doc|'''Exhibit No. II-13b''']] ''is a flood questionnaire''.


== Task No. 15 - Conduct Field Surveys ==
See City standard Scope of Services in [[Phase_II_-_Preliminary_Design#Task_No._3_-_Consultant_Selection.2FCertification|'''Phase II, Task 3''']] for survey control requirements.
Sufficient and required data necessary for design purposes shall be collected. The field survey shall be in accordance with current accepted and required surveying practices. See City standard Scope of Services in [[#Task_No._3-4_-_Hire_Consultant|Preliminary Design, Task 3-4]] for survey control requirements.
 
{{Note| Any Johnson County Vertical Control Network Bench Marks that will be disturbed as part of the project must be reset. The standard specification and a bid item for this work must be included in the contract documents.  These benchmark locations can be found on Johnson County [https://maps.jocogov.org/ims/'''AIMS Mapping'''] web page under the Utilities layer.}}
 
== '''Task No. 14 - Continue Environmental Process''' ==
{{Top}}
 
Once authorization for the project is completed, KDOT will complete an initial review of the project location and scope to determine the degree of analyses that is required in order to comply with State and Federal environmental laws and regulations.
 
The BLP will receive from the City the Form [http://www.ksdot.org/Assets/wwwksdotorg/bureaus/burlocalproj/Forms/1307.pdf '''1307'''], along with all applicable permits attached, prior to obligation of funds, to comply with the NEPA process. (See [[Phase_III_-_Final_Design#Task_No._14_-_Submit_PS&E_Package|'''Phase III, Task No. 14''']]).
If detailed environmental analyses are required, the investigation will be initiated at this time. Final and complete analyses and application for permits by the City may be completed after Field Check and detailed design information is available. All investigation and permit acquisitions will be conducted in accordance with the referenced manual and BLP Policy Memos.


== Task No. 16 - Begin Environmental Process ==
KDOT will control the environmental process task for projects with categorical exclusion. The complexity and effort will depend on each project. The exception would be if an Environmental Assessment or an Environmental Impact Statement is required. In this case, the City or Consultant would perform this task with KDOT and FHWA approval.
KDOT will control the environmental process task for projects with categorical exclusion. The complexity and effort will depend on each project. The exception would be if an Environmental Assessment or an Environmental Impact Statement is required. In this case, the City or Consultant would perform this task with KDOT and FHWA approval.


{{Exhibit|II-16.xlt|No. II-16|is a spreadsheet KDOT uses in tracking Overland Park administered projects.}}
{{Note|''For KDOT Projects this task is tracked by KDOT. ''The Project Engineer shall ensure this task is complete''.}}


The Project Engineer shall ensure that all items on the tracking sheet are completed.
For more information see Chapter [[Media:4.0 Environmental 2020.pdf|'''4.0 Environmental''']] of KDOT's LPA Project Development Manual.


== Task No. 17 - Schedule First Public Information Meeting ==
== Task No. 15 - Schedule First Public Information Meeting ==
Pre-Design - The Consultant/Project Manager shall schedule the first public information meeting. This meeting shall occur prior to beginning preliminary design and field surveys. The purpose of this meeting is to explain the project objectives, present the project schedule, hear the citizen's concerns and issues, discuss design issues and introduce the involved City Officials and Consultant employees.  For KDOT projects the Notice of Public Information Meeting must be published in the [http://www.kssos.org/pubs/pubs_kansas_register.asp Kansas Register] and [http://sunpublications.com Overland Park Sun.]
{{Top}}


The first public information meeting is scheduled by the Consultant/Project Manager. This meeting shall occur during preliminary design and after field surveys. The purpose of this meeting is to present the concept plan, project schedule, hear citizen's concerns, answer questions, discuss design issues and introduce the involved City Officials and Consultant employees.  For KDOT projects the Notice of Public Information Meeting must be published in the [http://www.kssos.org/pubs/pubs_kansas_register.asp '''Kansas Register'''] and [http://www.thelegalrecord.net '''The Legal Record'''].


Public information invites shall be sent to the following interested parties:
Public information invites shall be sent to the following interested parties:
*Subdivisions adjacent to the project  
*Subdivisions adjacent to the project  
*Home Owners Associations adjacent to the project (list of registered HOA available at communications desk)
*Home Owners Associations adjacent to the project. Contact the City Manager's office for a current list of HOA contacts.
*Group Chairperson for [http://www.opkansas.org/Resident-Resources/Conservation-Program Neighborhood Conservation Groups] adjacent to the project.  
*Group Chairperson for [https://www.opkansas.org/city-services/neighborhoods/neighborhood-conservation-program/ '''Neighborhood Conservation Groups'''] adjacent to the project.  
::''For the phone number of the group chairperson, contact the Neighborhood Planner at 913/895-6270.''  
::''For the phone number of the group chairperson, contact the Neighborhood Planner at 913/895-6270.''  


*Council Members of [http://www.opkansas.org/Resource_/PageResource/Maps-And-Stats/Maps/Adobe-Acrobat-PDF-Maps/wards.pdf Ward(s)] adjacent to the project  
*Council Members of [https://www.opkansas.org/city-government/city-council/ '''Ward'''(s)] adjacent to the project  
*City Manager  
*City Manager  
*City Communications Manager  
*City Communications Manager and Communications Assistant
*Funding Sources (KDOT, CARS, SMAC ...ect)  
*Funding Sources (KDOT, CARS, SMAC, etc.)  
*Other City (Olathe, Leawood ...ect)  
*Other City (Olathe, Leawood, etc.)  
*Public Works Management (PWMG)  
*Public Works Management (PWMG)  
*Supervisory Engineer  
*Supervisory Engineer  
*Construction Inspector  
*Construction Inspector  
*Consulting Firm  
*Consulting Firm
*Facilities Management (if meeting is being held at a City facility)
* If deemed necessary, Project Manager can invite police personnel.




The Property Owner Conversation Log should be used throughout the project to document all conversations with property owners.
The Property Owner Conversation Log should be used throughout the project to document all conversations with property owners.


{{Note|This and all subsequent Public Information Meeting notices should ask if participants need a language interpreter or a hearing assistance device and a phone number. All meeting rooms shall be ADA accessible. Title VI flyers regarding equal opportunity contracting are to be available at all public meetings.
}}


{{Exhibit|II-17.dot|No. II-17|is an example Invitation Letter to property owners.}}
{{Note|''This and all subsequent Public Information Meeting notices should ask if participants need a language interpreter or a hearing assistance device and a phone number. All meeting rooms shall be ADA accessible.'' The KDOT '''Equal Opportunity and Civil Rights Information''' brochure in [[Media:Title VI Brochure English.pdf|'''English''']] and [[Media:Title VI Brochure Spanish.pdf|'''Spanish''']] is to be made available at all public meetings.}}
{{Exhibit|II-17a.dot|No. II-17a|is an example Notice of Public Information Meeting.}}
 
{{Exhibit|II-17b.dot|No. II-17b|is a public meeting sign in sheet.}}
{{Exhibit|Exhibit No. II-15.docx|No. II-15|is an example Invitation Letter to property owners.}}
{{Exhibit|II-17c.dot|No. II-17c|is a public meeting agenda.}}
{{Exhibit|Exhibit No. II-15a.pdf|No. II-15a|is an example Notice of Public Information Meeting.}}
{{Exhibit|II-17d.dot|No. II-17d|is a public meeting handout.}}
{{Exhibit|Public Meeting Sign-In Sheet .docx|No. II-15b|is a public meeting sign in sheet.}}
{{Exhibit|Exhibit No. II-15c.docx|No. II-15c|is an example Public Meeting Citizen Comment Form.}}
{{Exhibit|II-15d flyer.pdf|No. II-15d|is an example Public Meeting Handout.}}
 
 
 
For those who wish to use a Blue Valley School District facility for the public meeting, an on-line [https://www.bluevalleyk12.org/Page/34388 '''Facility Rental Reservation Request'''] is available. Once the request is submitted, the BVSD Facility Scheduling Office will send a confirmation if the requested space is available.


== Task No. 18 - Begin Title Report Process ==  
== Task No. 16 - Begin Title Report Process ==
{{Top}}
The Consultant and/or the Project Manager shall prepare an RFP and forward to a minimum of three land title firms. The RFP should include a map or plan indicating the location of the project and the number of tracts of land involved. Proposals will be forwarded to the Project Manager whereby a firm will be selected and an agreement executed. The RFP should request the following information:
The Consultant and/or the Project Manager shall prepare an RFP and forward to a minimum of three land title firms. The RFP should include a map or plan indicating the location of the project and the number of tracts of land involved. Proposals will be forwarded to the Project Manager whereby a firm will be selected and an agreement executed. The RFP should request the following information:
*legal description of the property and copy of recorded deed(s),  
*legal description of the property and copy of recorded deed(s),  
Line 256: Line 374:
*records of previous condemnations (available in the office of the District Court of Johnson County Kansas, Olathe, Kansas).  
*records of previous condemnations (available in the office of the District Court of Johnson County Kansas, Olathe, Kansas).  


In addition, the RFP should provide instructions that all data to be provided in electronic disk format acceptable to the City. Finally the RFP will establish a date for completing the title certification and report.  
In addition, the RFP should provide instructions on methods of delivery of the title report acceptable to the City. Finally the RFP will establish a date for completing the title certification and report.  
 
{{Exhibit|II-16a.xlt|No. II-16a|is a list of land title companies to be considered in RFP requests.}}
{{Exhibit|II-16b.dot|No. II-16b|is a sample land title RFP letter.}}
{{Exhibit|II-16c.pdf|No. II-16c|is a sample location map with parcel numbers.}}
{{Exhibit|II-16d.dot|No. II-16d|is a sample letter to selected land title company.}}
{{Exhibit|II-16e.dot|No. II-16e|is a sample letter to land title companies not selected.}}
 
== Task No. 17 - Begin Geotechnical Report Process ==
{{Top}}
 
The Consultant/Project Engineer shall determine what appropriate geotechnical information and data is necessary to adequately design the project.  Drilled shaft foundations for bridges require specialized inspection.  If drilled shaft foundations are anticipated and the Consultant cannot perform this work, the service of a subconsultant may be utilized after receiving written approval from the City.  For projects designed by City Staff an RFP shall be prepared and forwarded to qualified firms.
 
Refer to [[#Task No. 3 - Consultant Selection/Certification| '''Phase II, Task No. 3''']] for information on consultant selection process.
 
{{Exhibit|IV-2a.docx|No. IV-2a|is a list of materials testing / geotechnical service companies.}}


{{Exhibit|II-18a.xlt|No. II-18a|is a list of land title companies to be considered in RFP requests.}}
For projects involving bridge construction, refer to Geotechnical Bridge Foundation Investigation Practice, found in Chapter [[Media:6.0 Bridge Design 2020.pdf|'''6.0 Bridge Design''']] of KDOT's '''LPA Project Development Manual'''.
{{Exhibit|II-18b.dot|No. II-18b|is a sample land title RFP letter.}}
{{Exhibit|II-18c.pdf|No. II-18c|is a sample location map with parcel numbers and a parcel ownership report.}}
{{Exhibit|II-18d.dot|No. II-18d|is a sample letter to selected land title company.}}
{{Exhibit|II-18e.dot|No. II-18e|is a sample letter to land title companies not selected.}}
{{Exhibit|II-18f.dot|No. II-18f|is a list of common easement holders and mortgage companies for use by title companies in completing title certificates.}}


== Task No. 19 - Begin Geotechnical Report Process ==
== '''Task No. 18 - Submit Request for Design Exception to KDOT''' ==
The Consultant/Project Engineer shall determine what appropriate geotechnical information and data is necessary to adequately design the project.  Drilled shaft foundations for bridges require specialized inspection.  If drilled shaft foundations are anticipated and the Consultant cannot provide this service, use of a subconsultant may be used after receiving written approval from the City.  For projects designed by City Staff an RFP shall be prepared and forwarded to qualified firms.
{{Top}}


{{Exhibit|II-19.dot|No. II-19|is a sample RFP letter to geotechnical firms, proposal format, summary of pay items (Attachment A), detailed description and description of services (Attachment B).}}
If, during the development of plans for proposed federally funded projects, it is determined that there are circumstances that may make it impractical to meet the applicable guidelines, the Consultant/Project Manager shall submit in writing to the Bureau of Local Projects (KDOT) any request for project design exceptions, using a summary format like the form in [[Media:Design Exception Request Summary Form 2020.pdf|'''Figure 5.1''']] of the LPA Project Development Manual. A request for a design exception may be made at any time in the design process when sufficient information is available to adequately evaluate the situation.


{{Exhibit|IV-2a.dot|No. IV-2a|is a list of materials testing / geotechnical service companies.}}
All design exceptions are subject to approval by the Bureau Chief of BLP. The request may involve one or more of the following controlling criteria: design speed, lane and shoulder width, bridge width, structural capacity, horizontal and vertical alignment, grades, stopping sight distance, cross slopes, superelevation, horizontal and vertical clearances. Justification for the request shall be included along with cost estimates for reasonable alternates. Supporting documents should be consistent with Section 2.3.4 of the KDOT Design Manual, Volume I, Bureau of Road Design.


For projects involving bridge construction, [[media:BLP-Memo-05-15.pdf|'''BLP Memo 05-15 Geotechnical Bridge Foundation Investigation Practice''']] is to be used when writing contracts for geotechnical services.
(See '''KDOT Road Design Manual 2014.pdf''' in ''K:\Library\References\KDOT Design Manual'').


== Task No. 20 - Prepare Field Check Plans ==
For design exceptions documentation, use Overland Park [[Media:Design exceptions.docx|'''Design Exceptions''']] form to be submitted in addition to the KDOT form.  
Plans should be approximately 50 percent complete for field check review including any proposed easement and R/W takings along with a preliminary construction cost estimate and updated project schedule/checklist. The plans shall be stamped "Preliminary—Field Check".
{{Exhibit|I-25b.xlt|No. I-25b|is a project schedule/checklist.}}


See [[media:Blp-memo-03-12.pdf|'''BLP Memo 03-12 Engineer's Professional Seal and Signature on Plans.''']]
For projects with other funding sources all requests for design exceptions shall be directed to the City Engineer.


== Task No. 21 - Distribute Plans ==
Document all design exceptions regardless of funding on [[Media:Design exceptions.docx|'''Design Exceptions''']] form and save to the project preliminary design folder.
The Consultant/Project Manager shall distribute preliminary plans to all utility company representatives. With this letter, the utility company representatives are advised of the second utility meeting.


Exhibit No. II-21 is a sample transmittal letter to utility company representatives.
For more information see section 5.2.2.2 (Design Exception/Allowance) in Chapter [[Media:5.0 Plan Development 2020.pdf|'''5.0 Plan Development''']] of KDOT's '''LPA Project Development Manual'''.


{{Exhibit|II-9.dot|No. II-9|is a list of Johnson County utility and pipeline companies, possible contacts, address and phone numbers.}}
For additional information regarding design exceptions on  non-KDOT projects refer to [[#Task No. 9 - Design Criteria| '''Phase II, Task No. 9''']] .


== Task No. 22 - Distribute Plans for Field Check ==
== Task No. 19 - Prepare Field Check Plans ==
The Consultant/Project Engineer shall distribute field check plans along with a copy of the project cost estimate and updated project schedule/checklist to the following:
{{Top}}
*all members of the Project Team (see below for Maintenance Division routing),
*City Engineer,
*City Traffic Engineer,


BLP for KDOT projects (if applicable), and  
Plans should be approximately 50 percent complete for field check review including any proposed easement and R/W takings along with a preliminary construction cost estimate and updated project schedule/checklist. The plans shall be stamped "Preliminary—Field Check".
{{Exhibit|I-13b.xlt|No. I-13b|is RUPIS project schedule.}}


other agency participants.  
See [[Media:Blp-memo-03-12.pdf|'''BLP Memo 03-12 Engineer's Professional Seal and Signature on Plans.''']]


The Project Manager will send one set of plans to the Maintenance Division District in which the project is located. The plans will go to the appropriate functional Supervisor using the Maintenance Plan Review Memo located under the Public Works tab of the General Templates in Microsoft Word. See Maintenance Plan Review Process for more information.  
For Field Check Plans preparation and submittal requirements on federally funded projects refer to Chapter [[Media:5.0 Plan Development 2020.pdf|'''5.0 Plan Development''']] of KDOT's '''LPA Project Development Manual'''.


{{Note|For KDOT Projects this task is tracked by KDOT see Exhibit No. II-16. The Project Engineer shall ensure this task is complete.}}
== Task No. 20 - Distribute Plans to Utility Companies. Schedule Utility Meeting. ==
{{Top}}


== Task No. 23 - Submit Request for Design Exception to KDOT ==
The Consultant/Project Manager will distribute field check plans to all utility company representatives and schedule the utility meeting. An agenda should accompany the meeting invite. Meeting minutes will be prepared following the meeting and distributed to all scheduled attendees.
The Consultant/Project Manager shall submit in writing to the Chief, Bureau of Local Projects (KDOT) any request for project design exceptions. The letter should list each design exception and fully explain the reason for the design exceptions.


== Task No. 24 - Schedule Second Utility Meeting ==
{{Note|''When scheduling utility meeting in Google calendar, in order to avoid conflicts with other utility meetings, CH-PW Utilities (found under Rooms tab) shall be "invited" as an attendee to all meetings, pre-bid conferences and pre-construction conferences or any meetings that require utility company attendance''.}}
When the Preliminary Plans are distributed to the utility companies, the second utility meeting is scheduled. An agenda shall accompany the letter and meeting minutes prepared and distributed.
Note:  In an effort to avoid scheduling conflicts with other called utility meetings an Outlook calendar has been created called PW Utilities. PW Utilities shall be invited as an attendee to all utility meetings, pre-bid conferences and pre-construction conferences or any meeting requesting utility company attendance.


The purpose of the second utility meeting is as follows:
The purpose of the utility meeting is as follows:
*check accuracy of utility locations on plans,  
*check accuracy of utility locations on plans,  
*establish what utilities need to be relocated,  
*establish what utilities need to be relocated,
*See [[Media:KCP&L DWG 130.1-12.pdf|'''Evergy DWG 130.1-12''']] for clearance requirements from signal or streetlight poles to utility lines. Verify all poles have proper clearance.
*establish timetable for accomplishing the relocations, and  
*establish timetable for accomplishing the relocations, and  
*re-confirm utility representative contacts.  
*re-confirm utility representative contacts.  


See [[#Task No. 9 - Schedule First Utility Meeting|Phase II, Task No. 9 for exhibits.]]
See [[#Task No. 7 - Initiate Utility Coordination. Schedule Utility Meeting (optional)|'''Phase II, Task No. 7''']] for exhibits.
 
== Task No. 21 - Update Preliminary Cost Estimate ==
{{Top}}
 
The Consultant/Project Manager shall prepare and submit an updated preliminary construction cost estimate. The form for this estimate shall resemble the Bid form with the item description, unit, approximate quantity, unit price and total. KDOT-BLP should receive a copy of this estimate.
 
All cost estimates shall utilize the City's [https://ppm.opkansas.org/wiki/index.php?title=Bid_item_list '''Standard Bid Items'''] and correspond to the measurement and payment as shown in the [https://ppm.opkansas.org/wiki/index.php?title=City_of_Overland_Park_Standard_Specifications_-_2020 '''City of Overland Park Standard Specifications'''].
 
== Task No. 22 - Update Preliminary Cash Flow Projection ==
{{Top}}
 
The Consultant/Project Manager shall prepare a preliminary cash flow projection, including construction costs, and submit it to the City Finance Department on the standard form.
 
See [[Media:Cash Flow TH-1027 6-2019 Rome.xlsx|'''Exhibit II-6''']].
 
== Task No. 23 - Distribute Plans for Field Check ==
{{Top}}
 
The Consultant/Project Engineer shall distribute field check plans along with a copy of the project cost estimate and updated RUPIS project schedule electronically via '''Bluebeam''' session to the following:
*all members of the Project Team (see [[Media:Maintenance Plan Review Process 2020.docx|'''Maintenance Plan Review Process''']] for Maintenance Division routing),
*City Engineer,
*City Traffic Engineer,
 
For KDOT projects the electronic field check plans shall be provided to the BLP for transmittal to the Environmental Services Section(KDOT), who will transmit plans to appropriate regulatory and resource agencies. Invitations to the regulatory and resource agencies to participate in the field check should be rendered if environmental mitigation is required. The Consultant/Project Engineer shall provide a project cost estimate to the BLP with the plans.
 
For the instructions on submitting E-Plans to BLP see the following:''
 
[https://www.ksdot.org/Assets/wwwksdotorg/bureaus/burLocalProj/BLPDocuments/KDOTBLPEplans.pdf '''User Guide for Electronic Plans Review'''];
[https://www.ksdot.org/Assets/wwwksdotorg/bureaus/burLocalProj/BLPDocuments/Eplansdocreq.pdf '''Specifications for Electronic Plans Submittal'''];
[https://www.ksdot.org/Assets/wwwksdotorg/bureaus/burLocalProj/BLPDocuments/KDOT_FTP_Instructions.pdf '''FTP Instructions'''].
 
 
{{Note|''For KDOT Projects this task is tracked by KDOT.  ''The Project Engineer shall ensure this task is complete''.}}
 
== Task No. 24 - Submit Required Permit Applications ==
{{Top}}


== Task No. 25 - Submit Required Permit Applications ==
The Consultant/Project Manager shall determine what permits will be required in order to construct the project. The following is a list of possible permits required:
The Consultant/Project Manager shall determine what permits will be required in order to construct the project. The following is a list of possible permits required:
   
   
*City of Overland Park Floodplain Development Permit - necessary for any work in a FEMA floodplain, including areas that will be FEMA floodplain once Johnson County Watershed studies are adopted.
*City of Overland Park Floodplain Development Permit - necessary for any work in a FEMA floodplain, including areas that will be FEMA floodplain once Johnson County Watershed studies are adopted.


{{Exhibit|II-25a.pdf|No. II-25a|is a memo of the steps to be taken on Public Works projects.}}
{{Exhibit|II-24a.pdf|No. II-24a|is a memo of the steps to be taken on Public Works projects.}}
{{Exhibit|II-25b.pdf|No. II-25b|is an application and submittal checklist for Floodplain Development Permit.}}
:[https://dw.opkansas.org/public/FileCabinets/2fa13812-70a3-4126-848b-3a20df7175c3/Documents/9615/FileDownload?targetFileType=Auto&keepAnnotations=false '''Exhibit No. II-24b'''] ''is an application and submittal checklist for Floodplain Development Permit''.
{{Exhibit|II-25b-1.pdf|No. II-25b-1|is FEMA's Procedures for "No Rise" Certifications.}}
{{Exhibit|II-24c.pdf|No. II-24c|is FEMA's Procedures for "No Rise" Certifications.}}
 
*[[Media:Temp Erosion & Pollution Control for PW Projects .pdf|'''Temporary Erosion and Pollution Control for Public Works Projects''']] is a memo summarizing permit requirements and project team procedures for Public Works projects.
 
*When a project disturbs more than 1 (one) acre, a Notice of Intent (NOI) permit from Kansas Department of Health and Environment (KDHE) and a Land Disturbance Permit (LDP) from the City of Overland Park are required.
:The NOI permit is submitted during final design phase of the project. The permit submittal requires clearance letters for the project site from the following agencies:
::<u>Kansas Department of Wildlife, Parks and Tourism</u> for threatened or endangered species habitat. Contact KDWPT by emailing the environmental review request (see [[Media:II-24 KDWPT Notification Letter.pdf|'''example''')]] to [email protected].
::<u>Kansas Historical Society</u> for historical and archaeological sites. The information for the project should be submitted to the KSHS via the Kansas Review & Compliance (KSR&C) system. Go to [https://review.kshs.org/Account/Login '''http://review.kshs.org'''] to create an account or log in to an existing account.
:Refer to [[Phase_III_-_Final_Design#Task_No._9_-_Submit_Final_Check_Plans_for_Review|'''Phase III, Task No.9''']] for the NOI application.
:The LDP is obtained prior to commencing construction activities. Refer to [[Phase_V_-_Construction#Task_No._8_-_Complete_Contractor_Permits|'''Phase V, Task No.8''']] for the LDP application.
 
*Permit to Construct-Obstruction in streams from Kansas Department of Agriculture[http://agriculture.ks.gov/divisions-programs/dwr ''' Division of Water Resources'''] is necessary for any work on a stream with more than 240 acres tributary drainage (some exceptions). 
 
:[https://agriculture.ks.gov/docs/default-source/dwr-ws-forms/application-for-2-100-and-3-100-permit.pdf?sfvrsn=2 '''Exhibit No. II-24d'''] ''is DWR application for permit for Obstruction in Streams.''
 
*State of Kansas - Environmental Coordination Act (ECA) - approval letters from various state agencies are typically required for Stream Obstructions permits and sometimes others.  Contacting these agencies directly for their approval letter can accelerate permitting. 
 
:{{Exhibit|II-24e.docx|No. II-24e| is a listing of contact information and addresses for the ECA agencies (current Oct 2015, see KSDA website above for updated lists).}}
 
*[http://www.kdheks.gov/waterwell/download/PluggingAbandonedWells.pdf '''Plugging Packet'''] ''is a handout detailing KDHE's requirements for plugging abandoned water wells.''
 
*Corps of Engineers 404 Permit - necessary for any work located within a "water of the United States", including wetlands.  '''http://www.usace.army.mil/Missions/CivilWorks/RegulatoryProgramandPermits.'''
 
:{{Exhibit|II-24f.pdf|No. II-24f|is a sample letter requesting a project be reviewed for nationwide permit coverage. (Visit [http://www.usace.army.mil/Missions/CivilWorks/RegulatoryProgramandPermits.aspx '''COE website'''] for latest forms and instructions if an individual permit is needed).}}
 
*FEMA Conditional and Final Letters of Map Revision - required for certain type of major work in the floodplain, as coordinated with the floodplain administrator (see City of OP Floodplain Development Permit, above). The latest permit forms and guidance can be obtained from [https://www.fema.gov/national-flood-insurance-program/national-flood-insurance-program-forms '''FEMA's website'''].
 
*KDOT Highway Permits - necessary for construction or utility relocation within KDOT Right of Way:
 
::::'''''Highway Permit Use of Right of Way''''' - [http://www.ksdot.org/Assets/wwwksdotorg/DOT_304_Hwy_permit.pdf KDOT '''Form 304''']
 
::::'''''Cased Utility Line Waiver''''' - [http://www.ksdot.org/Assets/wwwksdotorg/DOT_308_UtilityLine.pdf KDOT '''Form 308''']
 
::::'''''Highway Permit for Highway Access''''' - [http://www.ksdot.org/PDF_Files/DOT-Form-309.pdf KDOT '''Form 309''']
 
::::'''''Highway Permit Attachments to Bridges and Other Structures''''' - [http://www.ksdot.org/Assets/wwwksdotorg/DOT_310_Hwy_Permit_Bridges.pdf KDOT '''Form 310''']
 
::::'''''Access Application Information Sheet''''' - [http://www.ksdot.org/PDF_Files/DOT-Form-334.pdf KDOT '''Form 334''']
 
:See [[Media:KDOT Forms Instructions.pdf|'''Preparation of Application for Highway Permit Agreements''']] for instructions on preparation of KDOT Forms 304, 308, 309 and 334.
 
See [https://www.ksdot.org/Assets/wwwksdotorg/bureaus/burConsMain/Connections/UAP2007_2016_aug.pdf.pdf '''2007 KDOT Utility Accommodation Policy'''] for additional information.
 
All project related state and/or federal permits must be submitted and Form [https://www.ksdot.org/Assets/wwwksdotorg/bureaus/burLocalProj/Forms/1307.pdf '''1307'''] completed prior to submittal of final check plans. (See [[Media:Blp-memo-10-08.pdf|'''BLP Memo 10-08''']]). This shall be completed at least four months prior to project letting.
 
== Task No. 25 - Begin Field Check Plan Review ==
The persons who receive field check plans (see [[#Task No. 23 - Distribute Plans for Field Check|'''Task No. 23''']]) shall commence plan review. The review shall be completed prior to the scheduled Field Check meeting.
 
{{Note| Any Johnson County Vertical Control Network Bench Marks that will be disturbed as part of the project must be reset. The standard specification and a bid item for this work must be included in the contract documents.  These benchmark locations can be found on Johnson County [https://maps.jocogov.org/ims/'''AIMS Mapping'''] web page under the Utilities layer.}}
 
== Task No. 26 - Coordinate Electrical Service for Traffic Signals, Street Lighting and other City Facilities==
If applicable, begin [[Media:II-26 Electrical Services Address Procedures.pdf|'''Electrical Service Address Procedures''']] for streetlighting controllers, traffic signal controllers, electrical control centers for park irrigation controllers, flood warning or road weather information systems.
 
*See [[Media:II-26 KCPL Account Setup Form - Streetlighting.pdf|'''Evergy Account Setup Form - Streetlighting Control Center'''.]]


*City of Overland Park Land Disturbance Permit (LDP) - necessary for any work disturbing more than 1 acre total. ([http://www.kdheks.gov/ KDHE] permit also required, see below).
*See [[Media:II-26 KCPL Account Setup Form - Traffic Signal.pdf|'''Evergy Account Setup Form - Traffic Signal Control Center'''.]]


*Land Disturbance Permit and Erosion and Sediment Control Process is a memo of the steps to be taken on public works projects.
It is important that you specify the electrical service rate in the "Comments" section to insure the City of Overland Park will be billed the correct rate. The correct rate is listed in each of the applicable Service Applications.


:[http://www.opkansas.org/Documents-and-Forms/Detail/Land-Disturbance-Site-Development-Permit-Application '''Exhibit No. II-25d'''] ''is an application for LDP.''
*See [[Media:II-26 Sample Letter to KCP&L for Electrical Service.pdf|'''sample letter''']] to Evergy requesting power service.
*See [https://www2.opkansas.org/files/dw/api/Docs/11032?_ga=2.82690070.1222974240.1645795564-705664753.1645452083 ''' City of Overland Park Tax Exempt Certificate''']
*See [[Media:Form ST-28b Statement for Sales Tax Exemption.pdf|'''Sales Tax Exemption Form ST-28B''']]


*Permit to Construct-Obstruction in streams from [http://www.ksda.gov/dwr/ State Board of Agriculture - Division of Water Resources] - necessary for any work on a stream with more than 240 acres tributary drainage (some exceptions).  http://www.ksda.gov
The Account Form, Overland Park Tax Exempt Certificate and the Sales Tax Exemption Form ST-28B is required to be submitted for each control center.


{{Exhibit|II-25e.pdf|No. II-25e|is DWR application for permit for Obstruction in Streams.}}
== Task No. 26a - Coordinate Compressed Natural Gas (CNG) Service for Traffic Signals ==
{{Top}}


*State of Kansas - Environmental Coordination Act (ECA) - approvals letters from various state agencies are typically required for Stream Obstructions permits and sometimes others. Contacting these agencies directly for their approval letter can accelerate permitting.  http://www.ksda.gov
If applicable, begin [[Media:Natural gas service address procedures.pdf|'''Natural Gas Service Address Procedures''']] for CNG generators.


{{Exhibit|II-25f.dot|No. II-25f| is a listing of contact information and addresses for the ECA agencies (current Dec 2004, see KSDA website above for updated lists).}} 
*[[Media:Kansas city metro gas service area boundary map.pdf|Exhibit 1: '''Kansas City Metro Gas Service Area Boundary Map''']]


*NPDES NOI Permit — Notice of Intent for stormwater discharges associated with construction activity. KDHE - Bureau of Water, Industrial Programs Section. - necessary for any work disturbing more than 1 acre total.  (City of OP LDP also required, see above).  http://www.kdhe.state.ks.us/stormwater
*[[Media:Atmos energy pre-approved contractors list.pdf|Exhibit 2: '''Atmos Energy Pre-Approved Contractors List''']]


{{Exhibit|II-25g.pdf|No. II-25g|is a sample NPDES NOI Permit application.  For a blank application with instructions see the KDHE website.}}
*[[Media:Kansas Gas Service Line Application.docx|Exhibit 3: '''Kansas Gas Service Line Application (rev 01-01-14)''']]
{{Exhibit|II-25h.pdf|No. II-25h|is a copy of the State of Kansas NPDES General Permit for construction.  A copy of this permit must be kept onsite during construction, along with the rest of the Stormwater Pollution Prevention Plan "SWPPP".}}


[[media:Plugging_packet.pdf|Plugging Packet]] is a handout detailing KDHE's requirements for plugging abandoned water wells.
*[[Media:Kansas Gas Cover Letter Sample.docx|Exhibit 4: '''Kansas Gas Cover Letter Sample''']]


*Corps of Engineers 404 Permit - necessary for any work located within a "water of the United States", including wetlands. http://www.nwk.usace.army.mil/regulatory/regulatory.htm
*[[Media:Atmos Energy new meter set application.xlsx|Exhibit 5: '''Atmos Energy New Meter Set Application''']]


{{Exhibit|II-25i.pdf|No. II-25i|is a sample letter requesting a project be reviewed for nationwide permit coverage. (Visit [http://www.usace.army.mil/Pages/default.aspx COE website] for latest forms and instructions if an individual permit is needed).}}
*[[Media:Atmos Energy Elevated Pressure Request Form.pdf|Exhibit 6: '''Atmos Energy Request for Elevated Pressure''']]


*FEMA Conditional and Final Letters of Map Revision - required for certain type of major work in the floodplain, as coordinated with the floodplain administrator (see City of OP Floodplain Development Permit, above) - Obtain latest permit forms and guidance from website. http://www.fema.gov/plan/prevent/fhm/fmc_fmrp.shtm
*[[Media:Atmos Energy Cover Letter Sample.docx|Exhibit 7: '''Atmos Energy Cover Letter Sample''']]


*KDOT Highway Permits - necessary for construction or utility relocation within KDOT Right of Way.
*[https://dw.opkansas.org/public/FileCabinets/2fa13812-70a3-4126-848b-3a20df7175c3/Documents/9614/FileDownload?targetFileType=Auto&keepAnnotations=false Exhibit 8: '''Commercial Building Permit Application''']


{{Exhibit|II-25j.pdf|No. II-25j|is KDOT Form 304, Highway Permit Agreement Use of Right of Way.}}
== Task No. 26b - Coordinate Removal of Streetlights Purchased from Evergy ==
{{Exhibit|II-25k.dot|No. II-25k|is KDOT Form 308, Cased Utility Line Waiver.}}
{{Top}}
{{Exhibit|II-25l.dot|No. II-25l|is KDOT Form 309, Highway Permit for Highway Access.}}
{{Exhibit|II-25m.pdf|No. II-25m|is KDOT Form 310, Highway Permit Agreement Attachments to Bridges and Other Structures.}}
{{Exhibit|II-25n.dot|No. II-25n|is KDOT Form 334, Access Application Information Sheet.}}
{{Exhibit|II-25o.pdf|No. II-25o|is instructions on preparation of KDOT Forms 304, 308, 309 and 334.}}


See [http://www.ksdot.org/burconsmain/connections/uap2007.pdf 2007 KDOT Utility Accommodation Policy] for additional information.
If applicable, begin the [[Media:Removal of Existing Streetlight Procedure.pdf|'''Removal of Existing Streetlight Procedure''']] for streetlights that were purchased from Evergy (KCP&L).


== Task No. 26 - Prepare Preliminary Cost Estimate (update) ==
*See [[Media:Letter to Black & McDonald requesting the removal of streetlights.pdf|'''sample letter to Black & McDonald''']] requesting proposals for removing streetlights.
The Consultant/Project Manager shall prepare and submit an updated preliminary construction cost estimate. The form for this estimate shall resemble the Bid form with the item description, unit, approximate quantity, unit price and total. KDOT-BLP should receive a copy of this estimate.
 
*See [[Media:Proposal to remove streetlights from Black & McDonald.pdf|'''sample streetlight removal proposal''']] from Black & McDonald.


== Task No. 27 - Prepare Preliminary Cash Flow Projection (update) ==
== Task No. 27 - Schedule Field Check Meeting ==
The Consultant/Project Manager shall prepare a preliminary cash flow projection, including construction costs, and submit it to the City Finance Department on the standard form, see [[media:II-7.xlt|'''Exhibit No. II-7'''.]]
{{Top}}


== Task No. 28 - Begin Field Check Plan Review ==
The Project Manager shall schedule the Field Check meeting. Representatives of all funding sources are to be invited. The City Engineer/City Traffic Engineer or their designated representatives will attend all meetings. Prior to Field Check Meeting, coordinate with Engineering Services for development projects permitted in the area.
The persons [[#Task No. 22 - Distribute Plans for Field Check|(see Task No. 22)]] who receive field check plans shall commence plan review. The review shall be completed prior to the scheduled Field Check meeting.
If applicable, begin [[media:Electrical_Service_Address_Procedures_-_Preliminary_Plans_-_Task_28.pdf|Electrical Service Address Procedures]] for street lighting controllers, traffic signal controllers, electrical control centers for Parks and Recreation irrigation controllers, flood warning or road weather information systems.


See [[media:Exhibit_G_KCP%26L_Electrical_Service_Application.pdf|Exhibit G for KCP&L Commercial & Industrial Electrical Service Application.]]  
:[[Media:II-7e Sign in sheet.docx|'''Exhibit No. II-7e''']] ''is a meeting sign in sheet''.


See [[media:Sample_Letter_to_KCP%26L_Requesting_Power_-_Preliminary_Plans_-_Task_28.pdf|sample letter]] to KCP&L requesting power service.
Field check will be conducted at a pre-determined location. The Consultant or the City will provide a set of plans for field check. BLP will review comments and will discuss any necessary actions with the City and the Consultant.
After the field check meeting the consultant or the City will distribute minutes and provide BLP with a response to the issues identified/discussed in the meeting.


== Task No. 29 - Schedule Field Check Meeting ==
After field check plans have been received by BLP, a Field Check Report will be developed and provided to the City, Consultant and other necessary parties.
The Project Manager shall schedule the Field Check meeting. Representatives of all funding sources are to be invited. The City Engineer/City Traffic Engineer or their designated representatives will attend all meetings.


{{Exhibit|II-9d.dot|No. II-9d|is a meeting sign in sheet.}}
During the site review/field check meeting it should be determined if the proposed project will have a potential impact on rail facilities. If it appears that work will be near or within railroad right-of way, the LPA will coordinate with the railroad to determine the need for flagging, liability insurance, agreements, and a possible diagnostic review.


== Task No. 30 - Execute Official Agreement with KDOT ==
== '''Task No. 28 - Execute Official Agreement with KDOT''' ==
When the official KDOT agreement is received by the Project Manager, it is reviewed/approved by the Law Department and placed on the City Council agenda for consideration.
When the official KDOT agreement is received by the Project Manager, it is reviewed/approved by the Law Department and placed on the City Council agenda for consideration.


{{Exhibit|II-30.pdf|No. II-30|is a sample of KDOT's official 2007 KDOT Utility Accommodation Policy/Agreement.}}
:[https://www.ksdot.org/Assets/wwwksdotorg/bureaus/burConsMain/Connections/UAP2007_2016_aug.pdf.pdf '''Exhibit No. II-28'''] is Official  KDOT Utility Accomodation Policy/Agreement.''
{{Exhibit|II-30a.dot|No. II-30a|is a sample Resolution to be used when KDOT's City/State Agreement is sent to Council for approval. The Resolution number is to be obtained from the City Clerks office.}}
 
Compliance with KDOT's Non-Descrimination policies is required on all contracts. See [http://www.ksdot.org/Assets/wwwksdotorg/bureaus/offChiefCoun/Documents/Title%20VI%20Local%20Governments%20and%20Consultants%20Handbook.pdf'''Title VI Handbook'''] for more information.
 
== '''Task No. 29 - Continue Environmental Process''' ==
 
For more information see Chapter [[Media:4.0 Environmental 2020.pdf|'''4.0 Environmental''']] of KDOT's LPA Project Development Manual.
 
== '''Task No. 30 - Obtain Decision for Design Exception from KDOT''' ==
The Project Manager shall keep in close contact with BLP-KDOT, if a design exception was requested. Once the decision has been made, the results shall be disseminated to all interested and required parties.
== '''Task No. 31 - Complete Public Interest Finding''' ==
{{Top}}
 
If the deviation from a standard practice is requested, the Project Manager shall submit a [https://www.ksdot.org/Assets/wwwksdotorg/bureaus/burLocalProj/Forms/BLP-Proprietary%20Product%20Certification%20Form.pdf '''Proprietary Product Certification Form'''] or a Public Interest Finding (PIF) to BLP explaining the need for the deviation and why it is in the public's best interest to allow it.
 
For detailed information regarding the use of proprietary products see FHWA's [https://www.fhwa.dot.gov/construction/cqit/fr_qa.cfm '''Construction Program Guide'''].
 
== '''Task No. 32 - NHS Approval Procedure''' ==
{{Top}}
 
For projects on principal arterials, the Project Manager shall request special approval to administer a federally funded project on the National Highway System route, documenting the reason for the request and demonstrating that the City has successfully administered a non-NHS project. This request shall be submitted to the BLP for approval.
 
== Task No. 33 - Submit Right-of-Way Plans/Legal Descriptions ==
{{Top}}
 
The Consultant/Project Manager shall submit this information on the date as established with the project schedule. The legal descriptions shall be provided in electronic format along with a written original sealed by a registered land surveyor in the State of Kansas. A tract map for each property shall accompany the legal descriptions. The tract map shall clearly identify each type of proposed taking. Also included with the submittal shall be a copy of all the title company information. At this time  tract files should be created in project folder under '''\2-Preliminary Design\ROW and Easement Documents\Tract Files.'''
 
{{Exhibit|II-33.pdf|No. II-33|is an example of legal descriptions and tract map.}}
{{Exhibit|II-33a.pdf|No. II-33a|ia a Memorandum from the Register of Deeds, Johnson County, regarding legal description requirements for document indexing.}}
{{Exhibit|II-33b.pdf|No. II-33b|is a Sample Template from the Register of Deeds, Johnson County, showing required format (margin & paper size) for recording documents.}}
 
All prepared documents must conform to the Register of Deeds requirements and filed electronically with Johnson County RTA. If rejected, the City is notified by RTA via email.


== Task No. 31 - Obtain Decision for Design Exception from KDOT ==
{{Exhibit|II-33c RTA rejection email.pdf|No. II-33c|is an example of rejection email from JoCo RTA.}}
The Project Manager shall keep in close contact with BLP-KDOT, if a design exception was requested. The results shall be disseminated to all interested and required parties.


== Task No. 32 - Submit R/W Plans/Legal Descriptions ==
(The rejection email is generated automatically and it applies to the whole package of documents submitted. Therefore the entire package is rejected even if only one tract has an error. It is up to the Project Engineer or Engineering Technician to figure out which one.)
The Consultant/Project Manager shall submit this information on the date as established with the project schedule. The legal descriptions shall be provided in electronic format along with a written original sealed by a registered land surveyor in the State of Kansas. A tract map for each property shall accompany the legal descriptions. The tract map shall clearly identify each type of proposed taking. Also included with the submittal shall be a copy of all the title company information.


{{Exhibit|II-32.pdf|No. II-32|is an example of legal descriptions and tract map.}}
{{Note|In some instances Long Term Temporary Construction Easements (TCE) have been granted to the City during the development process. These existing TCEs are usually adjacent to thoroughfares. During the R/W Plan review the project technician is to check for any previously granted Long Term TCEs adjacent to the project. The TCEs can be viewed in ArcMap by adding ''"Easement and ROW"'' Data Layer from ''"Property"'' Data Group. Each easement in this layer is linked to a ''pdf'' image of the document by which that easement was acquired.}}
{{Exhibit|II-32a.pdf|No. II-32a|and}}
{{Exhibit|II-32b.pdf|No. II-32b|is a Memorandum from the Register of Deeds, Johnson County, regarding legal description format.}}
{{Exhibit|II-32c.pdf|No. II-32c|is a Rejection Notice used by the Register of Deeds listing all causes of rejection of filed documents. All prepared documents must conform to the Register of Deeds requirements.}}


{{Note|In some instances Long Term Temporary Construction Easement have been granted to the City during the development process. These existing Temporary Construction Easements are usually adjacent to thoroughfares. During the R/W Plan review the project technician is to check for any previously granted Long Term Temporary Construction Easements adjacent to the project. The easements are stored in K:\Maps\Plats\long term tce pdfs and can be identified by the plat map number.}}
== Task No. 34 - Hire Appraiser ==
{{Top}}


== Task No. 33 - Hire Appraiser ==
Project Manager shall form a Selection Committee and a qualification based selection process shall be used.
The Project Manager shall request RFP's from qualified appraisers. Subsequent to receiving the proposals, the Project Manager shall evaluate the proposals and make recommendations in accordance with City Policy.  If federal funding is involved the Project Manager shall form a Selection Committee and a qualification based selection process shall be used.
Appraiser and Acquisition Agent may be acquired by a stand-alone RFQ process or inclusion as a component of the qualifications based selection process for the Design Professional/Consultant, or as may be required by applicable federal or state laws/regulations.
   
   
{{Exhibit|II-33a.dot|No. II-33a|is a list of City qualified appraisers.}}
{{Exhibit|II-34a 12.2.22.docx|No. II-34a|is a list of City qualified appraisers.}}
{{Exhibit|II-33b.dot|No. II-33b|is a copy of City's Request for Proposal (RFP) letter.}}
{{Exhibit|RFQ Appraisal Acquisition.pdf|No. II-34b|is a copy of City's Request for Qualifications (RFQ).}}
{{Exhibit|II-33c.xlt|No. II-33c|is a  list of the project right-of-way takings.}}
{{Exhibit|Summary of takings.pdf|No. II-34c|is a  sample summary of the project right-of-way and easement takings.}}
{{Exhibit|II-33d.dot|No. II-33d|is a copy of Appraiser Agreement for fee under $10,000.}}
{{Exhibit|II-34d Appraiser Agreement under 10K rev 7-5-22.docx|No. II-34d|is an Appraiser Agreement for fee under $10,000.}}
{{Exhibit|II-33e.dot|No. II-33e|is a copy of Appraiser Agreement for fee over $10,000.}}
{{Exhibit|II-34e Appraiser Agreement over 10K rev 7-5-22.docx|No. II-34e|is an Appraiser Agreement for fee over $10,000.}}
{{Exhibit|II-33f.dot|No. II-33f|is a sample Intra City memorandum to the Selection Committee with proposals from appraisers and ranking sheet.}}
{{Exhibit|II-34f Memo to Selection Committee.pdf|No. II-34f|is a sample Intra City memorandum to the Selection Committee.}}
{{Exhibit|II-33g.dot|No. II-33g|is a sample Intra City memorandum to the Selection Committee with staff recommendations.}}
{{Exhibit|II-34g Proposal for Appraisal.pdf |No. II-34g|is a sample Proposal for Appraisal.}}
{{Exhibit|II-34h Ranking sheet rw proposals.pdf|No. II-34h| is a sample of ranking sheet.}}
 
See [https://www.fhwa.dot.gov/real_estate/local_public_agencies/lpa_guide/index.cfm '''FHWA's Real Estate Acquisition Guide For Local Public Agencies'''] for information that will be necessary when a project is started that requires the acquisition of real estate and receives any Federal funding.
 
{{Exhibit|II-34i appraisal review.dot|No. II-34i|is a copy of Appraisal Review form.}}
 
LPA representatives, appraisers and acquisition contractors involved with the R/W acquisition process must be certified in accordance with the ROWCP requirements. Refer to Chapter [[Media:7.0 Right of Way 2020.pdf|'''7.0 Right of Way''']] of KDOT's LPA Project Development Manual for additional information.
 
== Task No. 35 - Prepare R/W and Easement Documents ==
{{Top}}
 
The Project Manager will coordinate with the Contract Specialist assigned to the project the preparation of the various documents necessary for the takings required to construct the project.
 
The following is the list of the most commonly used documents:
 
:*[[Media:Access-easement-option-1.docx|'''Access Easement Option 1''']]
:*[[Media:Access-easement-option-2.docx|'''Access Easement Option 2''']]
:*[[Media:Deed-of-dedication.doc|'''Deed of Dedication''']]
:*[[Media:Kansas-warranty-deed.docx|'''Kansas Warranty Deed''']]
:*[[Media:Notice-of-termination-of-temporary-construction-easement.docx|'''Notice of Termination of Temporary Construction Easement''']]
:*[[Media:Permanent-drainage-easement-city-grantee.docx|'''Permanent Drainage Easement - City Grantee''']]
:*[[Media:Permanent-drainage-easement-city-grantor.docx|'''Permanent Drainage Easement - City Grantor''']]
:*[[Media:Permanent-drainage-easement-city-grantor-and-grantee.docx|'''Permanent Drainage Easement - City Grantor and Grantee''']]
:*[[Media:Permanent-maint-access-easement.docx|'''Permanent Maintenance Access Easement''']]
:*[[Media:Permanent-right-of-way-easement.docx|'''Permanent Right of Way Easement''']]
:*[[Media:Quit-claim-deed.docx|'''Quit Claim Deed''']]
:*[[Media:Real Estate Mortgage Release - Corporation.docx|'''Real Estate Mortgage Release - Corporation''']] (to be obtained when value of takings exceeds $50K)
:*[[Media:Real Estate Mortgage Release - Individual.docx|'''Real Estate Mortgage Release - Individual''']] (to be obtained when value of takings exceeds $50K)
:*[[Media:Sidewalk-and-traffic-signal-system-easement-2.docx|'''Sidewalk and Traffic Signal System Easement''']]
:*[[Media:Sidewalk-easement.docx|'''Sidewalk Easement''']]
:*[[Media:Sidewalk-variance-ce-std.docx|'''Sidewalk Variance - City Engineer Standard''']]
:*[[Media:Sidewalk-variance-pwc.docx|'''Sidewalk Variance - Public Works Committee''']]
:*[[Media:Sight Triangle Easement .docx|'''Sight Triangle Easement''']]
:*[[Media:Street-light-easement-2.docx|'''Street Light Easement''']]
:*[[Media:Temporary-construction-easement-city-grantee rev 6-9-22.docx|'''Temporary Construction Easement - City Grantee''']]
:*[[Media:Temporary-construction-easement-city-grantor.docx|'''Temporary Construction Easement - City Grantor''']]
:*[[Media:Temporary-Construction-Easement-Grading-Version-1.docx|'''Temporary Construction Easement for Grading - Version 1''']]
:*[[Media:Temporary-Construction-Easement-Grading-Version-2.docx|'''Temporary Construction Easement for Grading - Version 2''']]
:*[[Media:Temporary-Construction-Easement-Long-Term.docx|'''Temporary Construction Easement - Long Term''']]
:*[[Media:Traffic-signal-system-easement-2.docx|'''Traffic Signal System Easement''']]
:*[[Media:Utility-easement-city-grantee.docx|'''Utility Easement - City Grantee''']]
:*[[Media:Utility-easement-city-grantor.docx|'''Utility Easement - City Grantor''']]
:*[[Media:Utility-easement-city-grantor-and-grantee.docx|'''Utility Easement - City Grantor and Grantee''']]
 
The following documents are shown for information only and will be generated by the City of Overland Park:


See FHWA's Real Estate Acquisition Guide For Local Public Agencies for information that will be necessary when a project is started that requires the acquisition of real estate and receives any Federal funding.
:*[[Media:EASEMENT ACQUISITION AGREEMENT-final 11-12-15.docx|'''Easement Acquisition Agreement''']]
:*[[Media:EASEMENT ACQUISITION AGREEMENT-partial mortgage final 11-12-15.docx|'''Acquisition Agreement with Partial Mortgage Release''']]
:*[[Media:Amendment to EASEMENT ACQUISITION AGREEMENT.docx|'''Amendment to Easement Acquisition Agreement''']]
:*[[Media:Administrative Settlement Form.docx|'''Administrative Settlement Form''']]
:*[[Media:Restoration Agreement template 01.14.2020.docx|'''Restoration Agreement''']] and [[Media:Restoration Agreement-Exhibit A template.docx|'''Exhibit A''']]
All prepared right-of-way and easement documents must conform to the Register of Deeds requirements. See [[#Task No. 33 - Submit Right-of-Way Plans/Legal Descriptions|'''Phase II, Task No. 33''']] for exhibits.


{{Exhibit|II-33h.dot|No. II-33h|is a copy of Appraisal Review form.}}
== Task No. 36 - Schedule Second Public Information Meeting ==
{{Top}}


== Task No. 34 - Prepare R/W and Easement Documents ==
The purpose of this meeting is to present the Right of Way plans to the citizens. For KDOT projects the Notice of Public Information Meeting must be published in the [http://www.kssos.org/pubs/pubs_kansas_register.asp '''Kansas Register'''] and [http://www.thelegalrecord.net '''The Legal Record'''].
The Project Manager will coordinate the preparation of the various documents necessary for the takings required to construct the project.


{{Exhibit|II-34a.dot|No. II-34a| - Access Easement - Option 1}}
See [[#Task No. 15 - Schedule First Public Information Meeting|'''Phase II, Task No. 15''']] for list of invites.
{{Exhibit|II-34b.dot|No. II-34b| - Access Easement - Option 2}}
{{Exhibit|II-34c.dot|No. II-34c| - Permanent Maintenance Access Easement}}
{{Exhibit|II-34d.dot|No. II-34d| - Construction Easement}}
{{Exhibit|II-34e.dot|No. II-34e| - Deed of Dedication}}
{{Exhibit|II-34f.dot|No. II-34f| - Kansas Warranty Deed}}
{{Exhibit|II-34g.dot|No. II-34g| - Quit Claim Deed}}
{{Exhibit|II-34h.dot|No. II-34h| - Real Estate Mortgage Release - Individual}}
{{Exhibit|II-34i.dot|No. II-34i| - Real Estate Mortgage Release - Corporation}}
{{Exhibit|II-34j.dot|No. II-34j| - Permanent Drainage Easement - City Grantor}}
{{Exhibit|II-34k.dot|No. II-34k| - Permanent Drainage Easement - City Grantee}}
{{Exhibit|II-34l.dot|No. II-34l| - Permanent Drainage Easement - City Grantor & City Grantee}}
{{Exhibit|II-34m.dot|No. II-34m| - Permanent Right of Way Easement}}
{{Exhibit|II-34n.dot|No. II-34n| - Retaining Wall Easement}}
{{Exhibit|II-34o.dot|No. II-34o| - Sidewalk Easement}}
{{Exhibit|II-34p.dot|No. II-34p| - Sidewalk Variance}}
{{Exhibit|II-34q.dot|No. II-34q| - Temporary Construction Easement - City Grantor}}
{{Exhibit|II-34r.dot|No. II-34r| - Temporary Construction Easement - City Grantee}}
{{Exhibit|II-34s.dot|No. II-34s| - Temporary Construction Easement - Grading Version 1}}
{{Exhibit|II-34t.dot|No. II-34t| - Temporary Construction Easement - Grading Version 2}}
{{Exhibit|II-34u.dot|No. II-34u| - Notice of Termination of Temporary Construction Easement}}
{{Exhibit|II-34v.dot|No. II-34v| - Traffic Signal Easement}}
{{Exhibit|II-34vv.dot|No. II-34vv| - Street Light Easement}}
{{Exhibit|II-34w.dot|No. II-34w| - Utility Easement - City Grantor}}
{{Exhibit|II-34x.dot|No. II-34x| - Utility Easement - City Grantee}}
{{Exhibit|II-34y.dot|No. II-34y| - Utility Easement - City Grantor & City Grantee}}
{{Exhibit|II-34z.dot|No. II-34z| - Right of Way Purchase Contract - Johnson County Public Works}}
{{Exhibit|II-34zz.dot|No. II-34zz| - Easement Acquisition Agreement - City of Overland Park}}
{{Exhibit|II-32a.pdf|No. II-32a|and}} 
{{Exhibit|II-32b.pdf|No. II-32b|is a Memorandum from the Register of Deeds, Johnson County, regarding legal description format.}}


{{Exhibit|II-32c.pdf|No. II-32c|is a Rejection Notice used by the Register of Deeds listing all causes of rejection of filed documents. All prepared documents must conform to the Register of Deeds requirements.}}
{{Exhibit|II-36.docx|No. II-36|is an example Invitation Letter to property owners.}}
{{Exhibit|II-36a public meeting notice.pdf|No. II-36a|is an example Notice of Public Information Meeting.}}
{{Exhibit|Public Meeting Sign-In Sheet .docx|No. II-36b|is a public meeting sign in sheet.}}
{{Exhibit|Public Meeting Handout.pdf|No. II-36c|is a public meeting handout.}}


== Task No. 35 - Schedule Second Public Information Meeting ==
{{Note|This and all subsequent Public Information Meeting notices should ask if participants need a language interpreter or a hearing assistance device and a phone number. All meeting rooms shall be ADA accessible. The KDOT '''Equal Opportunity and Civil Rights Information''' brochure in [[Media:Title VI Brochure English.pdf|'''English''']] and [[Media:Title VI Brochure Spanish.pdf|'''Spanish''']] regarding equal opportunity contracting are to be made available at all public meetings.}}
The purpose of this meeting is to present the preliminary plans to the citizens. For KDOT projects the Notice of Public Information Meeting must be published in the Kansas Register and Overland Park Sun. See Phase II, Task No. 17 for list of invites.


{{Exhibit|II-35.dot|No. II-35|is an example Invitation Letter to property owners.}}
For those who wish to use a Blue Valley School District facility for the public meeting, an on-line [https://district.bluevalleyk12.org/Community/Pages/FacilityRental.aspx '''Facility Rental Reservation Request'''] is available. Once the request is submitted, the BVSD Facility Scheduling Office will send a confirmation if the requested space is available.
{{Exhibit|II-35a.dot|No. II-35a|is an example Notice of Public Information Meeting.}}
{{Exhibit|II-35b.dot|No. II-35b|is a public meeting sign in sheet.}}
{{Exhibit|II-35c.dot|No. II-35c|is a public meeting handout.}}


{{Note|This and all subsequent Public Information Meeting notices should ask if participants need a language interpreter or a hearing assistance device and a phone number. All meeting rooms shall be ADA accessible.}}
== [[:Category:Phase II Exhibits|All Phase II Exhibits]] ==

Latest revision as of 14:42, 19 March 2024

Home I-Vision II-Preliminary Design III-Final Design IV-Pre-Construction V-Construction VI-Retrospect

Introduction

Phase II begins the engineering design and plan preparation process for a project. The date for beginning this process will depend upon the approved project schedule, budget and time anticipated to complete the various phases/tasks.

The project team will play an important decision-making role in managing a project. This team will consist of City staff and private consultants (if applicable).

Intra-department, public involvement, and utility company meetings are commenced during this phase.

Field check plans are prepared, distributed and reviewed along with preliminary construction cost estimates. Also, R/W and easement documents are completed and, if required, appraisers are hired.

Phase II Checklist

Task No. 1 - Identify Project Team

Top

When a project is scheduled to begin the design phase, the Project Team is to be identified by the City Engineer and/or the City Traffic Engineer, depending on the scope of the project. The purpose of this team is to provide input, information, support, and execution throughout the project planning, design, and construction. The Project Team will generally include the following members: Project Manager, Traffic Engineer, Construction Inspector, Traffic Maintenance Technician, Maintenance Representative, Engineering Technician, Contract Specialist, Law Department Representative, and Finance Representative.

Task No. 2 - Decide if City Staff to Design

Top

The City Engineer and/or the City Traffic Engineer in consultation with the Project Team will decide whether the project will be designed by the City Staff or by a Consulting Engineer.

Task No. 3 - Consultant Selection/Certification

Top

The City shall select and negotiate with a consultant for project design in accordance with the City Resolution No. 4550 if the design is funded solely with local funds. If federal or state funds are used for the design, the City will use an approved list of consultants furnished by the BLP and will follow the current BLP Consultant Selection Procedures. If the City intends to use federal funds in the construction engineering, and use the same consultant for both preliminary engineering (PE) and construction engineering (CE), following the current BLP Consultant Selection Procedure for the PE will satisfy the requirements for the CE selection.

Prior to the beginning of the selection process, Project Manager shall notify via email DPW and CE of upcoming RFQ for consulting services. The project name, list of firms to receive the RFQ and any other pertinent information will be provided.

For more information see Chapter 3.0 Preliminary Engineering (PE) Consultant Selection and Agreement and Chapter 11.0 Construction Engineering (CE) Consultant Selection and Agreement of KDOT's LPA Project Development Manual.

When federal funds are used in the preliminary engineering, the City will provide KDOT a certification that appropriate steps have been completed and the process complied with all applicable regulations. Any work done prior to obligation of federal funds will be non-participating.

GeekNotesIcon.png Note: This Manual will be provided to the Consultant during the negotiating process. When negotiating an agreement with a consulting firm a narrative of services and a fee schedule is required (examples below).
Exhibit No. II-3a City’s standard Engineering / Architectural services agreement for design projects.
Exhibit No. II-3b(1) City’s standard Supplemental Agreement for Professional Engineering Services. (First)
Exhibit No. II-3b(2) City’s standard Supplemental Agreement for Professional Engineering Services. (Second and beyond)
Exhibit No. II-3c City’s standard Consultant Agreement for non-design projects.
Exhibit No. II-3d City’s standard Supplemental Agreement to the Consultant Agreement for non-design projects.
Exhibit No. II-3e is a sample of City’s standard Scope of Services.
(When writing contracts for projects involving bridge construction, refer to Chapter 6.0 Bridge Design of KDOT's LPA Project Development Manual).
Exhibit No. II-3e(1) City’s standard Scope of Services for a Street Lighting project.
Exhibit No. II-3e(2) City’s standard Scope of Services for a Traffic Signal project.
Exhibit No. II-3f City’s standard fee schedule for engineering services agreement.
Exhibit No. II-3g is a sample RFQ packet for consulting services.
Exhibit No. II-3h is a sample Ranking Memo to Consultant Selection Committee.
Exhibit No. II-3i is a sample Ranking Sheet to be completed by the Consultant Selection Committee.
Exhibit No. II-3j is a sample Interview Memo to Consultant Selection Committee.
Exhibit No. II-3k is a sample of a compiled Ranking Sheet.
Exhibit No. II-3l is a sample letter requesting interview of short list Consulting Firms.

The selection committee shall meet after ranking sheets are completed and any interviews have been held. This meeting is to ensure consensus of the selection committee prior to letters being sent to consultants.

Exhibit No. II-3m is a sample letter to selected Consulting Firm.
Exhibit No. II-3n is a sample letter to Consulting Firms not selected.
Exhibit No. II-3o is a list of Consulting Firms.

Task No. 4 - Submit Project Description to Law Department. Execute Ordinances-Resolution.

Top

The physical location of the project and a description of what is to be constructed is to be submitted to the Law Department. A feasibility report shall include the physical location of the project, a description of what is to be constructed, a cost estimate, and other necessary information required by the Law Department. The description project centerline shall include the permanent improvements (not tapers for street projects).

An example of a project description is as follows:

The construction of Switzer Road from north of the centerline of 159th Street to south of the centerline of 151st Street. Construction will include a dual roadway with a median. Left turn lanes will be located at side streets as required. Concrete sidewalks will be located on the west side of Switzer Road. An asphalt bike and pedestrian trail will be located on the east side of Switzer Road. The project also includes construction of storm sewers, street lights, restoration, and other items incidental to the street construction.

The Project Manager, in conjunction with the Law Department, will determine if all necessary City ordinances or resolutions have been executed in order to authorize the project. Examples of possible documents are:

Exhibit No. II-4a Resolution on advisability of the creation of an Improvement District,
Exhibit No. II-4b Resolution authorizing and providing for the creation of an Improvement District,
Exhibit No. II-4c Ordinance providing for the public improvement of a Main Trafficway.

Task No. 5 - Prepare Project Schedule

Top

If a Consultant is to be hired, the anticipated construction time period shall be provided. The Consultant shall submit a schedule, indicating the design phases, R/W / easement submittal, meetings, bid opening date and construction time period. If the City Staff is designing the project, a similar schedule shall be prepared by the City Project Manager.

Task No. 6 - Submit Cash Flow Projections (Engineering Cost)

Top

When requested, a cash flow projection for engineering services shall be submitted to the City Finance Department.

Exhibit II-6 is the standard cash flow form.

Task No. 7 - Initiate Utility Coordination. Schedule Utility Meeting (optional)

Top

Early in the preliminary design phase, the Project Manager will contact all public and private utility officials, informing them of the upcoming project (project limits and schedule) and requesting the information on their facilities (location maps, existing utility easements and any other pertinent information) in the vicinity.

Exhibit No. II-7 is a sample email (initial contact) to the utilities.
(Project Location Map and Utility Response Forms should be attached to the email).

If the Project Manager chooses to hold a meeting, an agenda should be prepared and distributed in advance of the meeting to all scheduled attendees.

The typical agenda items are as follows:

  • utility location maps/information;
  • existing utility easements;
  • project schedule;
  • possible critical out-of-service time periods;
  • utility representatives contact information.

Meeting minutes shall also be prepared following the meeting and distributed to all scheduled attendees, including those who were invited but did not attend.

GeekNotesIcon.png Note: When scheduling utility meeting in Google calendar, in order to avoid conflicts with other utility meetings, CH-PW Utilities (found under Rooms tab) shall be "invited" as an attendee to all meetings, pre-bid conferences and pre-construction conferences or any meetings that require utility company attendance.
Exhibit No. II-7a is a list of utility companies.
Exhibit No. II-7b is a sample request for utility plans and easement documents.
Exhibit No. II-7c is a sample invitation letter for Utility Coordination Meeting.
Exhibit No. II-7d sample agenda for Utility Coordination Meeting.
Exhibit No. II-7e meeting sign in sheet.
Exhibit No. II-7f sample of utility coordination meeting minutes.

Johnson County Wastewater

Exhibit No. II-7g Right-Of-Way Agreement
Exhibit No. II-7h Right-Of-Way Agreement, Reference Sheet
Exhibit No. II-7i Right-Of-Way Agreement, Project Checklist
Exhibit No. II-7j Payment invoice to JCW for reimbursement of relocation costs.

Water District No.1 of Johnson County

Exhibit No. II-7k Right-Of -Way Agreement

Transmission Pipe Line

Exhibit No. II-7l is a sample of Encroachment Guidelines.

Evergy

Exhibit No. II-7m Governmental Relocation Contact List
Exhibit No. II-7n Service Territory Map

For Verizon inquiries see Memorandum Request for OSP facility records.

Refer to the City's Utility Relocation Guidelines for all relocation planning.

Refer to Manual of Infrastructure Standards for excavation and safety requirements.

For federally funded projects refer to Chapter 8.0 Status of Utilities of KDOT's LPA Project Development Manual for additional information.

Task No. 8 - Pre-Design Meeting

Top

A pre-design meeting shall be scheduled prior to commencing any significant design work. A meeting agenda shall be prepared and distributed in advance of the meeting to the scheduled attendees. Meeting minutes shall be prepared and distributed to all attendees. The purpose of this meeting is to discuss varies anticipated design issues:

  • specific limits of improvements;
  • median openings and left/right turn storage lengths;
  • utility conflicts;
GeekNotesIcon.png Note: All utilities within construction limits will be shown on the 1304 Form.
Land Disturbance Permit;
KDHE Stormwater NOI;
Corps of Engineers 404 Permit;
Kansas DWR;
Floodplain Development Permit;
  • detours/street closings;
  • project phasing/traffic control;
  • identify equipment or material on critical path (see note below);
  • distribute City's Standard Bid Items to be used during design;
  • coordinate with Engineering Services for development projects permitted in the area.
GeekNotesIcon.png Note: It may be necessary to purchase equipment or material in advance of actual project letting date. Generally this will involve separate purchasing contracts for signal poles, LED's, signal cabinets, controllers and load switches. Items on the critical path that could delay the project completion date should be identified and the need for separate purchasing contracts discussed. The BLP project manager should also be included in discussions to make sure federal/state requirements are met for the pre-purchased items.

Task No. 9 - Design Criteria

Top

Project design shall be in accordance with accepted engineering practices and all applicable state, AASHTO and federal Criteria. These criteria include, but not limited to the following references:
  • Public and Private Streets
Current edition of AASHTO's A Policy on Geometric Design of Highways and Streets 2018, 7th Edition (Green Book). (See K:\Library\References\AASHTO)
Current edition of KDOT's Standard Specifications for State Road and Bridge Construction.
Current edition of KDOT's LPA Project Development Manual.
Current City of Overland Park Municipal Code.
Chapter 13.10 Public Street, Streetlighting and Sidewalk Requirements
Chapter 13.12 Construction on Rights-of-Way.
Chapter 15.10 Stormwater Management Program - Standards and Permitting
Current City of Overland Park Design and Construction Standards Volume 1 Design Criteria and Volume 2 Construction Specifications
  • Stormwater Conveyance and Treatment Facilities
Current City of Overland Park Design and Construction Standards Volume 1 Design Criteria and Volume 2 Construction Specifications as a supplement to APWA Section 5600.
  • Erosion and Sediment Control
Current City of Overland Park Design and Construction Standards Volume 1 Design Criteria and Volume 2 Construction Specifications as a supplement to APWA Section 5100.
  • Traffic Signals
Traffic signals shall be designed in accordance with the latest edition of the Manual on Uniform Traffic Control Devices. Traffic signal mast arm poles shall be designed in accordance with the 2013 AASHTO Standard Specifications for Structural Supports for Highway Signs, Luminaires and Traffic Signals, Sixth Edition, LTS-6.
  • Permanent Traffic Control Signs
Permanent traffic control signs shall be designed in accordance with the latest edition of the Manual on Uniform Traffic Control Devices and the City's Traffic Sign Design Manual.
  • Pavement Markings
Pavement markings shall be designed in accordance with the latest edition of the Manual on Uniform Traffic Control Devices and the City's Pavement Marking Design Manual.
  • Streetlights
Streetlights shall be designed in accordance with Resolution No. 4036 and the City's Streetlighting Design Manual.
Current City of Overland Park Design and Construction Standards Volume 1 Design Criteria. Refer to Part F for the design criteria for all streetlighting projects.
  • Traffic Control
Work Zone Traffic Control shall be designed in accordance with the City’s Traffic Control Handbook.
  • Bridges
City of Overland Park Bridge Design Information
Exhibit No. II-9a is a list of bridge design information.
Exhibit No. II-9b is Public Works Department Bridge Asset Inventory Procedure (February 2018).
Also see
Chapter 6.0 Bridge Design of KDOT's LPA Project Development Manual
LRFD Bridge Design Manual, Volume III, KDOT, current edition. (See K:\Library\References\KDOT Design Manual\KDOT Bridge Design Manual December 2021.pdf)
LRFD Bridge Design Specifications, AASHTO, current edition
  • Johnson County Wastewater
Exhibit No. II-9c Designers Checklist for City Streets and Stormwater Improvements.
Exhibit No. II-9d Memo from JCW on existing brick manholes with new cone sections.
For city street or stormwater improvement projects that require sanitary sewer relocation or extension, full sanitary sewer design plans per JCW plan requirements and specifications must be approved by JCW. See below for requirements.
Procedures for Privately Financed Gravity Sewer Main Projects
Minimum Plan Requirements for Gravity Sewer Main Projects
Construction and Material Specifications for Sanitary Sewers
Sanitary Sewer Standard Details.
For the status of sanitary sewer plan submittals and projects see Johnson County Wastewater Commercial Permitting page.
Also see Phase II, Task No. 7 for Right-Of-Way agreement between JCW and City of Overland Park.
  • Current Johnson County Stormwater Management Program Policy and Procedures
See Phase I, Task No. 3
  • Additional Design Guidance for Reference:
"Roadside Design Guide", AASHTO, current edition;
"Highway Capacity Manual"(HCM), current edition;
"Guide for the Development of Bicycle Facilities", AASHTO, current edition. (See K:\Projects\Manual\AASHTO Guide for the Development of Bicycle Facilities 2012.pdf).
American with Disabilities Act (ADA) Guidelines and Standards, United States Access Board;
Proposed Guidelines for Pedestrian Facilities in the Public Right-of-Way (PROWAG), United States Access Board;
"Urban Street Design Guide" NACTO, current edition;
"Urban Bikeway Design Guide" NACTO, current edition;
"Kansas Roundabout Guide" KDOT, current edition;
Greenway Linkages Plan for Overland Park;
South Overland Park Transportation Plan;
Overland Park Bicycle Master Plan;
FHA Roundabouts Informational Guide.
  • Design Exceptions:
If, during the development of plans for proposed project, it is determined that there are circumstances that may make it impractical to meet the applicable guidelines, the Consultant/Project Manager shall fill out the following forms:
Use Design Exceptions form to document all design exceptions and save it to the project preliminary design folder.
Use Design Deviations form to document design deviations, revisions to the standard design that do not adversely impact the design intent, and save to the project preliminary design folder.
See Phase II, Task No. 18 for design exceptions on federally funded projects.

Task No. 10 - Standard Details

Top

The City's Public Works Department maintains and updates Standard Details for publicly funded projects under the direction of the City Engineer. If Johnson County Wastewater facilities are involved in the project, Sanitary Sewer Standard Details shall be incorporated into the plans.

Also, the following are typical thoroughfare sections to be used for the infrastructure improvements as recommended by South Overland Park Transportation Plan:

Ultimate 4- and 3-Lane Thoroughfare Sections;

Ultimate 2-Lane Thoroughfare Sections;

Interim Thoroughfare Sections.

Task No. 11 - SMAC Preliminary Study

Top

For SMAC funded projects a preliminary study should be prepared and delivered to Johnson County SMAC officials prior to beginning any design work.

See Phase I, Task No. 3 for details and checklist for preparing this study.

Task No. 12 - Other Agency Agreements (if Applicable)

Top

Local government agency agreements should be executed under Phase I, Task No. 11. If these agreements were not executed prior to beginning of design, execution shall be completed at this time in the preliminary design phase.

Task No. 13 - Conduct Field Surveys

Top

Sufficient and required data necessary for design purposes shall be collected. The field survey shall be in accordance with state statutes, and current accepted and required surveying practices. Prior to the beginning of land survey or utility relocation work the letter to the residences adjacent to the project will be mailed out informing property owners of upcoming activities. Included with the letter is flood questionnaire to be used for storm drainage improvements consideration.

Exhibit No. II-13a is a sample pre-survey letter to residents.
Exhibit No. II-13b is a flood questionnaire.

See City standard Scope of Services in Phase II, Task 3 for survey control requirements.

GeekNotesIcon.png Note: Any Johnson County Vertical Control Network Bench Marks that will be disturbed as part of the project must be reset. The standard specification and a bid item for this work must be included in the contract documents. These benchmark locations can be found on Johnson County AIMS Mapping web page under the Utilities layer.

Task No. 14 - Continue Environmental Process

Top

Once authorization for the project is completed, KDOT will complete an initial review of the project location and scope to determine the degree of analyses that is required in order to comply with State and Federal environmental laws and regulations.

The BLP will receive from the City the Form 1307, along with all applicable permits attached, prior to obligation of funds, to comply with the NEPA process. (See Phase III, Task No. 14). If detailed environmental analyses are required, the investigation will be initiated at this time. Final and complete analyses and application for permits by the City may be completed after Field Check and detailed design information is available. All investigation and permit acquisitions will be conducted in accordance with the referenced manual and BLP Policy Memos.

KDOT will control the environmental process task for projects with categorical exclusion. The complexity and effort will depend on each project. The exception would be if an Environmental Assessment or an Environmental Impact Statement is required. In this case, the City or Consultant would perform this task with KDOT and FHWA approval.

GeekNotesIcon.png Note: For KDOT Projects this task is tracked by KDOT. The Project Engineer shall ensure this task is complete.

For more information see Chapter 4.0 Environmental of KDOT's LPA Project Development Manual.

Task No. 15 - Schedule First Public Information Meeting

Top

The first public information meeting is scheduled by the Consultant/Project Manager. This meeting shall occur during preliminary design and after field surveys. The purpose of this meeting is to present the concept plan, project schedule, hear citizen's concerns, answer questions, discuss design issues and introduce the involved City Officials and Consultant employees. For KDOT projects the Notice of Public Information Meeting must be published in the Kansas Register and The Legal Record.

Public information invites shall be sent to the following interested parties:

  • Subdivisions adjacent to the project
  • Home Owners Associations adjacent to the project. Contact the City Manager's office for a current list of HOA contacts.
  • Group Chairperson for Neighborhood Conservation Groups adjacent to the project.
For the phone number of the group chairperson, contact the Neighborhood Planner at 913/895-6270.
  • Council Members of Ward(s) adjacent to the project
  • City Manager
  • City Communications Manager and Communications Assistant
  • Funding Sources (KDOT, CARS, SMAC, etc.)
  • Other City (Olathe, Leawood, etc.)
  • Public Works Management (PWMG)
  • Supervisory Engineer
  • Construction Inspector
  • Consulting Firm
  • Facilities Management (if meeting is being held at a City facility)
  • If deemed necessary, Project Manager can invite police personnel.


The Property Owner Conversation Log should be used throughout the project to document all conversations with property owners.


GeekNotesIcon.png Note: This and all subsequent Public Information Meeting notices should ask if participants need a language interpreter or a hearing assistance device and a phone number. All meeting rooms shall be ADA accessible. The KDOT Equal Opportunity and Civil Rights Information brochure in English and Spanish is to be made available at all public meetings.
Exhibit No. II-15 is an example Invitation Letter to property owners.
Exhibit No. II-15a is an example Notice of Public Information Meeting.
Exhibit No. II-15b is a public meeting sign in sheet.
Exhibit No. II-15c is an example Public Meeting Citizen Comment Form.
Exhibit No. II-15d is an example Public Meeting Handout.


For those who wish to use a Blue Valley School District facility for the public meeting, an on-line Facility Rental Reservation Request is available. Once the request is submitted, the BVSD Facility Scheduling Office will send a confirmation if the requested space is available.

Task No. 16 - Begin Title Report Process

Top

The Consultant and/or the Project Manager shall prepare an RFP and forward to a minimum of three land title firms. The RFP should include a map or plan indicating the location of the project and the number of tracts of land involved. Proposals will be forwarded to the Project Manager whereby a firm will be selected and an agreement executed. The RFP should request the following information:

  • legal description of the property and copy of recorded deed(s),
  • mailing address of the property owner,
  • all lien holders of record and recorded mortgage(s),
  • all easements of record and copy of recorded document(s),
  • dedicated R/W and copy of recorded document(s), and
  • records of previous condemnations (available in the office of the District Court of Johnson County Kansas, Olathe, Kansas).

In addition, the RFP should provide instructions on methods of delivery of the title report acceptable to the City. Finally the RFP will establish a date for completing the title certification and report.

Exhibit No. II-16a is a list of land title companies to be considered in RFP requests.
Exhibit No. II-16b is a sample land title RFP letter.
Exhibit No. II-16c is a sample location map with parcel numbers.
Exhibit No. II-16d is a sample letter to selected land title company.
Exhibit No. II-16e is a sample letter to land title companies not selected.

Task No. 17 - Begin Geotechnical Report Process

Top

The Consultant/Project Engineer shall determine what appropriate geotechnical information and data is necessary to adequately design the project. Drilled shaft foundations for bridges require specialized inspection. If drilled shaft foundations are anticipated and the Consultant cannot perform this work, the service of a subconsultant may be utilized after receiving written approval from the City. For projects designed by City Staff an RFP shall be prepared and forwarded to qualified firms.

Refer to Phase II, Task No. 3 for information on consultant selection process.

Exhibit No. IV-2a is a list of materials testing / geotechnical service companies.

For projects involving bridge construction, refer to Geotechnical Bridge Foundation Investigation Practice, found in Chapter 6.0 Bridge Design of KDOT's LPA Project Development Manual.

Task No. 18 - Submit Request for Design Exception to KDOT

Top

If, during the development of plans for proposed federally funded projects, it is determined that there are circumstances that may make it impractical to meet the applicable guidelines, the Consultant/Project Manager shall submit in writing to the Bureau of Local Projects (KDOT) any request for project design exceptions, using a summary format like the form in Figure 5.1 of the LPA Project Development Manual. A request for a design exception may be made at any time in the design process when sufficient information is available to adequately evaluate the situation.

All design exceptions are subject to approval by the Bureau Chief of BLP. The request may involve one or more of the following controlling criteria: design speed, lane and shoulder width, bridge width, structural capacity, horizontal and vertical alignment, grades, stopping sight distance, cross slopes, superelevation, horizontal and vertical clearances. Justification for the request shall be included along with cost estimates for reasonable alternates. Supporting documents should be consistent with Section 2.3.4 of the KDOT Design Manual, Volume I, Bureau of Road Design.

(See KDOT Road Design Manual 2014.pdf in K:\Library\References\KDOT Design Manual).

For design exceptions documentation, use Overland Park Design Exceptions form to be submitted in addition to the KDOT form.

For projects with other funding sources all requests for design exceptions shall be directed to the City Engineer.

Document all design exceptions regardless of funding on Design Exceptions form and save to the project preliminary design folder.

For more information see section 5.2.2.2 (Design Exception/Allowance) in Chapter 5.0 Plan Development of KDOT's LPA Project Development Manual.

For additional information regarding design exceptions on non-KDOT projects refer to Phase II, Task No. 9 .

Task No. 19 - Prepare Field Check Plans

Top

Plans should be approximately 50 percent complete for field check review including any proposed easement and R/W takings along with a preliminary construction cost estimate and updated project schedule/checklist. The plans shall be stamped "Preliminary—Field Check".

Exhibit No. I-13b is RUPIS project schedule.

See BLP Memo 03-12 Engineer's Professional Seal and Signature on Plans.

For Field Check Plans preparation and submittal requirements on federally funded projects refer to Chapter 5.0 Plan Development of KDOT's LPA Project Development Manual.

Task No. 20 - Distribute Plans to Utility Companies. Schedule Utility Meeting.

Top

The Consultant/Project Manager will distribute field check plans to all utility company representatives and schedule the utility meeting. An agenda should accompany the meeting invite. Meeting minutes will be prepared following the meeting and distributed to all scheduled attendees.

GeekNotesIcon.png Note: When scheduling utility meeting in Google calendar, in order to avoid conflicts with other utility meetings, CH-PW Utilities (found under Rooms tab) shall be "invited" as an attendee to all meetings, pre-bid conferences and pre-construction conferences or any meetings that require utility company attendance.

The purpose of the utility meeting is as follows:

  • check accuracy of utility locations on plans,
  • establish what utilities need to be relocated,
  • See Evergy DWG 130.1-12 for clearance requirements from signal or streetlight poles to utility lines. Verify all poles have proper clearance.
  • establish timetable for accomplishing the relocations, and
  • re-confirm utility representative contacts.

See Phase II, Task No. 7 for exhibits.

Task No. 21 - Update Preliminary Cost Estimate

Top

The Consultant/Project Manager shall prepare and submit an updated preliminary construction cost estimate. The form for this estimate shall resemble the Bid form with the item description, unit, approximate quantity, unit price and total. KDOT-BLP should receive a copy of this estimate.

All cost estimates shall utilize the City's Standard Bid Items and correspond to the measurement and payment as shown in the City of Overland Park Standard Specifications.

Task No. 22 - Update Preliminary Cash Flow Projection

Top

The Consultant/Project Manager shall prepare a preliminary cash flow projection, including construction costs, and submit it to the City Finance Department on the standard form.

See Exhibit II-6.

Task No. 23 - Distribute Plans for Field Check

Top

The Consultant/Project Engineer shall distribute field check plans along with a copy of the project cost estimate and updated RUPIS project schedule electronically via Bluebeam session to the following:

For KDOT projects the electronic field check plans shall be provided to the BLP for transmittal to the Environmental Services Section(KDOT), who will transmit plans to appropriate regulatory and resource agencies. Invitations to the regulatory and resource agencies to participate in the field check should be rendered if environmental mitigation is required. The Consultant/Project Engineer shall provide a project cost estimate to the BLP with the plans.

For the instructions on submitting E-Plans to BLP see the following:

User Guide for Electronic Plans Review; Specifications for Electronic Plans Submittal; FTP Instructions.


GeekNotesIcon.png Note: For KDOT Projects this task is tracked by KDOT. The Project Engineer shall ensure this task is complete.

Task No. 24 - Submit Required Permit Applications

Top

The Consultant/Project Manager shall determine what permits will be required in order to construct the project. The following is a list of possible permits required:

  • City of Overland Park Floodplain Development Permit - necessary for any work in a FEMA floodplain, including areas that will be FEMA floodplain once Johnson County Watershed studies are adopted.
Exhibit No. II-24a is a memo of the steps to be taken on Public Works projects.
Exhibit No. II-24b is an application and submittal checklist for Floodplain Development Permit.
Exhibit No. II-24c is FEMA's Procedures for "No Rise" Certifications.
  • When a project disturbs more than 1 (one) acre, a Notice of Intent (NOI) permit from Kansas Department of Health and Environment (KDHE) and a Land Disturbance Permit (LDP) from the City of Overland Park are required.
The NOI permit is submitted during final design phase of the project. The permit submittal requires clearance letters for the project site from the following agencies:
Kansas Department of Wildlife, Parks and Tourism for threatened or endangered species habitat. Contact KDWPT by emailing the environmental review request (see example) to [email protected].
Kansas Historical Society for historical and archaeological sites. The information for the project should be submitted to the KSHS via the Kansas Review & Compliance (KSR&C) system. Go to http://review.kshs.org to create an account or log in to an existing account.
Refer to Phase III, Task No.9 for the NOI application.
The LDP is obtained prior to commencing construction activities. Refer to Phase V, Task No.8 for the LDP application.
  • Permit to Construct-Obstruction in streams from Kansas Department of Agriculture Division of Water Resources is necessary for any work on a stream with more than 240 acres tributary drainage (some exceptions).
Exhibit No. II-24d is DWR application for permit for Obstruction in Streams.
  • State of Kansas - Environmental Coordination Act (ECA) - approval letters from various state agencies are typically required for Stream Obstructions permits and sometimes others. Contacting these agencies directly for their approval letter can accelerate permitting.
Exhibit No. II-24e is a listing of contact information and addresses for the ECA agencies (current Oct 2015, see KSDA website above for updated lists).
  • Plugging Packet is a handout detailing KDHE's requirements for plugging abandoned water wells.
Exhibit No. II-24f is a sample letter requesting a project be reviewed for nationwide permit coverage. (Visit COE website for latest forms and instructions if an individual permit is needed).
  • FEMA Conditional and Final Letters of Map Revision - required for certain type of major work in the floodplain, as coordinated with the floodplain administrator (see City of OP Floodplain Development Permit, above). The latest permit forms and guidance can be obtained from FEMA's website.
  • KDOT Highway Permits - necessary for construction or utility relocation within KDOT Right of Way:
Highway Permit Use of Right of Way - KDOT Form 304
Cased Utility Line Waiver - KDOT Form 308
Highway Permit for Highway Access - KDOT Form 309
Highway Permit Attachments to Bridges and Other Structures - KDOT Form 310
Access Application Information Sheet - KDOT Form 334
See Preparation of Application for Highway Permit Agreements for instructions on preparation of KDOT Forms 304, 308, 309 and 334.

See 2007 KDOT Utility Accommodation Policy for additional information.

All project related state and/or federal permits must be submitted and Form 1307 completed prior to submittal of final check plans. (See BLP Memo 10-08). This shall be completed at least four months prior to project letting.

Task No. 25 - Begin Field Check Plan Review

The persons who receive field check plans (see Task No. 23) shall commence plan review. The review shall be completed prior to the scheduled Field Check meeting.

GeekNotesIcon.png Note: Any Johnson County Vertical Control Network Bench Marks that will be disturbed as part of the project must be reset. The standard specification and a bid item for this work must be included in the contract documents. These benchmark locations can be found on Johnson County AIMS Mapping web page under the Utilities layer.

Task No. 26 - Coordinate Electrical Service for Traffic Signals, Street Lighting and other City Facilities

If applicable, begin Electrical Service Address Procedures for streetlighting controllers, traffic signal controllers, electrical control centers for park irrigation controllers, flood warning or road weather information systems.

It is important that you specify the electrical service rate in the "Comments" section to insure the City of Overland Park will be billed the correct rate. The correct rate is listed in each of the applicable Service Applications.

The Account Form, Overland Park Tax Exempt Certificate and the Sales Tax Exemption Form ST-28B is required to be submitted for each control center.

Task No. 26a - Coordinate Compressed Natural Gas (CNG) Service for Traffic Signals

Top

If applicable, begin Natural Gas Service Address Procedures for CNG generators.

Task No. 26b - Coordinate Removal of Streetlights Purchased from Evergy

Top

If applicable, begin the Removal of Existing Streetlight Procedure for streetlights that were purchased from Evergy (KCP&L).

Task No. 27 - Schedule Field Check Meeting

Top

The Project Manager shall schedule the Field Check meeting. Representatives of all funding sources are to be invited. The City Engineer/City Traffic Engineer or their designated representatives will attend all meetings. Prior to Field Check Meeting, coordinate with Engineering Services for development projects permitted in the area.

Exhibit No. II-7e is a meeting sign in sheet.

Field check will be conducted at a pre-determined location. The Consultant or the City will provide a set of plans for field check. BLP will review comments and will discuss any necessary actions with the City and the Consultant. After the field check meeting the consultant or the City will distribute minutes and provide BLP with a response to the issues identified/discussed in the meeting.

After field check plans have been received by BLP, a Field Check Report will be developed and provided to the City, Consultant and other necessary parties.

During the site review/field check meeting it should be determined if the proposed project will have a potential impact on rail facilities. If it appears that work will be near or within railroad right-of way, the LPA will coordinate with the railroad to determine the need for flagging, liability insurance, agreements, and a possible diagnostic review.

Task No. 28 - Execute Official Agreement with KDOT

When the official KDOT agreement is received by the Project Manager, it is reviewed/approved by the Law Department and placed on the City Council agenda for consideration.

Exhibit No. II-28 is Official KDOT Utility Accomodation Policy/Agreement.

Compliance with KDOT's Non-Descrimination policies is required on all contracts. See Title VI Handbook for more information.

Task No. 29 - Continue Environmental Process

For more information see Chapter 4.0 Environmental of KDOT's LPA Project Development Manual.

Task No. 30 - Obtain Decision for Design Exception from KDOT

The Project Manager shall keep in close contact with BLP-KDOT, if a design exception was requested. Once the decision has been made, the results shall be disseminated to all interested and required parties.

Task No. 31 - Complete Public Interest Finding

Top

If the deviation from a standard practice is requested, the Project Manager shall submit a Proprietary Product Certification Form or a Public Interest Finding (PIF) to BLP explaining the need for the deviation and why it is in the public's best interest to allow it.

For detailed information regarding the use of proprietary products see FHWA's Construction Program Guide.

Task No. 32 - NHS Approval Procedure

Top

For projects on principal arterials, the Project Manager shall request special approval to administer a federally funded project on the National Highway System route, documenting the reason for the request and demonstrating that the City has successfully administered a non-NHS project. This request shall be submitted to the BLP for approval.

Task No. 33 - Submit Right-of-Way Plans/Legal Descriptions

Top

The Consultant/Project Manager shall submit this information on the date as established with the project schedule. The legal descriptions shall be provided in electronic format along with a written original sealed by a registered land surveyor in the State of Kansas. A tract map for each property shall accompany the legal descriptions. The tract map shall clearly identify each type of proposed taking. Also included with the submittal shall be a copy of all the title company information. At this time tract files should be created in project folder under \2-Preliminary Design\ROW and Easement Documents\Tract Files.

Exhibit No. II-33 is an example of legal descriptions and tract map.
Exhibit No. II-33a ia a Memorandum from the Register of Deeds, Johnson County, regarding legal description requirements for document indexing.
Exhibit No. II-33b is a Sample Template from the Register of Deeds, Johnson County, showing required format (margin & paper size) for recording documents.

All prepared documents must conform to the Register of Deeds requirements and filed electronically with Johnson County RTA. If rejected, the City is notified by RTA via email.

Exhibit No. II-33c is an example of rejection email from JoCo RTA.

(The rejection email is generated automatically and it applies to the whole package of documents submitted. Therefore the entire package is rejected even if only one tract has an error. It is up to the Project Engineer or Engineering Technician to figure out which one.)

GeekNotesIcon.png Note: In some instances Long Term Temporary Construction Easements (TCE) have been granted to the City during the development process. These existing TCEs are usually adjacent to thoroughfares. During the R/W Plan review the project technician is to check for any previously granted Long Term TCEs adjacent to the project. The TCEs can be viewed in ArcMap by adding "Easement and ROW" Data Layer from "Property" Data Group. Each easement in this layer is linked to a pdf image of the document by which that easement was acquired.

Task No. 34 - Hire Appraiser

Top

Project Manager shall form a Selection Committee and a qualification based selection process shall be used. Appraiser and Acquisition Agent may be acquired by a stand-alone RFQ process or inclusion as a component of the qualifications based selection process for the Design Professional/Consultant, or as may be required by applicable federal or state laws/regulations.

Exhibit No. II-34a is a list of City qualified appraisers.
Exhibit No. II-34b is a copy of City's Request for Qualifications (RFQ).
Exhibit No. II-34c is a sample summary of the project right-of-way and easement takings.
Exhibit No. II-34d is an Appraiser Agreement for fee under $10,000.
Exhibit No. II-34e is an Appraiser Agreement for fee over $10,000.
Exhibit No. II-34f is a sample Intra City memorandum to the Selection Committee.
Exhibit No. II-34g is a sample Proposal for Appraisal.
Exhibit No. II-34h is a sample of ranking sheet.

See FHWA's Real Estate Acquisition Guide For Local Public Agencies for information that will be necessary when a project is started that requires the acquisition of real estate and receives any Federal funding.

Exhibit No. II-34i is a copy of Appraisal Review form.

LPA representatives, appraisers and acquisition contractors involved with the R/W acquisition process must be certified in accordance with the ROWCP requirements. Refer to Chapter 7.0 Right of Way of KDOT's LPA Project Development Manual for additional information.

Task No. 35 - Prepare R/W and Easement Documents

Top

The Project Manager will coordinate with the Contract Specialist assigned to the project the preparation of the various documents necessary for the takings required to construct the project.

The following is the list of the most commonly used documents:

The following documents are shown for information only and will be generated by the City of Overland Park:

All prepared right-of-way and easement documents must conform to the Register of Deeds requirements. See Phase II, Task No. 33 for exhibits.

Task No. 36 - Schedule Second Public Information Meeting

Top

The purpose of this meeting is to present the Right of Way plans to the citizens. For KDOT projects the Notice of Public Information Meeting must be published in the Kansas Register and The Legal Record.

See Phase II, Task No. 15 for list of invites.

Exhibit No. II-36 is an example Invitation Letter to property owners.
Exhibit No. II-36a is an example Notice of Public Information Meeting.
Exhibit No. II-36b is a public meeting sign in sheet.
Exhibit No. II-36c is a public meeting handout.
GeekNotesIcon.png Note: This and all subsequent Public Information Meeting notices should ask if participants need a language interpreter or a hearing assistance device and a phone number. All meeting rooms shall be ADA accessible. The KDOT Equal Opportunity and Civil Rights Information brochure in English and Spanish regarding equal opportunity contracting are to be made available at all public meetings.

For those who wish to use a Blue Valley School District facility for the public meeting, an on-line Facility Rental Reservation Request is available. Once the request is submitted, the BVSD Facility Scheduling Office will send a confirmation if the requested space is available.

All Phase II Exhibits