User contributions for Irina Idelson
Results for Irina Idelson talk block log uploads logs
A user with 4,241 edits. Account created on 9 April 2012.
24 July 2012
- 14:2814:28, 24 July 2012 diff hist +2 Phase I - Vision →Task 13 Submit KDOT Form 1302 for Project Request. Submit City's Request to Administer the Project
- 14:2714:27, 24 July 2012 diff hist +28 N File:I-15.doc Irina Idelson moved page File:I-15.doc to File:I-13c.doc current
- 14:2714:27, 24 July 2012 diff hist 0 m File:I-13c.doc Irina Idelson moved page File:I-15.doc to File:I-13c.doc current
- 14:2614:26, 24 July 2012 diff hist +275 Phase I - Vision →Task 13 Submit KDOT Form 1302 for Project Request. Submit City's Request to Administer the Project
- 14:2514:25, 24 July 2012 diff hist +49 Phase I - Vision →Task 13 Submit KDOT Form 1302 for Project Request
- 14:1314:13, 24 July 2012 diff hist +1 Phase I - Vision →Task 14 - Receive Project Authorization from KDOT. Begin Environmental Process.
- 14:0814:08, 24 July 2012 diff hist −30 Phase II - Preliminary Design →Task No. 3 - Consultant Selection/Certification
- 14:0714:07, 24 July 2012 diff hist 0 Phase II - Preliminary Design →Task No. 3 - Consultant Selection/Certification
- 14:0514:05, 24 July 2012 diff hist 0 File:I-11d.dot Irina Idelson uploaded a new version of "File:I-11d.dot": Interlocal Agreement
- 13:5913:59, 24 July 2012 diff hist +8 Phase I - Vision →Task 15 - Submit City Request to KDOT to Administer Federal Funded Projects
- 13:5613:56, 24 July 2012 diff hist +1 Phase I - Vision →Task 15 - Submit City Request to KDOT to Administer Federal Funded Projects
- 13:4713:47, 24 July 2012 diff hist +2 Phase I - Vision →Task 13 Submit KDOT Form 1302 for Project Request
- 13:2113:21, 24 July 2012 diff hist 0 Phase I - Vision →Task 12 - Obtain Priority Evaluation from KDOT
- 12:0412:04, 24 July 2012 diff hist −3 Phase I - Vision →Task 12 - Obtain Priority Evaluation from KDOT
- 12:0312:03, 24 July 2012 diff hist −9 Phase I - Vision →Task 15 - Submit City Request to KDOT to Administer Federal Funded Projects {{KDOT}}
- 12:0212:02, 24 July 2012 diff hist −9 Phase I - Vision →Task 14 - Receive Project Authorization from KDOT. Begin Environmental Process. {{KDOT}}
- 12:0212:02, 24 July 2012 diff hist −9 Phase I - Vision →Task 13 Submit KDOT Form 1302 for Project Request {{KDOT}}
- 12:0112:01, 24 July 2012 diff hist −6 Phase I - Vision →Task 11 - Execute Local Project Agreements
- 11:5911:59, 24 July 2012 diff hist +18 Phase I - Vision →Task 11 - Execute Local Project Agreements
- 11:5811:58, 24 July 2012 diff hist −9 Phase I - Vision →Task 12 - Obtain Priority Evaluation from KDOT {{KDOT}}
- 11:5711:57, 24 July 2012 diff hist −679 Phase I - Vision →Task 11 - Execute Local Project Agreement - City
- 11:5711:57, 24 July 2012 diff hist −422 Phase I - Vision →Task 11 Execute Local Project Agreement - SMAC
- 11:5611:56, 24 July 2012 diff hist +615 Phase I - Vision →Task 11 - Execute Local Project Agreements
- 11:5611:56, 24 July 2012 diff hist +361 Phase I - Vision →Task 11 - Execute Local Project Agreements
- 11:5511:55, 24 July 2012 diff hist +17 Phase I - Vision →Task 11 - Execute Local Project Agreement - CARS
- 11:5111:51, 24 July 2012 diff hist −3 Phase I Flow Chart No edit summary current
- 11:1711:17, 24 July 2012 diff hist 0 Phase I - Vision →Task 2 - Prepare Feasibility Report
23 July 2012
- 16:5416:54, 23 July 2012 diff hist 0 Phase V - Construction →Task No. 14 - On-Going Contractor Payments
- 16:5316:53, 23 July 2012 diff hist 0 N File:V-14c.xls No edit summary
- 16:1316:13, 23 July 2012 diff hist 0 File:V-14a.xlt Irina Idelson uploaded a new version of "File:V-14a.xlt": template with instructions for creating a monthly pay estimate
- 16:0716:07, 23 July 2012 diff hist 0 Phase VI - Retrospect →Task No. 9 - Receive Final Payment from KDOT
- 15:5315:53, 23 July 2012 diff hist +1 Phase VI - Retrospect →Task No. 6 and 7 - Complete Two-Year Inspection and Bond Release
- 15:5315:53, 23 July 2012 diff hist +30 N File:VI-7a .xlsx two year inspection punch list
- 15:5115:51, 23 July 2012 diff hist +1 Phase VI - Retrospect →Task No. 6 and 7 - Complete Two-Year Inspection and Bond Release
- 15:5015:50, 23 July 2012 diff hist 0 File:VI-7b.dot Irina Idelson uploaded a new version of "File:VI-7b.dot": letter to the contractor releasing the maintenance bond
- 15:4815:48, 23 July 2012 diff hist 0 File:VI-7a.dot Irina Idelson uploaded a new version of "File:VI-7a.dot": two year inspection punch list
- 15:2915:29, 23 July 2012 diff hist 0 Phase VI - Retrospect →Task No. 6 and 7 - Complete Two-Year Inspection and Bond Release
- 15:2415:24, 23 July 2012 diff hist +1 Phase VI - Retrospect →Task No. 5 - Update City Historical Records
- 15:2315:23, 23 July 2012 diff hist −389 Phase VI - Retrospect →Task No. 5 - Update City Historical Records
- 15:1315:13, 23 July 2012 diff hist +3 Phase VI - Retrospect →Task No. 4 - Complete Bond Sale
- 15:0715:07, 23 July 2012 diff hist 0 Phase VI - Retrospect →Task No. 3 - Conduct Post-Project Conference
- 15:0615:06, 23 July 2012 diff hist 0 Phase VI - Retrospect →Task No. 3 - Conduct Post-Project Conference
- 15:0415:04, 23 July 2012 diff hist −5 Phase VI - Retrospect →Task No. 3 - Conduct Post-Project Conference
- 15:0015:00, 23 July 2012 diff hist 0 Phase VI - Retrospect →Task No. 1 - Procedures for Final Cost and Project Close Out
- 14:5614:56, 23 July 2012 diff hist 0 Phase VI - Retrospect →Task No. 1 - Procedures for Final Cost and Project Close Out
- 14:2414:24, 23 July 2012 diff hist −40 Phase V - Construction →Task No. 28 - Approve Contractor Final Pay and Surety Release
- 14:2314:23, 23 July 2012 diff hist −40 Phase V - Construction →Task No. 26 - Receive Final Acceptance from KDOT
- 14:2214:22, 23 July 2012 diff hist +1 Phase V - Construction →Task No. 25 - Submit Construction Summary Document to KDOT
- 14:2214:22, 23 July 2012 diff hist −41 Phase V - Construction →Task No. 25 - Submit Construction Summary Document to KDOT
- 14:1814:18, 23 July 2012 diff hist 0 Phase V - Construction →Task No. 28 - Approve Contractor Final Pay and Surety Release