- 10:09, 24 April 2012 diff hist +50 Phase II - Preliminary Design →Task No. 20 - Distribute Plans to Utility Companies. Schedule Second Utility Meeting.
- 10:03, 24 April 2012 diff hist −92 Phase II - Preliminary Design →Task No. 20 - Distribute Plans to Utility Companies. Schedule Second Utility Meeting.
- 09:13, 24 April 2012 diff hist −919 Phase II - Preliminary Design
- 09:11, 24 April 2012 diff hist +867 Phase II - Preliminary Design
- 09:07, 24 April 2012 diff hist +55 Phase II - Preliminary Design →Task No. 20 - Distribute Plans
- 09:02, 24 April 2012 diff hist 0 Phase II - Preliminary Design →Task No. 21 - Distribute Plans
- 09:00, 24 April 2012 diff hist 0 Phase II - Preliminary Design →Task No. 18 - Submit Request for Design Exception tp KDOT
- 08:59, 24 April 2012 diff hist 0 Phase II - Preliminary Design
- 08:54, 24 April 2012 diff hist 0 Phase II - Preliminary Design →Task No. 23 - Submit Request for Design Exception to KDOT
- 08:48, 24 April 2012 diff hist 0 Phase II - Preliminary Design →Task No. 18 - Prepare Field Check Plans
- 08:39, 24 April 2012 diff hist −10 Phase II - Preliminary Design →Task No. 18 - Prepare Field Check Plans
- 08:38, 24 April 2012 diff hist −12 Phase I - Vision →Task 13 Submit KDOT Form 1302 for Project Request {{KDOT}}
- 08:34, 24 April 2012 diff hist +4 Phase II - Preliminary Design →Task No. 18 - Prepare Field Check Plans
- 08:27, 24 April 2012 diff hist +8 Phase I - Vision →Task 13 Submit KDOT Form 1302 for Project Request {{KDOT}}
- 08:20, 24 April 2012 diff hist 0 Phase II - Preliminary Design →Task No. 20 - Prepare Field Check Plans
- 08:18, 24 April 2012 diff hist 0 Phase II - Preliminary Design →Task No. 19 - Begin Geotechnical Report Process
- 08:15, 24 April 2012 diff hist 0 Phase II - Preliminary Design →Task No. 16 - Begin Title Report Process
- 08:14, 24 April 2012 diff hist +29 N File:II-18c.pdf moved File:II-18c.pdf to File:II-16c.pdf current
- 08:14, 24 April 2012 diff hist 0 m File:II-16c.pdf moved File:II-18c.pdf to File:II-16c.pdf
- 08:14, 24 April 2012 diff hist 0 Phase II - Preliminary Design →Task No. 18 - Begin Title Report Process
- 14:49, 23 April 2012 diff hist −2 Phase II - Preliminary Design →Task No. 15 - Schedule First Public Information Meeting
- 14:37, 23 April 2012 diff hist +5 Phase II - Preliminary Design →Task No. 15 - Schedule First Public Information Meeting
- 14:36, 23 April 2012 diff hist +24 Phase II - Preliminary Design →Task No. 15 - Schedule First Public Information Meeting
- 14:35, 23 April 2012 diff hist +51 Phase II - Preliminary Design →Task No. 15 - Schedule First Public Information Meeting
- 14:32, 23 April 2012 diff hist −2 Phase II - Preliminary Design →Task No. 17 - Schedule First Public Information Meeting
- 14:26, 23 April 2012 diff hist +155 Phase II - Preliminary Design →Task No. 14 - Continue Environmental Process
- 14:20, 23 April 2012 diff hist +748 Phase II - Preliminary Design →Task No. 16 - Begin Environmental Process
- 13:18, 23 April 2012 diff hist −40 Phase II - Preliminary Design →Task No. 13 - Conduct Field Surveys
- 13:16, 23 April 2012 diff hist +88 Phase II - Preliminary Design →Task No. 13 - Conduct Field Surveys
- 13:12, 23 April 2012 diff hist 0 Phase II - Preliminary Design →Task No. 12 - Agency Agreement (if Applicable)
- 11:42, 23 April 2012 diff hist +2 Phase II - Preliminary Design →Task No. 13 - Conduct Field Surveys
- 11:41, 23 April 2012 diff hist −4 Phase II - Preliminary Design →Task No. 15 - Conduct Field Surveys
- 11:34, 23 April 2012 diff hist 0 Phase II - Preliminary Design →Task No. 14 - Agency Agreement (if Applicable)
- 11:32, 23 April 2012 diff hist 0 Phase II - Preliminary Design →Task No. 13 - SMAC Preliminary Study
- 11:31, 23 April 2012 diff hist −4 Phase II - Preliminary Design →Task No. 10 - Standard Details
- 11:30, 23 April 2012 diff hist −7 Phase II - Preliminary Design →Task No. 12 - Standard Details
- 11:25, 23 April 2012 diff hist −1 Phase II - Preliminary Design →Task No. 11 - Design Criteria
- 11:23, 23 April 2012 diff hist −1 Phase II - Preliminary Design →Task No. 10 - Pre-Design Meeting
- 11:21, 23 April 2012 diff hist 0 Phase II - Preliminary Design →Task No. 7 - Schedule First Utility Meeting
- 11:20, 23 April 2012 diff hist +28 N File:II-9m.pdf moved File:II-9m.pdf to File:II-7m.pdf current
- 11:20, 23 April 2012 diff hist 0 m File:II-7n.pdf moved File:II-9m.pdf to File:II-7m.pdf
- 11:19, 23 April 2012 diff hist +28 N File:II-9l.pdf moved File:II-9l.pdf to File:II-7l.pdf current
- 11:19, 23 April 2012 diff hist +28 N File:II-9k.pdf moved File:II-9k.pdf to File:II-7k.pdf current
- 11:19, 23 April 2012 diff hist 0 m File:II-7l.pdf moved File:II-9k.pdf to File:II-7k.pdf
- 11:18, 23 April 2012 diff hist +28 N File:II-9j.pdf moved File:II-9j.pdf to File:II-7j.pdf current
- 11:18, 23 April 2012 diff hist 0 m File:II-7k.pdf moved File:II-9j.pdf to File:II-7j.pdf
- 11:17, 23 April 2012 diff hist +28 N File:II-9h.pdf moved File:II-9h.pdf to File:II-7h.pdf current
- 11:17, 23 April 2012 diff hist 0 m File:II-7i.pdf moved File:II-9h.pdf to File:II-7h.pdf
- 11:16, 23 April 2012 diff hist +28 N File:II-9g.pdf moved File:II-9g.pdf to File:II-7g.pdf current
- 11:16, 23 April 2012 diff hist 0 m File:II-7h.pdf moved File:II-9g.pdf to File:II-7g.pdf