- 09:2809:28, 3 June 2020 diff hist +18 Phase VI - Retrospect →Task No. 1 - Procedures for Final Cost and Project Close Out
- 09:2809:28, 3 June 2020 diff hist +38 N File:Final Project Cost Memo.pdf Project Cost Memo to DPW current
- 09:2409:24, 3 June 2020 diff hist +18 Phase VI - Retrospect →Task No. 1 - Procedures for Final Cost and Project Close Out
- 09:2409:24, 3 June 2020 diff hist +38 N File:Cost Sheet from Finance.pdf Final Project Cost Sheet current
- 09:1009:10, 3 June 2020 diff hist −5 Phase V - Construction →Task No. 25 - Submit Construction Summary Document to KDOT
- 09:1009:10, 3 June 2020 diff hist +99 Phase V - Construction →Task No. 25 - Submit Construction Summary Document to KDOT
- 09:0609:06, 3 June 2020 diff hist −7 Phase V - Construction →Task No. 15 - On-Going Change Orders
- 09:0509:05, 3 June 2020 diff hist +21 Phase V - Construction →Task No. 15 - On-Going Change Orders
- 09:0009:00, 3 June 2020 diff hist −1 Phase V - Construction →Task No. 24 - Submit Material Certification to KDOT
- 08:5808:58, 3 June 2020 diff hist +24 Phase V - Construction →Task No. 22 - Project Completion Certification & Scheduling of the Final Inspection Prior to Expiration of 2 Year Maintenance Bond
- 08:4708:47, 3 June 2020 diff hist +58 Phase V - Construction →Task No. 22 - Project Completion Certification & Scheduling of the Final Inspection Prior to Expiration of 2 Year Maintenance Bond
- 08:4408:44, 3 June 2020 diff hist +37 N File:Final Acceptance Letter.pdf Final Acceptance Letter current
- 08:4408:44, 3 June 2020 diff hist +34 Phase V - Construction →Task No. 22 - Project Completion Certification & Scheduling of the Final Inspection Prior to Expiration of 2 Year Maintenance Bond
- 08:4108:41, 3 June 2020 diff hist +37 N File:Final Acceptance Letter.docx Final Acceptance Letter current
- 08:3808:38, 3 June 2020 diff hist −2 Phase V - Construction →Task No. 22 - Project Completion Certification & Scheduling of the Final Inspection Prior to Expiration of 2 Year Maintenance Bond
- 08:3708:37, 3 June 2020 diff hist +37 Phase V - Construction →Task No. 22 - Project Completion Certification & Scheduling of the Final Inspection Prior to Expiration of 2 Year Maintenance Bond
- 08:3708:37, 3 June 2020 diff hist −29 Phase V - Construction →Task No. 21 - Receive Contractor Project Completion Certification
- 08:3608:36, 3 June 2020 diff hist +35 Phase V - Construction →Task No. 22 - Project Completion Certification & Scheduling of the Final Inspection Prior to Expiration of 2 Year Maintenance Bond
- 08:3508:35, 3 June 2020 diff hist +54 N File:Certificate of Engineer word.docx Certificate of Engineer as to Completion current
- 08:3108:31, 3 June 2020 diff hist +29 Phase V - Construction →Task No. 21 - Receive Contractor Project Completion Certification
- 08:3008:30, 3 June 2020 diff hist +54 N File:Certificate of Engineer.pdf Certificate of Engineer as to Completion current
2 June 2020
- 15:4815:48, 2 June 2020 diff hist −122 Phase V - Construction →Task No. 21 - Receive Contractor Project Completion Certification
- 15:3615:36, 2 June 2020 diff hist −2 Phase V - Construction →Task No. 21 - Receive Contractor Project Completion Certification
- 15:3515:35, 2 June 2020 diff hist +94 Phase V - Construction →Task No. 21 - Receive Contractor Project Completion Certification
- 15:2715:27, 2 June 2020 diff hist −1 Phase V - Construction →Task No. 20 - Send Letter to Owners Regarding Sod Care, etc.
- 15:2615:26, 2 June 2020 diff hist −14 Phase V - Construction →Task No. 20 - Send Letter to Owners Regarding Sod Care, etc.
- 15:2515:25, 2 June 2020 diff hist −3 Phase V - Construction →Task No. 20 - Send Letter to Owners Regarding Sod Care, etc.
- 15:2415:24, 2 June 2020 diff hist +7 Phase V - Construction →Task No. 20 - Send Letter to Owners Regarding Sod Care, etc.
- 15:2415:24, 2 June 2020 diff hist +231 Phase V - Construction →Task No. 20 - Send Letter to Owners Regarding Sod Care, etc.
- 15:0015:00, 2 June 2020 diff hist +16 Phase V - Construction →Task No. 15 - On-Going Change Orders
- 15:0015:00, 2 June 2020 diff hist +49 N File:CO Transmittal Letter.pdf Transmittal Letter for Change Order current
- 14:5414:54, 2 June 2020 diff hist +6 Phase V - Construction →Task No. 15 - On-Going Change Orders
- 14:4314:43, 2 June 2020 diff hist +6 Phase V - Construction →Task No. 15 - On-Going Change Orders
- 13:1513:15, 2 June 2020 diff hist +19 Phase V - Construction →Task No. 16 - On-Going Construction Administration
- 13:1513:15, 2 June 2020 diff hist +38 N File:Progress Meeting Minutes.pdf Progress Meeting Minutes current
- 13:1213:12, 2 June 2020 diff hist +18 Phase V - Construction →Task No. 16 - On-Going Construction Administration
- 13:1213:12, 2 June 2020 diff hist +37 N File:Progress Meeting Agenda.pdf Progress Meeting Agenda current
- 12:4312:43, 2 June 2020 diff hist 0 Phase IV - Pre-Construction →Task No. 2 - Selection of Material Testing Firm
- 12:4112:41, 2 June 2020 diff hist 0 File:IV-2a.docx Irina Idelson uploaded a new version of File:IV-2a.docx
- 11:0611:06, 2 June 2020 diff hist −8 Phase II - Preliminary Design →Task No. 36 - Schedule Second Public Information Meeting
- 11:0611:06, 2 June 2020 diff hist +36 N File:Public Meeting Handout.pdf Public Meeting Handout current
- 10:5810:58, 2 June 2020 diff hist −6 Phase II - Preliminary Design →Task No. 36 - Schedule Second Public Information Meeting
- 10:2210:22, 2 June 2020 diff hist −2 Phase II - Preliminary Design →Task No. 34 - Hire Appraiser
- 10:2010:20, 2 June 2020 diff hist −22 Phase II - Preliminary Design →Task No. 34 - Hire Appraiser
- 07:5007:50, 2 June 2020 diff hist +14 Phase II - Preliminary Design →Task No. 34 - Hire Appraiser
- 07:4807:48, 2 June 2020 diff hist +55 N File:Summary of takings.pdf Summary of Right-of-Way/Easements takings current
- 07:3807:38, 2 June 2020 diff hist +36 Phase II - Preliminary Design →Task No. 34 - Hire Appraiser
- 07:3407:34, 2 June 2020 diff hist +16 Phase II - Preliminary Design →Task No. 34 - Hire Appraiser
- 07:3307:33, 2 June 2020 diff hist −8 Phase II - Preliminary Design →Task No. 34 - Hire Appraiser
- 07:3207:32, 2 June 2020 diff hist 0 Phase II - Preliminary Design →Task No. 34 - Hire Appraiser