- 14:33, 7 August 2012 diff hist 0 File:II-34a.dot Irina Idelson uploaded a new version of "File:II-34a.dot": Notice of Public Information Meeting
- 14:29, 7 August 2012 diff hist 0 File:II-34 public meeting invitation.docx Irina Idelson uploaded a new version of "File:II-34 public meeting invitation.docx": Public Meeting Invitation
- 14:26, 7 August 2012 diff hist +27 Phase II - Preliminary Design →Task No. 34 - Schedule Second Public Information Meeting
- 14:25, 7 August 2012 diff hist +24 N File:II-34 public meeting invitation.docx Public Meeting Invitaion
- 14:15, 7 August 2012 diff hist +1 Phase II - Preliminary Design →Task No. 34 - Schedule Second Public Information Meeting
- 14:14, 7 August 2012 diff hist +84 Phase II - Preliminary Design →Task No. 34 - Schedule Second Public Information Meeting
- 14:11, 7 August 2012 diff hist −306 Phase II - Preliminary Design →Task No. 33 - Prepare R/W and Easement Documents
- 14:10, 7 August 2012 diff hist +1 Phase II - Preliminary Design →Task No. 33 - Prepare R/W and Easement Documents
- 14:10, 7 August 2012 diff hist +9 Phase II - Preliminary Design →Task No. 33 - Prepare R/W and Easement Documents
- 14:09, 7 August 2012 diff hist +9 Phase II - Preliminary Design →Task No. 31 - Submit R/W Plans/Legal Descriptions
- 14:09, 7 August 2012 diff hist +84 Phase II - Preliminary Design →Task No. 33 - Prepare R/W and Easement Documents
- 13:36, 7 August 2012 diff hist +21 Phase II - Preliminary Design →Task No. 32 - Hire Appraiser
- 13:35, 7 August 2012 diff hist +28 N File:II-32c summary of takings.xlsx Project Right-of-Way Takings
- 13:33, 7 August 2012 diff hist 0 File:II-33c.xlt Irina Idelson uploaded a new version of "File:II-33c.xlt": Project Right-of-Way takings
- 13:11, 7 August 2012 diff hist +6 Phase II - Preliminary Design →Task No. 31 - Submit R/W Plans/Legal Descriptions
- 11:57, 7 August 2012 diff hist −113 Phase II - Preliminary Design →Task No. 28 - Execute Official Agreement with KDOT
- 11:56, 7 August 2012 diff hist −140 Phase II - Preliminary Design →Task No. 28 - Execute Official Agreement with KDOT
- 11:56, 7 August 2012 diff hist +184 Phase II - Preliminary Design →Task No. 28 - Execute Official Agreement with KDOT
- 11:53, 7 August 2012 diff hist +38 Phase II - Preliminary Design →Task No. 28 - Execute Official Agreement with KDOT
- 11:49, 7 August 2012 diff hist +62 Phase II - Preliminary Design →Task No. 28 - Execute Official Agreement with KDOT
- 11:35, 7 August 2012 diff hist 0 File:II-15b.dot Irina Idelson uploaded a new version of "File:II-15b.dot": meeting sign in sheet
- 11:34, 7 August 2012 diff hist 0 File:II-15.dot Irina Idelson uploaded a new version of "File:II-15.dot": Public Meeting Invitation
- 16:29, 6 August 2012 diff hist 0 File:III-11a-4b Instructions to Bidders-Option B.docx Irina Idelson uploaded a new version of "File:III-11a-4b Instructions to Bidders-Option B.docx": Instructions to Bidders - Option B
- 16:28, 6 August 2012 diff hist 0 File:III-11a-4a Instructions to Bidders-Option A.docx Irina Idelson uploaded a new version of "File:III-11a-4a Instructions to Bidders-Option A.docx": Instructions to Bidders - Option A
- 16:27, 6 August 2012 diff hist 0 File:III-11a-3.docx Irina Idelson uploaded a new version of "File:III-11a-3.docx": General Condition for contracts over 50K
- 08:39, 6 August 2012 diff hist +11 Phase V - Construction →Task No. 19 - Prepare Revisions/As-Built Plans
- 08:38, 6 August 2012 diff hist +34 N File:As-built plan procedure flow chart August 2012).xlsx As-built plan procedure flow chart
- 14:22, 27 July 2012 diff hist +52 Phase II - Preliminary Design →Task No. 23 - Distribute Plans for Field Check
- 14:19, 27 July 2012 diff hist +352 Phase IV - Pre-Construction →Task No. 6 - Distribute Plans, Contract Documents and Estimate
- 10:44, 27 July 2012 diff hist 0 Phase VI - Retrospect →Task No. 8 - Receive Project Audit by KDOT
- 10:43, 27 July 2012 diff hist −99 Phase VI - Retrospect →Task No. 8 - Receive Project Audit by KDOT
- 08:30, 27 July 2012 diff hist +205 Phase VI - Retrospect →Task No. 8 - Receive Project Audit by KDOT
- 08:22, 27 July 2012 diff hist +21 Phase VI - Retrospect →Task No. 8 - Receive Project Audit by KDOT
- 16:37, 26 July 2012 diff hist +6 Phase II - Preliminary Design →Task No. 12 - Agency Agreements (if Applicable)
- 16:37, 26 July 2012 diff hist −1 Phase I - Vision →Task 11 - Execute Local Project Agreements
- 16:07, 26 July 2012 diff hist 0 File:III-11a-4b Instructions to Bidders-Option B.docx Irina Idelson uploaded a new version of "File:III-11a-4b Instructions to Bidders-Option B.docx": Instructions to Bidders - Option B
- 16:05, 26 July 2012 diff hist 0 File:III-11a-4a Instructions to Bidders-Option A.docx Irina Idelson uploaded a new version of "File:III-11a-4a Instructions to Bidders-Option A.docx": Instructions to Bidders - Option A
- 15:12, 26 July 2012 diff hist +2 Phase I - Vision →Task 13 Submit KDOT Form 1302 for Project Request. Submit City's Request to Administer the Project
- 14:55, 26 July 2012 diff hist −7 Phase II - Preliminary Design →Task No. 12 - Agency Agreements (if Applicable)
- 14:54, 26 July 2012 diff hist +1 Phase II - Preliminary Design →Task No. 12 - Agency Agreements (if Applicable)
- 14:53, 26 July 2012 diff hist +1 Phase II - Preliminary Design →Task No. 12 - Agency Agreement (if Applicable)
- 11:15, 26 July 2012 diff hist 0 File:II-32e.dot Irina Idelson uploaded a new version of "File:II-32e.dot": Appraiser Agreement over 10K current
- 11:14, 26 July 2012 diff hist 0 File:II-32d.dot Irina Idelson uploaded a new version of "File:II-32d.dot": Appraiser Agreement under 10K current
- 11:09, 26 July 2012 diff hist +1 Phase II - Preliminary Design →Task No. 27 - Schedule Field Check Meeting
- 11:06, 26 July 2012 diff hist 0 Phase II - Preliminary Design →Task No. 25 - Begin Field Check Plan Review
- 11:03, 26 July 2012 diff hist −5 Phase II - Preliminary Design →Task No. 24 - Submit Required Permit Applications
- 11:00, 26 July 2012 diff hist −1 Phase II - Preliminary Design →Task No. 24 - Submit Required Permit Applications
- 11:00, 26 July 2012 diff hist −1 Phase II - Preliminary Design →Task No. 24 - Submit Required Permit Applications
- 11:00, 26 July 2012 diff hist +2 Phase II - Preliminary Design →Task No. 24 - Submit Required Permit Applications
- 10:59, 26 July 2012 diff hist 0 Phase II - Preliminary Design →Task No. 24 - Submit Required Permit Applications