- 15:36, 11 September 2019 diff hist +6 Phase V - Construction →Task No. 12 - On-Going Inspections
- 15:34, 11 September 2019 diff hist +30 N File:SWPPP-ConstructionSiteIntspectionReport-Final.pdf Final PW ESC Inspection Report current
- 15:33, 11 September 2019 diff hist +18 Phase V - Construction →Task No. 12 - On-Going Inspections
- 15:31, 11 September 2019 diff hist +24 N File:SWPPP-ConstructionSiteIntspectionReport.pdf PW ESC Inspection Report current
- 15:29, 11 September 2019 diff hist +46 Phase V - Construction →Task No. 7 - Schedule Pre-Construction Conference/Project Sign Confirmation
- 15:07, 11 September 2019 diff hist +31 N File:SWPPP-Contractor'sCertificationForm.pdf Contractor's Certification Form current
- 14:13, 3 September 2019 diff hist +12 Phase IV - Pre-Construction →Task No. 5 - Notice to Contractors/DBE Firms
- 14:12, 3 September 2019 diff hist +50 N File:IV-5l Plan Rooms.docx List of Plan Rooms associated with DBE Contractors
- 13:28, 3 September 2019 diff hist 0 File:IV-5l.docx Irina Idelson uploaded a new version of "File:IV-5l.docx"
- 11:20, 3 September 2019 diff hist 0 File:IV-5l.docx Irina Idelson uploaded a new version of "File:IV-5l.docx"
- 11:19, 3 September 2019 diff hist 0 File:IV-5j.docx Irina Idelson uploaded a new version of "File:IV-5j.docx"
- 11:17, 3 September 2019 diff hist 0 File:IV-5i.docx Irina Idelson uploaded a new version of "File:IV-5i.docx"
- 11:17, 3 September 2019 diff hist 0 File:IV-5h.docx Irina Idelson uploaded a new version of "File:IV-5h.docx"
- 11:15, 3 September 2019 diff hist 0 File:IV-5g.docx Irina Idelson uploaded a new version of "File:IV-5g.docx"
- 11:14, 3 September 2019 diff hist 0 File:IV-5f.docx Irina Idelson uploaded a new version of "File:IV-5f.docx"
- 11:13, 3 September 2019 diff hist 0 File:IV-5e.docx Irina Idelson uploaded a new version of "File:IV-5e.docx"
- 11:12, 3 September 2019 diff hist 0 File:IV-5d.docx Irina Idelson uploaded a new version of "File:IV-5d.docx"
- 11:11, 3 September 2019 diff hist 0 File:IV-5c.docx Irina Idelson uploaded a new version of "File:IV-5c.docx"
- 11:09, 3 September 2019 diff hist 0 File:IV-5b.docx Irina Idelson uploaded a new version of "File:IV-5b.docx"
- 11:08, 3 September 2019 diff hist 0 File:IV-5a.docx Irina Idelson uploaded a new version of "File:IV-5a.docx"
- 11:04, 3 September 2019 diff hist 0 File:II-3o.xlsx Irina Idelson uploaded a new version of "File:II-3o.xlsx"
- 11:04, 30 August 2019 diff hist +43 Phase I - Vision →Task 14 - Receive Project Authorization from KDOT. Begin Environmental Process.
- 11:02, 30 August 2019 diff hist +28 N File:Project Authorization Packet.pdf Project Authorization Packet current
- 10:44, 30 August 2019 diff hist +37 Phase I - Vision →Task 13 - Submit KDOT Form 1302 for Project Request. Submit City's Request to Administer the Project
- 10:40, 30 August 2019 diff hist +86 N File:KDOT transmittal letter.docx KDOT Transmittal Letter - project programming request, Schedule, Request to administer current
- 10:32, 30 August 2019 diff hist −61 Phase I - Vision →Task 13 - Submit KDOT Form 1302 for Project Request. Submit City's Request to Administer the Project
- 10:32, 30 August 2019 diff hist +89 Phase I - Vision →Task 13 - Submit KDOT Form 1302 for Project Request. Submit City's Request to Administer the Project
- 10:30, 30 August 2019 diff hist +22 N File:RupisCity Admin.pdf Rupis Project Schedule current
- 10:29, 30 August 2019 diff hist +6 Phase I - Vision →Task 13 - Submit KDOT Form 1302 for Project Request. Submit City's Request to Administer the Project
- 10:28, 30 August 2019 diff hist +2 Phase I - Vision →Task 13 - Submit KDOT Form 1302 for Project Request. Submit City's Request to Administer the Project
- 10:28, 30 August 2019 diff hist +92 Phase I - Vision →Task 13 - Submit KDOT Form 1302 for Project Request. Submit City's Request to Administer the Project
- 10:25, 30 August 2019 diff hist +27 N File:RupisCity Admin-form.xls Rupis Project Schedule form current
- 08:31, 30 August 2019 diff hist −78 Phase I - Vision →Task 13 - Submit KDOT Form 1302 for Project Request. Submit City's Request to Administer the Project
- 08:30, 30 August 2019 diff hist +59 Phase I - Vision →Task 13 - Submit KDOT Form 1302 for Project Request. Submit City's Request to Administer the Project
- 08:25, 30 August 2019 diff hist +14 N File:Form 1302-revised 2018.xlsx KDOT Form 1302 current
- 08:24, 30 August 2019 diff hist +48 Phase I - Vision →Task 13 - Submit KDOT Form 1302 for Project Request. Submit City's Request to Administer the Project
- 08:05, 30 August 2019 diff hist −17 Phase I - Vision →Task 13 - Submit KDOT Form 1302 for Project Request. Submit City's Request to Administer the Project
- 07:48, 30 August 2019 diff hist +41 Phase I - Vision →Task 13 - Submit KDOT Form 1302 for Project Request. Submit City's Request to Administer the Project
- 15:58, 29 August 2019 diff hist +32 Phase V - Construction →Task No. 16 - On-Going Construction Administration
- 15:55, 29 August 2019 diff hist +32 Phase I - Vision →Task 11 - Execute Other Agency Agreements
- 15:52, 29 August 2019 diff hist +20 N File:Staff Billing Report.pdf Staff Billing Report current
- 15:32, 29 August 2019 diff hist +53 Phase I - Vision →Task 11 - Execute Other Agency Agreements
- 15:29, 29 August 2019 diff hist +40 N File:Executed Construction Agreement IC-10-055.pdf Executed SMAC Agreement for construction current
- 15:25, 29 August 2019 diff hist +46 Phase I - Vision →Task 11 - Execute Other Agency Agreements
- 14:50, 29 August 2019 diff hist +34 N File:Executed Design Agreement IC-10-055.pdf Executed SMAC Agreement for design current
- 12:18, 29 August 2019 diff hist +16 Phase I - Vision →Task 2 - Prepare Feasibility Report
- 12:13, 29 August 2019 diff hist +60 N File:Stormwater improvements policy and procedures.pdf Public Works Policy and Procedures - Stormwater Improvements current
- 12:09, 29 August 2019 diff hist −300 Phase I - Vision →Task 2 - Prepare Feasibility Report
- 12:06, 29 August 2019 diff hist +7 Phase I - Vision →Task 2 - Prepare Feasibility Report
- 12:05, 29 August 2019 diff hist +42 N File:ID Petition.pdf Petition form for the Improvement District