Phase IV Checklist
City of Overland Park, Kansas
Public Works Department
Project Procedures Manual Checklist
Phase IV - Pre-construction (Letting Process-KDOT)
Project Number/Name/Description____________________________________________________________
______________________________________________________________________________________
City Project Engineer/Manager______________________________________________________________
Consultant - Staff Design___________________________________________________________________
Engineer's construction cost estimate_________________________________________________________
Bid Opening Date________________________________________________________________________
Project Schedule_________________________________________________________________________
Date Initial Task No. Resp. Task Description
____ ____ 1 CO/PE Complete Plans, Specification and Estimate
____ ____ 2 PM Distribute Material Testing Proposals
____ ____ 3 CS Set Bid Opening Date - Schedule Room
____ ____ 4 CS Publish Legal Advertisement
____ ____ 5 CO/AA Notice to Contractors/DBE Firms
____ _____ 6 CO/PE Distribute Plans, Contract Documents & Estimates
____ ____ 7 PM Conduct Pre-Bid Conference
____ ____ 8 PM Determine Contractor Pre-Qualifications
____ ____ 9 CO/PE Prepare Contract Document/Addendum
____ ____ 10 CS Complete Bid Opening
____ ____ 11 CO/PE Complete Detailed Bid Tabulation
____ ____ 12 PM Determine/Approve Contractor Qualifications and Sub-Contractor Percentage
____ ____ 13 PM Determine DBE Involvement
____ ____ 14 PM/CS Evaluate Possible Contractor Collusion
____ ____ 15 PM Submit Project Cost Estimate to Finance Dept.
____ ____ 16 PM Submit Staff Recommendation for Contract Award
____ ____ 17 CS Award Contract by City Council
____ ____ 18 PM Receive Bid Approval from KDOT
____ ____ 19 PM Receive Concurrence and Award from KDOT
____ ____ 20 PM Submit Letting Summary Document to KDOT
Checklist is to be completed by the Project Manager for each task. The checklist is to be printed at the completion of each Phase and place on the left side of the project file. If a task in not applicable enter "N/A" and provide short explanation.