- 10:28, 2 January 2019 diff hist +16 Phase III - Final Design →Task No. 22 - Confirm Construction Engineering Responsibility
- 09:51, 2 January 2019 diff hist +16 Phase II - Preliminary Design →Task No. 3 - Consultant Selection/Certification
- 07:30, 26 October 2018 diff hist 0 File:II-3o.xlsx Irina Idelson uploaded a new version of "File:II-3o.xlsx"
- 10:28, 10 October 2018 diff hist +186 Phase V - Construction →Task No. 16 - On-Going Construction Administration
- 15:47, 8 October 2018 diff hist +114 Phase III - Final Design →Task No. 11 - Submit Contract Documents and Insurance
- 15:42, 8 October 2018 diff hist +29 N File:III-11a-2c eBid Certification Form KDOT.docx Certification for eBid - KDOT current
- 15:36, 8 October 2018 diff hist 0 File:III-11a-6a Notice to Bidders KDOT.docx Irina Idelson uploaded a new version of "File:III-11a-6a Notice to Bidders KDOT.docx" current
- 15:33, 8 October 2018 diff hist 0 File:III-11a-10a Table of Contents KDOT.docx Irina Idelson uploaded a new version of "File:III-11a-10a Table of Contents KDOT.docx" current
- 15:26, 8 October 2018 diff hist 0 File:III-11a-6 2 eBid-Notice to Bidders.docx Irina Idelson uploaded a new version of "File:III-11a-6 2 eBid-Notice to Bidders.docx" current
- 15:21, 8 October 2018 diff hist 0 File:III-11a-6b Notice to Bidders-CDBG.docx Irina Idelson uploaded a new version of "File:III-11a-6b Notice to Bidders-CDBG.docx" current
- 10:01, 1 October 2018 diff hist 0 File:II-3o.xlsx Irina Idelson uploaded a new version of "File:II-3o.xlsx"
- 14:13, 25 September 2018 diff hist −1 Phase IV - Pre-Construction →Task No. 6 - Distribute Plans, Contract Documents and Estimate
- 14:11, 25 September 2018 diff hist +34 N File:IV-6 Engineers Estimate.docx A Template for Engineer's Estimate current
- 14:02, 25 September 2018 diff hist 0 File:V-14b cetificate of subcontract work and payment.xlsx Irina Idelson uploaded a new version of "File:V-14b cetificate of subcontract work and payment.xlsx" current
- 13:57, 25 September 2018 diff hist 0 File:V-14a Pay estimate with DBE.xlsx Irina Idelson uploaded a new version of "File:V-14a Pay estimate with DBE.xlsx" current
- 16:30, 24 September 2018 diff hist 0 File:II-3o.xlsx Irina Idelson uploaded a new version of "File:II-3o.xlsx"
- 08:18, 20 September 2018 diff hist −189 Phase V - Construction →Task No. 22 - Project Completion Certification & Scheduling of the Final Inspection Prior to Expiration of 2 Year Maintenance Bond
- 10:05, 17 September 2018 diff hist +55 Phase V - Construction →Task No. 14 - On-Going Contractor Payments
- 09:58, 17 September 2018 diff hist +60 N File:KDOT Form 1010LP.xlsx Certificate of Subcontract Work and Pavement - 2017 Revision current
- 08:41, 17 September 2018 diff hist +13 Phase V - Construction →Task No. 15 - On-Going Change Orders