- 11:40, 1 November 2019 diff hist −31 Phase IV - Pre-Construction →Task No. 7 - Conduct Pre-Bid Conference
- 11:37, 1 November 2019 diff hist +92 Phase IV - Pre-Construction →Task No. 7 - Conduct Pre-Bid Conference
- 11:26, 1 November 2019 diff hist +29 Phase IV - Pre-Construction →Task No. 7 - Conduct Pre-Bid Conference
- 11:25, 1 November 2019 diff hist +1 Phase IV - Pre-Construction →Task No. 7 - Conduct Pre-Bid Conference
- 11:25, 1 November 2019 diff hist 0 Phase IV - Pre-Construction →Task No. 7 - Conduct Pre-Bid Conference
- 11:25, 1 November 2019 diff hist +39 Phase IV - Pre-Construction →Task No. 7 - Conduct Pre-Bid Conference
- 11:23, 1 November 2019 diff hist +32 N File:IV-7b pre-bid sign in sheet.doc Pre-Bid Conference Sign in Sheet current
- 11:11, 1 November 2019 diff hist +31 Phase IV - Pre-Construction →Task No. 7 - Conduct Pre-Bid Conference
- 11:10, 1 November 2019 diff hist +25 N File:IV-7 PreBid Agenda.pdf Pre-Bid Conference Agenda current
- 10:56, 1 November 2019 diff hist −348 Phase IV - Pre-Construction →Task No. 6 - Distribute Plans, Contract Documents and Estimate
- 10:53, 1 November 2019 diff hist −6 Phase IV - Pre-Construction →Task No. 4 - Publish Legal Advertisement
- 10:14, 1 November 2019 diff hist 0 File:Blp-memo-03-12.pdf Irina Idelson uploaded a new version of "File:Blp-memo-03-12.pdf" current
- 09:01, 1 November 2019 diff hist 0 Phase III - Final Design →Task No. 22 - Confirm Construction Engineering Responsibility
- 08:51, 1 November 2019 diff hist −2 Phase III - Final Design →Task No. 19 - Receive Obligation of Funds from KDOT
- 08:50, 1 November 2019 diff hist +58 Phase III - Final Design →Task No. 19 - Receive Obligation of Funds from KDOT
- 08:49, 1 November 2019 diff hist +38 N File:III-19 Obligation of Funds Authority to Admin.pdf Letter from KDOT - Obligation of Funds current
- 16:26, 31 October 2019 diff hist +30 Phase III - Final Design →Task No. 12 - Prepare Engineer’s Cost Estimate
- 16:24, 31 October 2019 diff hist +22 N File:Engineer's Cost Estimate Final Plans.pdf Cost Estimate - Signed current
- 16:10, 31 October 2019 diff hist +37 Phase III - Final Design →Task No. 19 - Receive Obligation of Funds from KDOT
- 16:01, 31 October 2019 diff hist +1 Phase III - Final Design →Task No. 17 - Complete Utility Relocations
- 16:01, 31 October 2019 diff hist +150 Phase III - Final Design →Task No. 17 - Complete Utility Relocations
- 15:51, 31 October 2019 diff hist +2 Phase III - Final Design →Task No. 13 - Prepare Design Summary Document
- 15:51, 31 October 2019 diff hist +1 Phase III - Final Design →Task No. 13 - Prepare Design Summary Document
- 15:50, 31 October 2019 diff hist 0 File:III-13a design summary document.pdf Irina Idelson uploaded a new version of "File:III-13a design summary document.pdf" current
- 15:48, 31 October 2019 diff hist +18 Phase III - Final Design →Task No. 13 - Prepare Design Summary Document
- 15:46, 31 October 2019 diff hist +28 N File:III-13a design summary document.pdf Design Summary Document - OP
- 15:25, 31 October 2019 diff hist +14 Phase III - Final Design →Task No. 13 - Prepare Design Summary Document
- 15:23, 31 October 2019 diff hist +33 N File:Design Summary Document memo.pdf Design Summary Document memo_KDOT current
- 15:16, 31 October 2019 diff hist +11 Phase III - Final Design →Task No. 14 - Submit PS&E Package
- 15:12, 31 October 2019 diff hist +31 N File:III-14 Request for Obligation.pdf Request for Obligation of Funds
- 14:13, 31 October 2019 diff hist +17 Phase III - Final Design →Task No. 12 - Prepare Engineer’s Cost Estimate
- 08:17, 31 October 2019 diff hist +204 Phase III - Final Design →For KDOT (Federally Funded) projects, the City’s Standard Contract Documents shall be supplemented with the following required contract provisions:
- 16:28, 30 October 2019 diff hist −10 Phase III - Final Design →Task No. 11 - Submit Contract Documents and Insurance
- 15:08, 30 October 2019 diff hist −4 Phase III - Final Design →Task No. 9 - Submit Final Check Plans for Review
- 16:12, 29 October 2019 diff hist +1 Phase III - Final Design →Task No. 4 - Complete NEPA Documentation
- 16:33, 28 October 2019 diff hist +1 Phase II - Preliminary Design →Task No. 36 - Schedule Second Public Information Meeting
- 16:02, 28 October 2019 diff hist −1 Phase II - Preliminary Design →Task No. 28 - Execute Official Agreement with KDOT
- 16:00, 28 October 2019 diff hist +41 Phase II - Preliminary Design →Task No. 28 - Execute Official Agreement with KDOT
- 15:49, 28 October 2019 diff hist +32 Phase II - Preliminary Design →Task No. 27 - Schedule Field Check Meeting
- 15:18, 28 October 2019 diff hist −32 Phase II - Preliminary Design →Task No. 26a - Coordinate Compressed Natural Gas (CNG) Service for Traffic Signals
- 14:51, 28 October 2019 diff hist +5 Phase II - Preliminary Design →Task No. 24 - Submit Required Permit Applications
- 14:34, 28 October 2019 diff hist +37 Phase II - Preliminary Design →Task No. 24 - Submit Required Permit Applications
- 14:22, 28 October 2019 diff hist +6 Phase II - Preliminary Design →Task No. 24 - Submit Required Permit Applications
- 13:29, 28 October 2019 diff hist +24 Phase II - Preliminary Design →Task No. 15 - Schedule First Public Information Meeting
- 13:28, 28 October 2019 diff hist +28 N File:Public Meeting Sign-In Sheet .docx Public Meeting Sign-In Sheet current
- 13:07, 28 October 2019 diff hist −13 Phase II - Preliminary Design →Task No. 13 - Conduct Field Surveys
- 13:06, 28 October 2019 diff hist +30 N File:Pre-survey letter.pdf Pre-survey letter to residents current
- 14:27, 25 October 2019 diff hist −15 Phase V - Construction →Task No. 12 - On-Going Inspections
- 14:25, 25 October 2019 diff hist +30 N File:PW ESC Inspection Report Final.pdf Final PW ESC Inspection Report current
- 14:23, 25 October 2019 diff hist −15 Phase V - Construction →Task No. 12 - On-Going Inspections