- 11:32, 10 January 2019 diff hist +91 Phase II - Preliminary Design →Task No. 10 - Standard Details
- 11:31, 10 January 2019 diff hist +16 N File:Thoroughfare Interim Sections Jan-2019.pdf Interim Sections
- 11:31, 10 January 2019 diff hist +107 Phase II - Preliminary Design →Task No. 10 - Standard Details
- 11:29, 10 January 2019 diff hist +24 N File:Thoroughfare Ultimate 2-Lane Sections Jan-2019.pdf Ultimate 2-lane Sections
- 11:28, 10 January 2019 diff hist +121 Phase II - Preliminary Design →Task No. 10 - Standard Details
- 11:27, 10 January 2019 diff hist +31 N File:Thoroughfare Ultimate 4- and 3-Lane Sections Jan-2019.pdf Ultimate 4- and 3-lane Sections
- 11:25, 10 January 2019 diff hist +161 Phase II - Preliminary Design →Task No. 10 - Standard Details
- 17:21, 7 January 2019 diff hist −15 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 10:31, 7 January 2019 diff hist −285 Phase II - Preliminary Design →Task No. 18 - Submit Request for Design Exception to KDOT
- 10:29, 7 January 2019 diff hist −43 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 10:24, 7 January 2019 diff hist +40 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 10:17, 7 January 2019 diff hist +165 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 09:08, 7 January 2019 diff hist +639 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 10:07, 4 January 2019 diff hist +52 Phase II - Preliminary Design →Task No. 18 - Submit Request for Design Exception to KDOT
- 10:06, 4 January 2019 diff hist 0 N File:Design deviations.docx current
- 10:05, 4 January 2019 diff hist +53 Phase II - Preliminary Design →Task No. 18 - Submit Request for Design Exception to KDOT
- 10:01, 4 January 2019 diff hist 0 N File:Design exceptions.docx
- 09:59, 4 January 2019 diff hist +457 Phase II - Preliminary Design →Task No. 18 - Submit Request for Design Exception to KDOT
- 11:17, 2 January 2019 diff hist +1 Stop Sign Design Guidelines →Governing Document Reference: current
- 11:16, 2 January 2019 diff hist +12 Stop Sign Design Guidelines →Governing Document Reference:
- 11:10, 2 January 2019 diff hist −5 Stop Sign Design Guidelines →Governing Document Reference:
- 11:07, 2 January 2019 diff hist 0 Stop Sign Design Guidelines →Governing Document Reference:
- 11:07, 2 January 2019 diff hist +6 Stop Sign Design Guidelines →Governing Document Reference:
- 11:06, 2 January 2019 diff hist +102 Stop Sign Design Guidelines →Governing Document Reference:
- 11:04, 2 January 2019 diff hist +79 Stop Sign Design Guidelines →Governing Document Reference:
- 11:01, 2 January 2019 diff hist −54 Stop Sign Design Guidelines →Governing Document Reference:
- 10:52, 2 January 2019 diff hist +84 Stop Sign Design Guidelines →Governing Document Reference:
- 10:48, 2 January 2019 diff hist +8 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 10:32, 2 January 2019 diff hist +4 Phase IV - Pre-Construction →Task No. 2 - Selection of Material Testing Firm
- 10:30, 2 January 2019 diff hist +57 Phase IV - Pre-Construction →Task No. 2 - Selection of Material Testing Firm
- 10:28, 2 January 2019 diff hist +16 Phase III - Final Design →Task No. 22 - Confirm Construction Engineering Responsibility
- 09:51, 2 January 2019 diff hist +16 Phase II - Preliminary Design →Task No. 3 - Consultant Selection/Certification
- 07:30, 26 October 2018 diff hist 0 File:II-3o.xlsx Irina Idelson uploaded a new version of "File:II-3o.xlsx"
- 10:28, 10 October 2018 diff hist +186 Phase V - Construction →Task No. 16 - On-Going Construction Administration
- 15:47, 8 October 2018 diff hist +114 Phase III - Final Design →Task No. 11 - Submit Contract Documents and Insurance
- 15:42, 8 October 2018 diff hist +29 N File:III-11a-2c eBid Certification Form KDOT.docx Certification for eBid - KDOT current
- 15:36, 8 October 2018 diff hist 0 File:III-11a-6a Notice to Bidders KDOT.docx Irina Idelson uploaded a new version of "File:III-11a-6a Notice to Bidders KDOT.docx" current
- 15:33, 8 October 2018 diff hist 0 File:III-11a-10a Table of Contents KDOT.docx Irina Idelson uploaded a new version of "File:III-11a-10a Table of Contents KDOT.docx" current
- 15:26, 8 October 2018 diff hist 0 File:III-11a-6 2 eBid-Notice to Bidders.docx Irina Idelson uploaded a new version of "File:III-11a-6 2 eBid-Notice to Bidders.docx" current
- 15:21, 8 October 2018 diff hist 0 File:III-11a-6b Notice to Bidders-CDBG.docx Irina Idelson uploaded a new version of "File:III-11a-6b Notice to Bidders-CDBG.docx" current
- 10:01, 1 October 2018 diff hist 0 File:II-3o.xlsx Irina Idelson uploaded a new version of "File:II-3o.xlsx"
- 14:13, 25 September 2018 diff hist −1 Phase IV - Pre-Construction →Task No. 6 - Distribute Plans, Contract Documents and Estimate
- 14:11, 25 September 2018 diff hist +34 N File:IV-6 Engineers Estimate.docx A Template for Engineer's Estimate current
- 14:02, 25 September 2018 diff hist 0 File:V-14b cetificate of subcontract work and payment.xlsx Irina Idelson uploaded a new version of "File:V-14b cetificate of subcontract work and payment.xlsx" current
- 13:57, 25 September 2018 diff hist 0 File:V-14a Pay estimate with DBE.xlsx Irina Idelson uploaded a new version of "File:V-14a Pay estimate with DBE.xlsx" current
- 16:30, 24 September 2018 diff hist 0 File:II-3o.xlsx Irina Idelson uploaded a new version of "File:II-3o.xlsx"
- 08:18, 20 September 2018 diff hist −189 Phase V - Construction →Task No. 22 - Project Completion Certification & Scheduling of the Final Inspection Prior to Expiration of 2 Year Maintenance Bond
- 10:05, 17 September 2018 diff hist +55 Phase V - Construction →Task No. 14 - On-Going Contractor Payments
- 09:58, 17 September 2018 diff hist +60 N File:KDOT Form 1010LP.xlsx Certificate of Subcontract Work and Pavement - 2017 Revision current
- 08:41, 17 September 2018 diff hist +13 Phase V - Construction →Task No. 15 - On-Going Change Orders
- 16:08, 14 September 2018 diff hist +1 Phase V - Construction →Task No. 26 - Receive Final Acceptance from KDOT
- 16:07, 14 September 2018 diff hist −117 Phase V - Construction →Task No. 22 - Project Completion Certification & Scheduling of the Final Inspection Prior to Expiration of 2 Year Maintenance Bond
- 16:02, 14 September 2018 diff hist +2 Phase V - Construction →Task No. 5 - Complete Sales Tax Exemption Forms
- 16:01, 14 September 2018 diff hist −67 Phase V - Construction →Task No. 5 - Complete Sales Tax Exemption Forms
- 16:00, 14 September 2018 diff hist −41 Phase V - Construction →Task No. 21 - Receive Contractor Project Completion Certification
- 15:56, 14 September 2018 diff hist +1 Phase V - Construction →Task No. 20 - Send Letter to Owners Regarding Sod Care, etc.
- 15:55, 14 September 2018 diff hist +7 Phase V - Construction →Task No. 17 - Complete Final Inspection and Prepare a Punch List
- 15:47, 14 September 2018 diff hist +1 Phase V - Construction →Task No. 15 - On-Going Change Orders
- 15:47, 14 September 2018 diff hist +1 Phase V - Construction →Task No. 15 - On-Going Change Orders
- 15:46, 14 September 2018 diff hist +73 Phase V - Construction →Task No. 15 - On-Going Change Orders
- 15:44, 14 September 2018 diff hist +6 Phase V - Construction →Task No. 15 - On-Going Change Orders
- 15:41, 14 September 2018 diff hist +6 Phase V - Construction →Task No. 15 - On-Going Change Orders
- 15:34, 14 September 2018 diff hist +94 Phase V - Construction →Task No. 15 - On-Going Change Orders
- 15:28, 14 September 2018 diff hist −1 Phase V - Construction →Task No. 15 - On-Going Change Orders
- 15:22, 14 September 2018 diff hist 0 Phase V - Construction →Task No. 14 - On-Going Contractor Payments
- 15:22, 14 September 2018 diff hist +2 Phase V - Construction →Task No. 14 - On-Going Contractor Payments
- 15:14, 14 September 2018 diff hist −1 Phase V - Construction →Task No. 14 - On-Going Contractor Payments
- 15:13, 14 September 2018 diff hist −2 Phase V - Construction →Task No. 14 - On-Going Contractor Payments
- 15:11, 14 September 2018 diff hist +7 Phase V - Construction →Task No. 14 - On-Going Contractor Payments
- 15:05, 14 September 2018 diff hist 0 Phase V - Construction →Task No. 14 - On-Going Contractor Payments
- 15:02, 14 September 2018 diff hist +82 Phase V - Construction →Task No. 14 - On-Going Contractor Payments
- 14:53, 14 September 2018 diff hist −69 Phase V - Construction →Task No. 10 - Issue Notice to Proceed
- 14:44, 14 September 2018 diff hist +2 Phase V - Construction →Task No. 6 - Complete Material Testing Contracts
- 14:22, 14 September 2018 diff hist +9 Phase V - Construction →Task No. 5 - Complete Sales Tax Exemption Forms
- 14:18, 14 September 2018 diff hist +54 Phase V - Construction →Task No. 4 - Distribute Executed Contract Documents
- 14:13, 14 September 2018 diff hist −10 Phase V - Construction →Task No. 4 - Distribute Executed Contract Documents
- 14:08, 14 September 2018 diff hist −2 Phase III - Final Design →For KDOT (Federally Funded) projects, the City’s Standard Contract Documents shall be supplemented with the following required contract provisions:
- 13:52, 14 September 2018 diff hist +8 Phase III - Final Design →For KDOT (Federally Funded) projects, the City’s Standard Contract Documents shall be supplemented with the following required contract provisions:
- 13:49, 14 September 2018 diff hist −5 Phase III - Final Design →For KDOT (Federally Funded) projects, the City’s Standard Contract Documents shall be supplemented with the following required contract provisions:
- 13:43, 14 September 2018 diff hist +2 Phase III - Final Design →Task No. 9 - Submit Final Check Plans for Review
- 13:42, 14 September 2018 diff hist +47 Phase III - Final Design →Task No. 9 - Submit Final Check Plans for Review
- 13:40, 14 September 2018 diff hist −6 Phase III - Final Design →Task No. 8 - Acquire Right-of-Way / Easements - Submit KDOT Forms 1306 and 1304
- 13:35, 14 September 2018 diff hist +6 Phase III - Final Design →Task No. 8 - Acquire Right-of-Way / Easements - Submit KDOT Forms 1306 and 1304
- 13:33, 14 September 2018 diff hist −12 Phase III - Final Design →Task No. 5 - Begin Right-of-Way / Easement Negotiations
- 13:14, 14 September 2018 diff hist +3 Phase II - Preliminary Design →Task No. 33 - Submit Right-of-Way Plans/Legal Descriptions
- 13:13, 14 September 2018 diff hist +1 Phase II - Preliminary Design →Task No. 33 - Submit Right-of-Way Plans/Legal Descriptions
- 13:13, 14 September 2018 diff hist +55 Phase II - Preliminary Design →Task No. 33 - Submit Right-of-Way Plans/Legal Descriptions
- 10:39, 14 September 2018 diff hist −2 Phase II - Preliminary Design →Task No. 33 - Submit Right-of-Way Plans/Legal Descriptions
- 10:31, 14 September 2018 diff hist +6 Phase II - Preliminary Design →Task No. 31 - Complete Public Interest Finding
- 10:30, 14 September 2018 diff hist +129 Phase II - Preliminary Design →Task No. 31 - Complete Public Interest Finding
- 10:21, 14 September 2018 diff hist +47 Phase II - Preliminary Design →Task No. 25 - Begin Field Check Plan Review
- 10:16, 14 September 2018 diff hist −4 Phase II - Preliminary Design →Task No. 24 - Submit Required Permit Applications
- 10:15, 14 September 2018 diff hist +77 Phase II - Preliminary Design →Task No. 24 - Submit Required Permit Applications
- 10:08, 14 September 2018 diff hist +25 Phase II - Preliminary Design →Task No. 18 - Submit Request for Design Exception to KDOT
- 10:02, 14 September 2018 diff hist +49 Phase II - Preliminary Design →Task No. 3 - Consultant Selection/Certification
- 09:50, 14 September 2018 diff hist +47 Phase II - Preliminary Design →Task No. 13 - Conduct Field Surveys
- 09:33, 14 September 2018 diff hist −1 Phase II - Preliminary Design →Task No. 9 - Design Criteria
- 09:19, 14 September 2018 diff hist +17 Phase IV - Pre-Construction →Task No. 14 - Determine Disadvantaged Business Enterprises (DBE) Involvement
- 09:03, 14 September 2018 diff hist −58 Phase IV - Pre-Construction →Task No. 8 - Determine Contractor Qualifications - KDOT Projects
- 16:13, 13 September 2018 diff hist −3 Phase V - Construction →Task No. 7 - Schedule Pre-Construction Conference/Project Sign Confirmation