24 July 2012
- 10:5610:56, 24 July 2012 diff hist +361 Phase I - Vision →Task 11 - Execute Local Project Agreements
- 10:5510:55, 24 July 2012 diff hist +17 Phase I - Vision →Task 11 - Execute Local Project Agreement - CARS
- 10:5110:51, 24 July 2012 diff hist −3 Phase I Flow Chart No edit summary current
- 10:1710:17, 24 July 2012 diff hist 0 Phase I - Vision →Task 2 - Prepare Feasibility Report
23 July 2012
- 15:5415:54, 23 July 2012 diff hist 0 Phase V - Construction →Task No. 14 - On-Going Contractor Payments
- 15:5315:53, 23 July 2012 diff hist 0 N File:V-14c.xls No edit summary
- 15:1315:13, 23 July 2012 diff hist 0 File:V-14a.xlt Irina Idelson uploaded a new version of "File:V-14a.xlt": template with instructions for creating a monthly pay estimate
- 15:0715:07, 23 July 2012 diff hist 0 Phase VI - Retrospect →Task No. 9 - Receive Final Payment from KDOT
- 14:5314:53, 23 July 2012 diff hist +1 Phase VI - Retrospect →Task No. 6 and 7 - Complete Two-Year Inspection and Bond Release
- 14:5314:53, 23 July 2012 diff hist +30 N File:VI-7a .xlsx two year inspection punch list
- 14:5114:51, 23 July 2012 diff hist +1 Phase VI - Retrospect →Task No. 6 and 7 - Complete Two-Year Inspection and Bond Release
- 14:5014:50, 23 July 2012 diff hist 0 File:VI-7b.dot Irina Idelson uploaded a new version of "File:VI-7b.dot": letter to the contractor releasing the maintenance bond
- 14:4814:48, 23 July 2012 diff hist 0 File:VI-7a.dot Irina Idelson uploaded a new version of "File:VI-7a.dot": two year inspection punch list
- 14:2914:29, 23 July 2012 diff hist 0 Phase VI - Retrospect →Task No. 6 and 7 - Complete Two-Year Inspection and Bond Release
- 14:2414:24, 23 July 2012 diff hist +1 Phase VI - Retrospect →Task No. 5 - Update City Historical Records
- 14:2314:23, 23 July 2012 diff hist −389 Phase VI - Retrospect →Task No. 5 - Update City Historical Records
- 14:1314:13, 23 July 2012 diff hist +3 Phase VI - Retrospect →Task No. 4 - Complete Bond Sale
- 14:0714:07, 23 July 2012 diff hist 0 Phase VI - Retrospect →Task No. 3 - Conduct Post-Project Conference
- 14:0614:06, 23 July 2012 diff hist 0 Phase VI - Retrospect →Task No. 3 - Conduct Post-Project Conference
- 14:0414:04, 23 July 2012 diff hist −5 Phase VI - Retrospect →Task No. 3 - Conduct Post-Project Conference
- 14:0014:00, 23 July 2012 diff hist 0 Phase VI - Retrospect →Task No. 1 - Procedures for Final Cost and Project Close Out
- 13:5613:56, 23 July 2012 diff hist 0 Phase VI - Retrospect →Task No. 1 - Procedures for Final Cost and Project Close Out
- 13:2413:24, 23 July 2012 diff hist −40 Phase V - Construction →Task No. 28 - Approve Contractor Final Pay and Surety Release
- 13:2313:23, 23 July 2012 diff hist −40 Phase V - Construction →Task No. 26 - Receive Final Acceptance from KDOT
- 13:2213:22, 23 July 2012 diff hist +1 Phase V - Construction →Task No. 25 - Submit Construction Summary Document to KDOT
- 13:2213:22, 23 July 2012 diff hist −41 Phase V - Construction →Task No. 25 - Submit Construction Summary Document to KDOT
- 13:1813:18, 23 July 2012 diff hist 0 Phase V - Construction →Task No. 28 - Approve Contractor Final Pay and Surety Release
- 13:1713:17, 23 July 2012 diff hist −2 Phase V - Construction →Task No. 28 - Approve Contractor Final Pay and Surety Release
- 13:1713:17, 23 July 2012 diff hist −106 Phase V - Construction →Task No. 28 - Approve Contractor Final Pay and Surety Release
- 13:1613:16, 23 July 2012 diff hist −51 Phase V - Construction →Task No. 28 - Approve Contractor Final Pay and Surety Release
- 13:1213:12, 23 July 2012 diff hist −42 Phase V - Construction →Task No. 28 - Approve Contractor Final Pay and Surety Release
- 13:1113:11, 23 July 2012 diff hist −1 Phase V - Construction →Task No. 28 - Approve Contractor Final Pay and Surety Release
- 13:1113:11, 23 July 2012 diff hist +119 Phase V - Construction →Task No. 28 - Approve Contractor Final Pay and Surety Release
- 12:5412:54, 23 July 2012 diff hist +567 Phase V - Construction →Task No. 26 - Receive Final Acceptance from KDOT
- 12:1712:17, 23 July 2012 diff hist +1 Phase V - Construction →Task No. 25 - Submit Construction Summary Document to KDOT
- 12:1712:17, 23 July 2012 diff hist 0 Phase V - Construction →Task No. 25 - Submit Construction Summary Document to KDOT
- 12:1612:16, 23 July 2012 diff hist −6 Phase V - Construction →Task No. 25 - Submit Construction Summary Document to KDOT
- 12:1512:15, 23 July 2012 diff hist +716 Phase V - Construction →Task No. 25 - Submit Construction Summary Document to KDOT
- 10:5910:59, 23 July 2012 diff hist +4 Phase V - Construction →Task No. 24 - Submit Material Certification to KDOT
- 10:5810:58, 23 July 2012 diff hist +337 Phase V - Construction →Task No. 24 - Submit Material Certification to KDOT
- 10:5510:55, 23 July 2012 diff hist +19 Phase V - Construction →Task No. 24 - Submit Material Certification to KDOT
- 10:5310:53, 23 July 2012 diff hist +3 Phase V - Construction →Task No. 24 - Submit Material Certification to KDOT
- 10:5010:50, 23 July 2012 diff hist +50 Phase V - Construction →Task No. 24 - Submit Material Certification to KDOT
- 10:4910:49, 23 July 2012 diff hist +134 Phase V - Construction →Task No. 24 - Submit Material Certification to KDOT
- 10:2810:28, 23 July 2012 diff hist +228 Phase V - Construction →Task No. 24 - Submit Material Certification to KDOT
- 10:1610:16, 23 July 2012 diff hist 0 File:V-23.dot Irina Idelson uploaded a new version of "File:V-23.dot": transmittal letter to KDOT regarding completion of project
- 09:3309:33, 23 July 2012 diff hist −17 Phase V - Construction →Task No. 23 - Submit Notice of Acceptance to KDOT
- 09:3009:30, 23 July 2012 diff hist +3 Phase V - Construction →Task No. 22 - Project Completion Certification & Scheduling of the Final Inspection Prior to Expiration of 2 Year Maintenance Bond
- 09:2709:27, 23 July 2012 diff hist +32 Phase V - Construction →Task No. 22 - Project Completion Certification & Scheduling of the Final Inspection Prior to Expiration of 2 Year Performance Bond
- 09:1909:19, 23 July 2012 diff hist 0 File:V-20b.dot Irina Idelson uploaded a new version of "File:V-20b.dot": sample tree care letter