User contributions for Joe Archer
Results for Joe Archer talk block log uploads logs
A user with 1,123 edits. Account created on 6 April 2010.
22 September 2015
- 14:3114:31, 22 September 2015 diff hist +50 Phase IV - Pre-Construction →Task No. 8 - Determine Contractor Qualifications
31 August 2015
- 07:4207:42, 31 August 2015 diff hist 0 File:III-11a-10a Table of Contents KDOT.docx Jearcher uploaded a new version of "File:III-11a-10a Table of Contents KDOT.docx"
- 07:4007:40, 31 August 2015 diff hist 0 File:III-11a-6a Notice to Bidders KDOT.docx Jearcher uploaded a new version of "File:III-11a-6a Notice to Bidders KDOT.docx"
- 07:3807:38, 31 August 2015 diff hist 0 File:III-11a-2a Bid-KDOT.docx Jearcher uploaded a new version of "File:III-11a-2a Bid-KDOT.docx"
28 August 2015
- 14:5414:54, 28 August 2015 diff hist +21 N File:Restoration Agreement template.pdf Restoration Agreement
- 14:5314:53, 28 August 2015 diff hist −1 Phase II - Preliminary Design →Task No. 33 - Prepare R/W and Easement Documents
- 14:5214:52, 28 August 2015 diff hist +99 Phase II - Preliminary Design →Task No. 33 - Prepare R/W and Easement Documents
27 July 2015
- 07:2907:29, 27 July 2015 diff hist 0 File:Sample letter to KCP&L informing.docx Jearcher uploaded a new version of "File:Sample letter to KCP&L informing.docx" current
2 July 2015
- 09:5709:57, 2 July 2015 diff hist 0 File:Streetlighting removal procedure during design.pdf Jearcher uploaded a new version of "File:Streetlighting removal procedure during design.pdf"
1 June 2015
- 13:0713:07, 1 June 2015 diff hist 0 File:II-3o May 2015.xlsx Jearcher uploaded a new version of "File:II-3o May 2015.xlsx" current
29 May 2015
- 10:1210:12, 29 May 2015 diff hist +1 Phase IV - Pre-Construction →Task No. 2 - Selection of Material Testing Firm
12 May 2015
- 07:4907:49, 12 May 2015 diff hist +24 N File:II-3o May 2015.xlsx List of Consulting Firms
- 07:4907:49, 12 May 2015 diff hist −2 Phase II - Preliminary Design →Task No. 3 - Consultant Selection/Certification
11 May 2015
- 09:1609:16, 11 May 2015 diff hist 0 File:II-34a.docx Jearcher uploaded a new version of "File:II-32a.docx"
4 May 2015
- 15:2615:26, 4 May 2015 diff hist 0 File:II-3o April 2015.xlsx Jearcher uploaded a new version of "File:II-3o April 2015.xlsx" current
3 April 2015
- 07:3007:30, 3 April 2015 diff hist +68 N File:V-11c.docx transmittal letter to the contractor for completed submittals review current
- 07:2807:28, 3 April 2015 diff hist +2 Phase V - Construction →Task No. 11 - Complete Submittals Review
23 March 2015
- 07:0107:01, 23 March 2015 diff hist +60 N File:KCP&L Electrical Service Application.docx KCP&L Commercial & Industrial Electrical Service Application current
- 07:0007:00, 23 March 2015 diff hist −23 Phase II - Preliminary Design →Task No. 26 - Coordinate Electrical Service for Traffic Signals and Street Lighting
6 March 2015
- 16:0916:09, 6 March 2015 diff hist +1 Phase II - Preliminary Design →Task No. 20 - Distribute Plans to Utility Companies. Schedule Second Utility Meeting.
- 16:0416:04, 6 March 2015 diff hist +13 Phase II - Preliminary Design →Task No. 20 - Distribute Plans to Utility Companies. Schedule Second Utility Meeting.
- 16:0316:03, 6 March 2015 diff hist +65 N File:KCP&L DWG 130.1-12.pdf KCP&L clearance from signal or streetlight poles to utility lines current
- 16:0216:02, 6 March 2015 diff hist −7 Phase II - Preliminary Design →Task No. 20 - Distribute Plans to Utility Companies. Schedule Second Utility Meeting.
- 16:0116:01, 6 March 2015 diff hist −44 Phase II - Preliminary Design →Task No. 20 - Distribute Plans to Utility Companies. Schedule Second Utility Meeting.
- 16:0016:00, 6 March 2015 diff hist +168 Phase II - Preliminary Design →Task No. 20 - Distribute Plans to Utility Companies. Schedule Second Utility Meeting.
- 15:5615:56, 6 March 2015 diff hist +49 Phase II - Preliminary Design →Task No. 20 - Distribute Plans to Utility Companies. Schedule Second Utility Meeting.
- 15:3415:34, 6 March 2015 diff hist 0 File:V-19a.docx Jearcher uploaded a new version of "File:V-19a.docx"
- 15:3415:34, 6 March 2015 diff hist +31 N File:V-19b.docx Street Light Project Data Sheet
- 15:3215:32, 6 March 2015 diff hist +1 Phase V - Construction →Task No. 19 - Prepare Revisions/As-Built Plans
20 February 2015
- 10:4110:41, 20 February 2015 diff hist 0 File:V-7a contractor submittal checklist.xlsx Jearcher uploaded a new version of "File:V-7a contractor submittal checklist.xlsx"
19 February 2015
- 09:2909:29, 19 February 2015 diff hist +65 N File:IV-2h.docx Supplemental Agreement for Construction Material Testing Services
- 09:2909:29, 19 February 2015 diff hist +52 N File:IV-2g.docx Agreement for Construction Material Testing Services
- 09:2809:28, 19 February 2015 diff hist −55 Phase IV - Pre-Construction →Task No. 2 - Selection of Material Testing Firm
21 January 2015
- 16:2516:25, 21 January 2015 diff hist 0 File:V-7a contractor submittal checklist.xlsx Jearcher uploaded a new version of "File:V-7a contractor submittal checklist.xlsx"
15 January 2015
- 09:0909:09, 15 January 2015 diff hist +20 N File:Tract File Checklist.docx Tract File Checklist current
- 09:0809:08, 15 January 2015 diff hist +42 Phase II - Preliminary Design →Task No. 31 - Submit Right-of-Way Plans/Legal Descriptions
- 09:0309:03, 15 January 2015 diff hist +125 Phase II - Preliminary Design →Task No. 31 - Submit Right-of-Way Plans/Legal Descriptions
19 December 2014
- 10:0710:07, 19 December 2014 diff hist 0 File:IV-2a.docx Jearcher uploaded a new version of "File:IV-2a.docx"
1 December 2014
- 09:0609:06, 1 December 2014 diff hist 0 File:Sample letter to Black & McDonald holding.docx Jearcher uploaded a new version of "File:Sample letter to Black & McDonald holding.docx" current
- 09:0109:01, 1 December 2014 diff hist 0 File:Streetlighting removal procedure during construction.pdf Jearcher uploaded a new version of "File:Streetlighting removal procedure during construction.pdf"
- 08:5708:57, 1 December 2014 diff hist +50 N File:Sample letter to KCP&L informing.docx sample letter to KCP&L informing to adjust billing
- 08:5408:54, 1 December 2014 diff hist +76 N File:Sample letter to Black & McDonald holding.docx sample letter to Black & McDonald holding release of removal of streetlights
- 08:5208:52, 1 December 2014 diff hist +87 N File:Sample letter to Black & McDonald releasing.docx sample letter to Black & McDonald releasing the removal of streetlights to construction current
- 08:5108:51, 1 December 2014 diff hist +2 Phase V - Construction →Task No. 11a - Coordinate Removal of Streetlights Purchased from KCP&L
- 08:5008:50, 1 December 2014 diff hist +1 Phase V - Construction →Task No. 11a - Coordinate Removal of Streetlights Purchased from KCP&L
- 08:4108:41, 1 December 2014 diff hist 0 File:Streetlighting removal procedure during design.pdf Jearcher uploaded a new version of "File:Streetlighting removal procedure during design.pdf"
- 08:3808:38, 1 December 2014 diff hist +54 N File:Sample letter requesting streetlight removal proposals.docx sample letter requesting streetlight removal proposals current
- 08:3708:37, 1 December 2014 diff hist +1 Phase II - Preliminary Design →Task No. 26b - Coordinate Removal of Streetlights Purchased from KCP&L
20 November 2014
- 09:5709:57, 20 November 2014 diff hist +6 Phase II - Preliminary Design →Task No. 26a - Coordinate Compressed Natural Gas (CNG) Service for Traffic Signals
- 09:5609:56, 20 November 2014 diff hist +11 Phase II - Preliminary Design →Task No. 26a - Coordinate Compressed Natural Gas (CNG) Service for Traffic Signals